Madeira v. Affordable Housing Foundation, Inc.Madeira v. Affordable Housing Foundation, Inc.
MEMORANDUM DECISION AND ORDER DENYING THIRD-PARTY DEFENDANTS’ MOTION FOR NEW TRIAL AND THIRD-PARTY PLAINTIFFS’ MOTION FOR JUDGMENT NOTWITHSTANDING THE VERDICT
This is an action to recover damages for personal injuries sustained by plaintiff Jose Madeira in the course of his work on a construction site in Monroe, NY. The third-party action was thereafter commenced by Affordable Housing, the site owner, and Mountain Developers, the general contractor, for indemnification from plaintiffs employer Cleidson Silva d/b/a C & L Construction. Silva is covered by Preferred National Insurance, which was
The case was tried to a jury in two parts over the course of nine days. At the conclusion of Phase I, the jury found that defendants Affordable and Mountain had violated their duties under the “Scaffold Law,” New York Labor Law § 240(1), and returned a verdict in favor of plaintiff Jose Madeira for $638,671.63. No issues of negligence on third-party liability were submitted to the jury in Phase I; plaintiffs claim was limited to a § 240(1) “strict liability” claim, and the jury considered only that issue. In the second phase of the trial, the jury determined that Paulo Miranda had entered into an indemnification agreement (DX4) on behalf of C & L Construction, and determined that C & L Construction was 82% liable for Madeira’s accident and Mountain and Affordable were each 9% liable.
Third-party plaintiffs and third-party defendant Silva have both submitted post-trial motions for judgment notwithstanding the verdict pursuant to FRCP Rule 50(b). For the following reasons both motions are denied, without need for response from other parties. 1
Third-Party Plaintiffs’ Motion for A Judgment Notwithstanding the Verdict Pursuant to FRCP 50(b)
Affordable and Mountain assign four grounds for setting aside the jury verdict. They argue:
First, that the jury’s award of lost earnings to the plaintiff Jose Madeira was erroneous because he is an undocumented worker, and therefore ineligible for those damages;
Second, that the jury’s apportionment of fault was erroneous because there was no finding of negligence in the “liability” phase of the trial (i.e. Phase I) to support that apportionment;
Third, that the preclusion of proof of lack of insurance was erroneous as a matter of law because, notwithstanding the stipulation that Affordable and Mountain were not additional insureds, there was a breach of the insurance clause of the indemnity agreement;
Finally, that the Court erred in dismissing Preferred, because the third-party plaintiffs were entitled to a defense and indemnity.
1. Plaintiff’s Alien Status Does Not Deprive Him of His Right to Lost Earnings
Affordable and Mountain argue that, under the Supreme Court’s reasoning in
Hoffman Plastic v. NLRB,
This case involves a claim for relief under New York state law. No federal cause of action is asserted. Under
Erie R. Co. v. Tompkins,
Plaintiffs alien status does not prevent him from recovering compensatory damages for defendants’ violation of New York Labor Law.
See Public Admin. of Bronx County v. Equitable Life Assurance Society of U.S.,
As I instructed the jury, under New York law, plaintiffs alien status is relevant to determining whether lost earnings are appropriate and, if so, how much should be awarded.
See Cano,
Affordable and Mountain do not clearly indicate whether they challenge only the back pay award (the only issue in
Hoffman )
or also the front pay award. With respect to the front pay issue,
Hoffman
is irrelevant. The jury was told that it could consider plaintiffs alien status in determining whether he would have continued to work and whether that work would be in the United States or elsewhere. Plain
2. The Jury’s Apportionment of Fault was Supported by the Evidence
Affordable and Mountain argue that, because § 240(1) imposes strict liability, there was no finding of negligence in what they label the “liability” phase of the trial. That being so, they argue that C & L cannot seek to avoid indemnifying third-party plaintiffs on the ground that they were negligent.
This is incorrect. There was no finding of negligence in the first phase of the trial because negligence was irrelevant to plaintiffs claim against Affordable and Mountain under § 240(1). Affordable and Mountain could have been — and were— held liable to plaintiff irrespective of any negligence on their part. Negligence was, however, relevant to Phase II of the trial. The jury was, therefore, asked if Affordable or Mountain were negligent, and, if so, to apportion fault at the conclusion of Phase II.
The indemnification provision provides: “To the fullest extent permitted by law, Subcontractor shall indemnify and hold harmless the General Contractor and Owner against any claims, damages, losses and expenses, including legal fees, arising out of or resulting from performance of subcontracted work to the extent caused in whole or part by the Subcontractor or anyone directly or indirectly employed by the subcontractor.”
The jury had to consider the issue of negligence in the second phase of the trial. Indeed, the issue was essential to a finding of the parties’ responsibilities under the indemnification agreement.
See Agricultural Insurance, Co. v. Ace Hardware Corp.,
Relying on
Lazzaro v. MJM Industries, Inc.,
The cases cited by Affordable and Mountain do not hold otherwise. In both
Based on the evidence in both phases of the trial, a jury could reasonably conclude that Affordable and Mountain failed to exercise due care in their supervision and control of the site, and that had they exercised proper care (for example, by ensuring toe holds were on the roof), plaintiffs accident would not have occurred. The jury answered the questions regarding negligence when they were asked to do so. Thus, I will not set aside the jury’s apportionment of liability.
3. Preclusion of Proof Regarding Lack of Insurance was Proper
The issue of whether there was a breach of the insurance clause is irrelevant, because no cause of action for such a breach was alleged. The parties’ Joint Pre-Trial order identified four issues to be tried: 1) the cause of plaintiffs accident; 2) the extent of plaintiffs injuries; 3) whether C & L was required, by virtue of its contractual obligation, to indemnify and hold harmless Affordable and Mountain; and 4) whether third-party plaintiffs were legally entitled to maintain a third-party action in the nature of a declaratory judgment action. There was no cause of action seeking damages as a result of C & L’s breach of its duty to name Affordable and Mountain as additional insureds, and no such issue was identified as triable in the pretrial order.
A Third-Party Plaintiffs had no direct claim against Preferred
In so far as Affordable and Mountain sought to obtain a declaratory judgment against Preferred, the parties stipulated that neither Affordable nor Mountain was an additional insured under C & L Construction’s insurance policy with Preferred. For that reason, Affordable and Mountain cannot maintain a direct action against Preferred. Affordable and Mountain are only incidental beneficiaries to the policy. They have no rights under the policy, and thus cannot maintain an action against
The fourth issue identified in the pretrial order was whether third-party plaintiffs were legally entitled to maintain an action for declaratory judgment.
2
The issue was framed poorly in the pre-trial order. However, in so far as Affordable and Mountain.sought to obtain a declaration that C & L Construction was liable to them for the judgment entered against them, they do not need a “declaration.” They have the jury’s verdict, which states that C & L agreed to indemnify them and is responsible for 82% of the judgment.
Third-Party Defendant’s Motion for A New Trial Pursuant to FRCP 50(b)
Cleidson Silva argues that the jury’s determination that Paulo Miranda assented to the terms of the indemnification agreement (DX4) is against the weight of the evidence. Although the jury concluded that Miranda did not sign DX4 (see Phase II Verdict Sheet, Q. 1), there was sufficient evidence from which a jury could conclude that he did in fact assent to its terms on behalf of Silva — in fact, as Silva’s partner.
Silva argues there was no evidence that Miranda understood the nature and terms of the written portion of the agreement, and therefore there was no meeting of the minds and he could not have assented to its terms by conduct or otherwise. Silva asserts that in his testimony Miranda failed to mention the indemnification provision and “merely testified that this ‘contract’ required him to prove that, he had insurance, and also required something relating to ‘additional insurance.’ ” (Silva Mem., 8.)
Silva’s memorandum refers to testimony, but fails to directly quote it, or offer citations to the record (presumably because counsel has failed to obtain the transcript). A review of the draft transcript reveals that Miranda testified that the contract was in two parts- — -“The first part you have to give the company you’re going to work for, that is Jacob in this case, the insurance certificates, showing that you have insurance for yourself and your employees, and the second part is an additional insurance which you have to give as well which shows you and your company are responsible for your employees.” Tr. 89:19-24. Based on this- testimony, it is clear that Miranda understood. C & L construction was responsible for the actions of its own employees. This is what the indemnification agreement provides. Whether or not Miranda is familiar with the legal terminology concerning indemnification is irrelevant.
There was also evidence presented at trial from which a reasonable jury could determine that Miranda understood the terms of the agreement, and assented to it on behalf of C & L Construction. Both Sofer and Miranda testified that Affordable and Mountain required indemnification and proof of insurance before C & L could begin work on the site. Miranda, Tr. 146:9-25; Sofer, Tr. 160:14-161:10, 163:18-164:4. By beginning work on the site and obtaining and delivering a Certificate of Insurance — as required in DX4 — Miranda consented to the terms of the agreement, regardless of whether he signed DX4 or not.
See Podhaskie v. Seventh Chelsea Associates,
Because the jury determined that Miranda was Silva’s partner, his actions and consent to be bound by the terms of DX4 also bound Silva and C & L Construction. The jury’s determination that Miranda was Silva’s partner was amply supported by the evidence (indeed, Silva does not move to overturn the verdict on that ground). Silva himself acknowledged that he and Miranda had been partners on another job; Silva sent his employees to work at the site; and Silva obtained the insurance for the job.
Finally, Silva argues that because the jury concluded that Miranda did not sign the document, it must be a forgery and therefore is void
ab initio. See Opals on Ice Lingerie v. Bodylines, Inc.,
No. 99 Civ. 3761,
This constitutes the decision and order of the Court.