121 Va. 102 | Va. Ct. App. | 1917
delivered the opinion of the court.
James A. Buchanan entered into a written agreement with John H. Nolan, a building contractor, whereby the latter agreed to furnish for the former all the material and labor necessary for the erection of a costly residence. After the work was less than half done, and after less than half of the total contract price had been paid, Nolan failed financially and surrendered the contract and the work done and to be done thereunder to Buchanan, who proceeded to carry the same to completion under the following provision of the contract:
“Art. V. Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after three days’ written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools and appliances thereon, and to employ any other person or persons 'to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor he shall not be entitled to any further payment under this contract until the said work shall be wholly finished, at which*106 time if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the .owner in finishing the work, such excess shall be paid by the owner to the contractor; but if such expense shall exceed such unpaid balance the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided either for furnishing materials or for finishing the work, and any balance incurred through such default, shall be audited and certified by the architect, whose certificate thereof shall be conclusive upon the parties.”
There is some controversy as to whether this clause in the contract was strictly complied with, but it is entirely clear from the evidence that there was such compliance, and the certificate of the architect, made after the building was completed, showed that Nolan was indebted to Buchanan in the sum of $4,756.49.
The appellants, Maddux and others, were sub-contractors who had furnished labor and material to Nolan, and to whom he was indebted at the time of his failure and surrender of the contract. Having filed their claim of liens in conformity with section 2477 of the Code of Virginia, and given notice thereof to Buchanan, they proceeded to institute their separate suits in equity to enforce the same. These suits were brought before the building was completed, and Buchanan filed, first, an original answer in each case, exhibiting his contract, denying any indebtedness whatever to the general contractor, and averring that it would cost more than the balance of the contract price to finish the work, and, later, a supplemental answer exhibiting the certificate of the architect and showing a balance due from the contractor of $4,756.49.
The several causes, which were heard together, were referred to a commissioner for a report upon a number of questions, but the gist of the inquiry, so far as it affects this appeal, was whether Buchanan owed Nolan anything at the time the contract was surrendered, or would owe him any
The decree was right in all respects. It, of course, comes to us with the strong presumption in its favor attaching to a decree by which the trial court has confirmed the report of a commissioner upon a question of fact (Hall v. Hall, 104 Va. 773, 776, 52 S. E. 557, and cases cited) ; but, independently of that presumption, the evidence satisfies us that there was no time after notice- to General Buchanan of the claim of the appellants when he was indebted in any amount to the general contractor; and this is necessarily the end of the case. Laborers and material men are favored by the statute, but not to the extent of requiring the owner of property to pay the same bills twice, once to the builder with whom he has contracted, and again to parties with whom he has no contractual relations. Our present mechanic’s lien laws deal fairly with both the owner and the sub-contractor, requiring the owner, after notice, to withhold from the general contractor enough to pay the sub-contractor, provided however, “the same does not exceed the sum in which the owner is indebted to the general contractor at the time the notice is given, or may thereafter become indebted by virtue of his contract with said general contractor.” (Code, sections 2477, 2479). The sub-contractor will generally be as well situated as the owner to determine whether the general contractor is solvent. To do more than our statute has done in relieving the sub-contractor of risk in this respect would be to make the owner of a building the guarantor of all the bills incurred thereon by the general contractor. This would unjustly, if not unconstitutionally, abridge the right of contract. The statute
The authority of the case of S. V. R. R. Co. v. Miller, 80 Va. 821, relied upon by counsel for appellants, in so far as it is at variance with the view here expressed, has been entirely destroyed by the subsequent change in the statute, which now very justly limits the liability of the owner to his indebtedness to the general contractor at or after the time he received notice of the sub-contractor’s claim.
In Burks’ Pleading and Practice, page 821, section 421, the author, after stating, as pointed out by counsel for appellants, that the sub-contractor is given by the statute three different methods by which he may secure the payment of the amount due him, namely, (1) by filing an independent lien, (2) by taking steps to hold the owner personally liable, and (3) by invoking the benefit of the general contractor’s lien, makes it perfectly clear that each of these three methods is dependent upon and limited by the indebtedness of the owner to the general contractor.
. But it is said that the contract between Buchanan and Nolan was not recorded, that the sub-contractors had no notice and were not bound by its terms, and-that the owner, therefore, became a trustee for the sub-contractors, and should have protected himself by requiring a bond of the general contractor.
There is no statute requiring the recordation of such contracts, and there is no rule of law making the owner a trustee for sub-contraqtors in such cases. Upon the con
What has been said disposes of the principal assignments of error. The remaining ones are of minor importance and will require only a brief discussion.
Included in the sum found by the commissioner as the balance due from Nolan" to Buchanan was an item for liquidated damages, under a clause in the contract providing for a payment by the contractor of $10 per day after a certain date until the work was completed. Appellants contend that it was error in the report and decree to so find. The question is not material, so far as appellants are concerned, for the reason that the item in question was only about half of the total balance found against Nolan, and with that item eliminated there would still be nothing upon which the claims of appellants could attach, either as liens or as grounds of personal liability against Buchanan.
The last assignment of error is that “the certificate of the architect is not binding upon any one, under the conditions as set forth in this petition, and the evidence in this cause, especially upon the sub-contractors, as the architect, in his certificate, made no reference to the fact of the material or work of the sub-contractors which he used or the amount of work performed by Nolan on the fourth payment.”
The answer to this contention is two-fold. In the first place, the report of the commissioner and the decree confirming the same do not rest upon the architect’s certificate, except in so far as it may have been considered by the commissioner and the court along with the deposition of the architect and all the other evidence in the cause. In the second place, the proposition upon which the assignment is predicated is, in itself, unsound. We have already seen that the appellants were dependent upon the existence of an indebtedness from Buchanan to Nolan, and that this indebtedness must have arisen in accordance with the terms of the contract between those two parties. The certificate
There is no error in the decree of the circuit court, and it must be affirmed.
Affirmed.