52 N.Y.S. 747 | N.Y. App. Div. | 1898
The learned counsel for the appellant insists that by the amended pleadings new issues were raised in this case, and that in consequence thereof different questions are presented oh this appeal from those which were decided by this court on the two former appeals. (13 App. Div. 232; 21 id. 472.) The complaint before the court on the first and second appeals contained an allegation of strict performance in accordance with the terms and conditions of the contract between the plaintiff and the defendant, but the amended complaint contains an allegation of substantial performance by the plaintiff of all the conditions of the contract and the completion of the work under the contract in accordance with the plans and specifications. The original complaint contained also an allegation that
Upon the question of waiver by acceptance of the work by the city, we find no substantial difference between the evidence as it was given on the last and as it appeared on the previous trials. We held on the first appeal that there was no waiver by the city of the conditions of the contract nor of the defects in performance, and that the acts of the commissioner of public works were not tantamount to an actual and voluntary acceptance of the work as a fulfillment of the contract, carrying with it an implied promise to pay for it. It was held on the first appeal that there was no waiver by taking possession of the work, and we do not see that the question is now presented under the proofs in any such way as to call for a different ruling. It is asserted that the claim as now made by the plaintiff is simply that of a waiver of full performance, to the extent of precluding the defendant from insisting that there was not a substantial performance, and there is not such a waiver as would prevent the defendant from recovering any damages suffered by reason of a failure fully to perform. Or, in other words, that the plaintiff would be entitled to recover upon proof of substantial performance, subject to recoupment of damages proven to be the result of nonperformance. There are cases in which on contracts, as, for instance, the sale and delivery of goods, a waiver of full performance may be shown and a deduction allowed a defendant for a plaintiff’s failure to perform the whole contract, and such are Brady v. Cassidy (145 N. Y. 171); Dalzell v. Fahys Watch Co. (138 id. 285); Avery v. Willson (81 id. 341); but the amended answer in this case sets up a
We have only then remaining for consideration the question whether any real change is made in the case, by reason of the abandonment of the allegation of the complaint of strict performance and the substitution of one of substantial performance. We think there is not, and for the reason that the proof does not show substantial performance. What is meant by the substantial performance of such a contract as that involved here is fully settled in the State of New York. In Woodward v. Fuller (80 N. Y. 312) it is said that literal or exact performance of a contract to build is no longer required. “ It is now the rule that where a builder has in good faith intended to comply with the contract, and has substantially complied with it, although there may be slight defects 'caused by inadvertence or unintentional omissions, he may recover the contract price.” And it is further said that the defects must not run through the whole work, nor ~be so essential as that the object of the parties to have the specific cmnount of work done in a particular way is not accomplished. The language of the court as quoted in the case last cited is but a repetition of what was said by Church, Ch. <7., in Phillip v. Gallant (62 N. Y. 264). The identical expressions first quoted are repeated in Nolan v. Whitney (68 N. Y. 650), which was also a case of a contract to do work in the erection
In the case at bar we have already decided upon similar proof that performance was not shown of this contract by the plaintiff, and hence there was nothing for a jury to pass upon. As the pleadings originally stood, we considered the question merely with reference to the allegation of strict performance, but on the point of sub-* stantial performance the same conclusion is compelled. The object of the contract was to secure a water-tight and not a water-drained cellar, and it was the contract of the plaintiff to produce that result in the way provided for in the specifications. It did not perform the contract; the defect is one which pervades the whole contract. It is not a mere technical, inadvertent or unimportant defect in the work, or departure from the specifications. That which was done was plainly inadequate to produce a water-tight cellar, and the substitution of the ejector, while it might drain the cellar, did not make it water tight as that term was used and intended to be used by the parties to the contract. There was no substantial performance of that contract. The proof failed to establish it, but plainly showed the contrary. The court below was right in dismissing the complaint, and the judgment and order appealed from must be affirmed, with costs.
Yaw Brunt, P. J., O’Brien, Ingraham and McLaughlin, J.J., concurred.
Judgment and order affirmed, with costs.