This аppeal concerns the interpretation and enforceability of an indemnification clause in a lease between third-party defendant-appellant Restoration Preservation Masonry, Inc. (“RPM”) and defendant-appellee *934 Dunlop Equipment Company, Inc. (“Dun-lop”). Plaintiff-appellee Charles MacGlash-ing was injured when an elevated work platform leased by Dunlop to RPM collapsed while he and another employee of RPM were using it in their masonry work. MacGlash-ing and his wife, residents of New Hampshire, brought a diversity action in tort against Dunlop, a Massachusetts corporation, in the district court of Massachusetts. Dunlop sued RPM, invoking the lease indemnification clause. Prior to trial the MacGlashings, with court approval, entered into a settlement agreement with Dunlop. The issue on appeal is whether the MacGlashings, standing in the shoes of Dun-lop, can collect the amount of the settlement from RPM under the indemnification clause of the lease between RPM and Dunlop. This issue was decided in favor of the MacGlashings and Dunlop by summary judgment. There is no question that Massachusetts law applies.
RPM maintаins that it has no obligation under the lease agreement to indemnify Dun-lop for damages flowing from Charles MacGlashing’s accident because Dunlop materially breached the agreement. It also challenges the scope of the indemnification clause. Discerning no error in the district court’s summary judgment analysis, we affirm.
I.
BACKGROUND
Viewed in the light most favorable to RPM, the nonmoving party, the facts are as follows. RPM, a Massachusetts-based corporation, employed Charles MacGlashing as a brick mason until September 2, 1993, when he was involved in a work-related acсident at The Longwood Towers located in Brookline, Massachusetts. In 1993, the Longwood Corporation (“Longwood”), owner of The Long-wood Towers complex, commissioned RPM to conduct phase II of a renovation project at Longwood Towers. Like phase I, which had been completed a year earlier by NER, Inc. (“NER”), phase II involved removal and replacement of brick and stone at the top of three eight-story buildings located in the complex. RPM was formed by former employees of NER. Several of them, including RPM’s president Paul Haven, hаd worked on phase I. During both phase I and II, mobile, elevated work platforms fitted with eight-foot outrigger devices, which extended off the main platform to expand its width, were utilized for stone and brick removal and to make certain setback portions of the buildings accessible. The outriggers were modifications to the original platform design.
On September 2, 1993, MacGlashing and a co-worker, James Proctor, were removing a piece of stone from the parapets of Building B when the work platform they were using collapsed. Both men fell eight stories to the grоund. Proctor died from the injuries he sustained. MacGlashing, who was thirty-nine at the time, survived, but suffered injuries that hospitalized him for six months and left him partially paralyzed and in constant pain. These injuries included, inter alia, broken bones, internal and neurological damage, a ruptured aorta and bladder, a perforated colon, lung damage, and lacerations. MacGlashing incurred more than $800,000.00 in medical fees and expenses as a result of the accident. His future medical costs and net economic loss have been projected between $600,000.00 to $1.1 million and $1.1 million to $1.3 million, respectively. At trial, the parties agreed that the platform involved in the accident collapsed because it could not bear the weight placed on it, but disagreed about whether the platform had been defectively designed, used negligently, or negligently modified by Dunlop. Dunlop, whose business consists of supplying work platforms for sale or lease, provided the platforms employed in both phase I and II of the Longwood Towers renovation project. It executed a July 7, 1993, lease agreement to provide four platforms with RPM’s president, Paul Haven, who had left NER to form RPM.
The lease agreement executed between RPM and Dunlop was a standard form contract and contained the following indemnification clause:
12. THE LESSEE HEREBY ABSOLVES THE LESSOR OF ANY RESPONSIBILITY OR OBLIGATION IN *935 THE EVENT OF ACCIDENT, REGARDLESS OF CAUSES OR CONSEQUENCES, AND THAT ANY COSTS, CLAIMS, COURT OR ATTORNEY’S FEES, OR LIABILITY RESULTING FROM THE USE OF DESCRIBED EQUIPMENT WILL BE INDEMNIFIED BY THE LESSEE REGARDLESS AGAINST WHOM THE CLAIMANT OR CLAIMANTS INSTITUTE ACTION.
II.
PROCEEDINGS BELOW
The MacGlashings brought a federal diversity jurisdiction suit, see 28 U.S.C. § 1332(a), against Dunlop, seeking recovery on theories of negligence, product liability, and breach of warranty. They charged Dunlop with negligence in the design and modification of the work platforms leased to RPM, negligence in failing to inspect the platforms and repair defects and damage, and negligence in failing to warn and instruct RPM employees in the use of the platform. They also asserted that Dunlop breached the implied warranty that the work platforms were merchantable and fit for their intended use. The MacGlashings later amended their complaint to assert claims against Longwood under Mass. Gen. L. eh. 143, § 51. These claims are not relevant to this appeal.
Dunlop filed a third-party complaint against RPM, seeking indemnification pursuant to their lease agreement. RPM denied any indemnification responsibility and counterclaimed, alleging that Dunlop materially breached the lease agreement by providing defective and unreasonably dangerous equipment.
Each of the parties filed summary judgment motions before the magistrate judge. Dunlop and the MacGlashings moved for summary judgment on Dunlop’s third-party complaint. They maintained that, under the indemnification clause contained in the lease agreement, RPM was obligated to indemnify Dunlop for any liability resulting from the use of the leased equipment and that Dunlop did not materially breach its obligations under that agreement. RPM contested this joint motion and filed its own motion for summary judgment on Dunlop’s third-party claims. In both instances, it contested the enforceability of the lease agreement executed with Dunlop, claiming that Dunlop materially breached the implied warranties of merchantability and fitness for a particular purpose contained in the agreement by failing to test the load-bearing capacity of the work platforms and outriggers prior to delivery of them to the project site.
The case was assigned to a magistrate judge. In her report and recommendations, she first addressed RPM’s summary judgment motion. The magistrate judge denied RPM’s claim that the leаse agreement it executed with Dunlop included an implied warranty of fitness for a particular purpose, under Mass. Gen. L. ch. 106, § 2-315, but agreed that it contained an implied warranty of merchantability, under Mass. Gen. L. ch. 106, § 2-314. The magistrate judge recommended that RPM’s motion for summary judgment be denied because she found that genuine issues of material fact existed as to whether Dunlop breached its implied warranties.
Turning to the joint motions for summary judgment filed by Dunlop and the MacGlash-ings, the magistrate judge concluded that the record, viewed in RPM’s favor, precluded a dismissal with prejudice, of RPM’s counterclaim for breach. She recommended, however, that Dunlop and the MacGlashings’ joint motion for summary judgment on Dunlop’s third-party complaint be allowed. The magistrate judge found that, barring a determination that Dunlop materially breached the lease agreement, RPM was “obligated to indemnify Dunlop for any liability resulting from Charles MaeGlashing’s use of the leased equipment.” She concluded that “whether Dunlop’s conduct amounted to a material or serious breach of the contract” was an issue of fact for the jury. Each of the parties filed timely objections to the magistrate judge’s report.
The district court issued an order accepting, in part, and modifying, in part, the Report and Recommendation of the magistrate judge. The district court agreed with the magistrate judge’s determination that RPM’s motion for summary judgment should be de *936 nied. While it also agreed that summary judgment in favor of Dunlop and the MacGlashings was appropriate on Dunlop's third-party complaint, the court rejected the magistrate judge's conclusion that RPM's obligation to indemnify Dunlop for damages ari~ing from Charles MacGlashing's injuries could be relieved by a material breach by Dunlop. The court held that, under Massachusetts law, a party's breach of an implied warranty was insufficient to invalidate a broadly worded indemnification clause.
The district court scheduled a jury trial on the various claims asserted by the parties. Before the trial date arrived, however, the MacGlashing's entered into a settlement agreement with Dunlop, subject to court approvaL The settlement contemplated satisfying the MacGlashings' suit for damages against Dunlop with a $750,000.00 cash payment-approximately 75 percent of the insurance coverage available to Dunlop through its insurer-and the assignment of Dunlop's claims against RPM and Longwood to the MacGlashings. Under the agreement, judgment was to enter in favor of Charles MacGlashing in the amount of $4,560,000.00 and in favor of Sharlene MacGlashing for $300,000.00. The MacGlashings agreed to seek no further recovery from Dunlop in the event they could not recover from RPM or Longwood.
The district court held a hearing and reviewed evidence before approving the settlement. At the hearing RPM's counsel stated, inter alia:
I don't believe that RPM has any оbjection to the structure of the settlement under the current circumstances ... I believe that the settlement is fair and equitable under these circumstances.
The district court approved the settlement. The claims against Longwood were tried to a jury which returned a verdict in favor of Longwood. The district court issued a final judgment dismissing the action of the MacGlashings against Longwood, entering judgment against Dunlop, and ordering that Charles MacGlashing recover $4,651,739.23 and his wife, $306,032.52-the amount of the settlement plus post-judgment interest at the rate of 5.86%-from RPM. This appeal followed.
III.
STANDARD OF REVIEW
We review the district court's grant of summary judgment de novo and review the record in the light most favorable to the nonmoving party, drawing all inferences in that party's favor. Den Norske Bank AS v. First Nat'l Bank of Boston,
Allegations of a factual dispute "will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact." Morrissey v. Boston Five Cents Sav. Bank,
Iv.
DISCUSSION
The issue is whether the indemnification clause contained in the lease agreement *937 RPM executed with Dunlop is enforceable and, if so, whether its scope includes liability for damages stemming from the injuries MacGlashing sustained as a result of the accident. RPM avers that it is not obligated, under Massachusetts law, to pay the judgment awarded the MacGlashings because Dunlop materially breached the lease agreement, relieving RPM of the рromise to indemnify Dunlop contained in the agreement. In the alternative, RPM argues that even if the indemnification clause is valid, it should not be deemed responsible for the particular claims advanced by the MacGlashings because they fall outside the contemplated scope of the agreement.
Appellees contest both of these arguments. We begin by addressing the enforceability of the lease agreement and then turn to a discussion of its scope.
Enforceability of the Lease Agreement’s Indemnification Clause
RPM challenges the еnforceability of the indemnification clause by attacking the validity of the lease agreement it executed with Dunlop.
See Kelly v. Dimeo, Inc.,
RPM, in effect, attempts to use the tort claim of the MacGlashings against Dunlop as a basis for its argument that Dunlop breached its implied warranty of merchantability. But the contract between RPM and Dunlop was for the lease of property. RPM cannot use the indemnity clause to turn an economic contract into one based on tort concepts.
Massachusetts law plainly forecloses RPM’s argument. It adopts the majority view which draws a clear distinction between tort recovery for physical injury and contract recovery for economic loss.
See Jacobs v. Yamaha Motor Corp.,
Moreover, appellant has not convinced us that the alleged breach of the lease agreement rendered the indemnification clause invalid, as if it had never been executed. The one-page contract executed between RPM and Dunlop contains standard-form language and clauses which suggest that the indemnity provision is separate from the underlying lease. The face of the agreement sеts out, inter alia, the type and cost of the equipment to be leased, as well as guidelines for its installation and transportation around the site, and expressly incorporates a July 21, 1993, handwritten note regarding delivery, assembly, and pickup of the work platforms by Paul Haven, RPM’s president.
The reverse side of the agreement contains seventeen numbered paragraphs that outline lease conditions and are clearly separated by spacing. Two of these reverse-side clauses concern responsibility for damages flowing from the use of equipment referred to in the lease agreement. The first clause provides that RPM assumes full responsibility under the agreement for damages, injuries, and accidents caused by the use of Dunlop equipment and reads:
3. Lessee assumes the full responsibility for damages, injuries and accidents resulting to any property or persons, caused by the use of said equipment while in the possession of the lessee, from the time of arrival at the above named location, during the term of lease, and until equipment is returned to lessor.
The second clause deals with indemnification and is one of six written in boldfaced type. It provides that RPM absolves Dunlop of any responsibility or obligation in the event of accidents resulting from the use of the leased equipment, regardless of cause or consequence and reads:
12. THE LESSEE HEREBY ABSOLVES THE LESSOR OF ANY RESPONSIBILITY OR OBLIGATION IN THE EVENT OF ACCIDENT, REGARDLESS OF CAUSES OR CONSEQUENCES, AND THAT ANY COSTS, CLAIMS, COURT OR ATTORNEY’S FEES, OR LIABILITY RESULTING FROM THE USE OF DESCRIBED EQUIPMENT WILL BE INDEMNIFIED BY THE LESSEE REGARDLESS AGAINST WHOM THE CLAIMANT OR CLAIMANTS INSTITUTE ACTION.
The standard form equipment sign-off sheets Paul Haven signed on the 20th, 22nd, 23rd, and 27th of July 1993, when Dunlop delivered the work platforms to the work site, contain similar language. They provide that RPM agrees that: “Dunlop, Inc. is not responsible for any damages to the building, or any injuries or accidents resulting to people or property caused from the use оr misuse of this equipment.”
Based on our reading of the lease and the sign-off sheets, we do not think RPM and Dunlop intended the covenants contained in the lease agreement and the indemnification clause to be dependent.
See Connolly v. Haines-Ce Brook, Inc.,
There is solid precedent for our decisiоn to treat the indemnification clause as a separate agreement unaffected by any breach of the lease contract.
See, e.g., Hill Constr. Corp. v. American Airlines, Inc.,
This holding persuades us that the course we adopt in this case would be followed by the Massachusetts courts. Under Massachusetts law, the allocation of risk through contractual agreements neither conflicts with public policy,
Canal Elec.,
Risk allocation agreements are common in the construction industry and are widely-regаrded as a “reasonable accommodation” between parties to a commercial agreement.
See Canal Elec.,
Nothing in the record suggests that Dun-lop acted in bad faith,
see
Mass. Gen. L. ch. 106 § 1-203 (1990),
Hill Constr.,
Scope of the Indemnification Clause Under Massachusetts Law
In addition to attacking the enforceability of the indemnity clause, RPM attacks its scope. It argues that, under Massachusetts law, the term “use” contained in paragraph 12 of the agreement cannot be read to include liability for claims brought on a theory of strict liability instead of negligence.
See Hayes v. Douglas Dynamics, Inc.,
The rule that indemnity contracts are to be strictly construed against the indemnitee no longer obtains in Massachusetts.
See Whittle,
We are not impressed by RPM’s argument that the indemnity clause’s failure to spеcifically refer to strict liability claims omits such claims from its scope. That the clause also fails to mention claims brought on a theory of negligence undermines the force of RPM’s argument significantly because there is little support for the contention that the omission of a specific reference to negligence invalidates an indemnity clause. Massachusetts cases such as
Shea,
We have little doubt that the language contained in the indemnity clause is broad enough to encompass claims brought on a theory of either negligence or strict liability. First, we do not agree with RPM that private agreements allocating the risk of strict liability for tort damages in the circumstances presented here thwart public policy. Such agreements are reasonable acсommodations in the construction industry context. Second, the language contained in paragraph 12 of the lease agreement is broad and expansive. It absolves Dunlop for “any responsibility or obligation” in the event of an accident, “regardless of cause or consequences,” stemming from the use of its equipment.
Similar language has been found sufficient to encompass indemnification obligations on claims brought on a theory of strict liability.
See Beloit Power Sys., Inc. v. Hess Oil Virgin Islands Corp.,
In
Polaroid Corp. v. Rollins Envtl. Serv. (NJ), Inc.,
Moreover, paragraph 14 of the lease convinces us that the parties intended the indemnity agreement to cover all liability whether grounded in negligence or strict liability. Paragraph 14 provides, in relevant part, “Our insurance [Dunlop’s] does not cover the equipment while in your possession [RPM’s].” It can be reasonably inferred from this that the parties intended RPM to procure insurance to cover thе burden it assumed under the indemnity clause.
Cf. Speers,
RPM’s contention that the indemnity clause is not conspicuous and cannot shift liability for defective equipment does not deserve extended comment. The clause is printed in capital letters. Its language is neither ambiguous nor confusing. The president of RPM testified that he read it and understood it. At oral argument counsel for RPM agreed that the lease was not a contract of adhesion.
We end our analysis by noting that at the hearing on the proposed settlement between the MacGlashings and Dunlop, counsel for RPM expressly approved the structure of the settlement and stated that it was fair and equitable.
V.
The judgments of the district court are affirmed. There will be added to the judgment amounts of $4,651,739.23 and $306,-032.52 such additional post-judgment interest as is due.
Costs on appeal awarded to appellees.
