143 N.Y.S. 221 | N.Y. App. Div. | 1913
This action is brought pursuant to the provisions of section 4 of the Labor Law (Consol. Laws, chap. 31; Laws of 1909, chap.
The complaint being, as has been said, based upon an alleged violation of section 3 of the Labor Law in the manner of performance of the contract which Hosier & Summers had with the city of Buffalo for the erection of this public building, it is important to determine whether, at the time of the violations alleged, there was in fact a contract between these parties. These violations all occurred between the 17th of April and the 1st day of Hay, 1912. The formal written contract was not in fact signed till Hay twenty-second, following. Plaintiff, however, contends that the contract was in fact made as early as April fourth, preceding.
There is no dispute that proper proceedings were had by the duly authorized city officials by which plans and specifications for the proposed building were duly adopted, a notice duly published calling for proposals or bids for the work of construction; that bids were received, and that it was duly ascertained by the commissioner of public works, upon whom rested the power and responsibility of the determination, that Hosier & Summers’ bid was that of the lowest responsible bidder. This bid was accompanied, as required by the terms of the advertisement, with a bond, conditioned in effect that if the bid was accepted the bidder would make the contract with the city according to the terms proposed in the advertisement for bids. But the legal scheme governing the letting of contracts of the class to which the contract in question belongs provided for a
The violations alleged occurred while a sub-contractor named
No intimation is made that the execution of the written contract was unduly delayed for the purpose of permitting any part of the work contemplated to be done without the statutory restrictions as to the manner of performance. It is doubtless true that, if there were a basis for a suggestion that the execution of the contract was in fact delayed for the purpose, even incidentally, of avoiding the statutory prohibitions, it would be held, and properly enough, that the contractors had in fact violated the statute, and no contract, under those circum
I think also that the trial court held properly that, even conceding that the work being done by Brown, the sub-contractor, at the time of the violations alleged was done under the contract between the city and the contractors, the evidence does not show that any of these violations were required, or permitted, by the contractor, or even that they occurred with its knowledge or consent. It would seem to be a manifest injustice to hold that violations of the statute for which the contractor was not responsible, as having itself required or permitted them, or as having with actual knowledge, or under such circumstances as would properly charge it with constructive knowledge that violations of the statute were either required or permitted by others, who were engaged on the work, could properly be attributed to the contractor for the purpose of enforcing the drastic penalty of a forfeiture of the contract.
The opinion of the trial court on this branch of the case leaves nothing of importance to be said. (19 Misc. Rep. 460.)
The judgment should be affirmed, with costs.
All concurred.
Judgment affirmed, with costs. •