delivered the opinion of the Court.
This suit wаs instituted by respondent to remove cloud from her title to certain property caused by the filing by petitioner of a mechanic’s lien asserting a claim for architect’s fee due him for drawing up- plans and specifications for a proposed restaurant and private club. Respondent admitted the contract between her and petitioner for services as an architect, but sоught to cancel his claimed lien on the grounds, first, that the plans and specifications which he prepared were incomplete, and, second, that the building which was called for would cost greatly in excess of the $60,000.00 to $70,000.00 limit agreed upon. Petitioner filed a cross-action to foreclose his lien and recover his fee. After the evidence had been presented, respondent filed а motion for an instructed verdict that petitioner take nothing by his cross-action and that the claimed mechanic’s lien be can-celled. The grounds of her motion were that petitioner neither рleaded nor proved that he was a licensed architect in good standing at the time the original agreement was entered into or at the time the work
Respondent’s motion for an instructed verdict was granted, and judgment rendered cancelling petitioner’s lien and removing it as a cloud on her title. Neither the order directing the jury to return a vеrdict in favor of respondent nor the judgment is based specifically on one or another of the grounds asserted in respondent’s motion, the judgment reciting that “under the evidence introduced and the рleadings of the parties” petitioner failed to establish a basis or ground to support a judgment in his favor.
The Court of Civil Appeals affirmed the judgment of the trial court upon the ground that it was incumbent upоn petitioner to plead and prove that he was a licensed architect in good standing at the time he entered into the contract with respondent and at the time he performed the work for her; and that the trial court did not abuse its discretion in refusing to allow petitioner to amend his pleadings. The court did not affirm the judgment on the ground that the evidence would not support a finding that the plаns and specifications were too incomplete to amount- to
a performance, but on that ground the court held that there was evidence from which a jury might conclude that there was substantial performance. It affirmed the trial court’s judgment on the ground that an instructed verdict was properly granted because of the failure of the pleadings and proof that petitioner was а licensed architect in good standing.
The application for writ of error contains three points. Point 1 is as follows:
“The Court of Civil Appeals erred in holding that it was incumbent upon Petitioner to plead and prove that he was a duly registered and licensed architect in good standing at the time the plans were prepared and at the time of the trial.”
Point 2 is as follows:
“The Court of Civil Appeals erred in sustaining the action of the trial court in refusing to allow Petitioner leave to file a trial amendment.”
The third point presents in different language the same basic question as the first point.
We sustain the first point, and that renders the second point immaterial.
Had the petitioner not filed a cross-action for his fee, and the suit had been only one by respondent to quiet title, clearly the burden of proof would have been upon her to establish that the adverse claim was a cloud upon her title; but, since petitioner filed a cross-action asserting the validity of his lien and seeking a foreclosure therеof, a judgment denying him recovery against respondent and a foreclosure of his claimed lien would have the effect of removing any cloud from plaintiff’s title. The question of whether petitioner’s рleading and proof were deficient seems, therefore, clearly presented for decision.
In Clark v. Eads,
Article 249a, Y.A.T.S., is a comprehensive statute regulating the
Rule 94, Texas Rules of Civil Procedure, places the obligation upon the defendant to plead illegality affirmatively as a defense. That rule should not be construed to limit illegality as an affirmative defense to contracts which are prohibited by law, but to include contracts rendered unenforceable because of some failure to comply with the law. The question narrowed down, then, is whether, when recovery is sought for services rendered as an architect, his compliance or failure to comply with the statute regulating the practice of architеcts determines whether such services were legally rendered. If it is a question of illegality of contract, clearly Rule 94 governs. In M.M.M., Inc. v. Mitchell,
Rule 94 serves a most useful and important purpose in our practice. If followed uniformly, it will mаke for more certainty in cases like the instant one. We can perceive of no reason why this case should not fall within the terms of that rule, and accordingly we hold that if petitioner was not in fаct an architect in good standing when he made the contract and performed the services alleged, then his contract was illegal and respondent should have affirmatively pleaded its illegality. In principle that conclusion finds support in Reid v. Associated Employers Lloyds,
In Swift v. Kelly,
It is respondent’s position that the judgment of the trial court should be sustained on the ground that no evidenсe was introduced from which a jury might conclude that there was any substantial performance of the contract. This point was overruled by the Court of Civil Appeals. It held: “Here the ultimate issue was whether the plans and specifications were substantially complete. There was a dispute in the evidence and such explanation of alleged deficiencies, and expressions of professional opinion with regard to this, that we think a fact issue was raised.” The evidence strongly indicates to our minds that the plans and specifications were deficient, especially in their treatmеnt of the plumbing, electrical and air-conditioning facilities, and that the proposed building could not be constructed within the specified limits of $60,000.00 to $70,000.00. Petitioner, however, testified that the plans and specifications were substantially complete and that it was good practice to omit certain details relating to plumbing and electrical facilities,
Resрondent’s motion for an instructed verdict contained the further ground that a recovery on quantum, meruit could not be had since the evidence showed an express contract. Petitioner does not assеrt here any claim of right to recover on that ground.
Our conclusion on the case as a whole is that the judgments of both courts below should be reversed, and the cause remanded to the trial court.
Opinion delivered October 5,1960.