OPINION
M.J. Sheridan and Son, Co., Inc., sued Seminole Pipeline Company alleging that Seminole had breached its contract with Sheridan by failing to provide Sheridan with a pipeline easement and that this damaged Sheridan because it was unable to proceed with its contract. Sheridan also sought recovery on theories of fraud and quantum meruit. After a jury trial, the court entered a directed verdict as to the fraud and quantum meruit causes of ac *622 tions, and the jury found that Seminole had provided Sheridan with a right-of-way within a reasonable time. Therefore, the court concluded that Seminole had not breached the contract, and entered a take-nothing judgment in its favor.
We affirm.
Sheridan agreed to construct a pipeline for Seminole on a right-of-way to be provided by Seminole. The contract consisted of general requirements, specifications sheet, equipment rate schedule, labor rates, and a job description. The job description provided for commencement on September 15, 1981, and completion by November 2, 1981. The contract was signed on November 3rd, and construction of the pipeline began November 9th and was completed on February 27, 1982.
The agreement contained specific provisions to record any extra work on a “memorandum of work” performed to be signed by representatives of both Sheridan and Seminole. The extra, work compensation was based on the actual cost of materials, the labor, and equipment rates contained in the bid.
A provision was provided for payment of shutdown rates on days when pipe could not be laid because of Seminole’s failure to provide the right-of-way. The first right-of-way problems began shortly after the start of construction, when Sheridan’s crews worked up to a property in which the easement had not been obtained. Sheridan recorded the shutdown days, submitted the charges, and was paid.
Other situations occurred where there was no right-of-way and the crews moved around the tract and worked on other tracts. When these “move arounds” occurred, the parties prepared a memorandum containing; (1) the location moved from; (2) the location moved to; (3) the men and equipment involved; and (4) the time consumed, and both parties signed the document. Also, the chief inspector for Seminole made a detailed explanation of the “move around” and approved a memorandum of work performed, which was signed and accepted by Sheridan’s superintendent. Sheridan would then include those charges, and Seminole paid such charges.
In point of error one, Sheridan contends that the trial court erred in denying it’s motion for new trial, arguing that the jury’s negative answer to special issue 1, which asked: “Do you find [from] a preponderance of the evidence that Seminole failed to provide Sheridan with right-of-way in a reasonable time?”, was against the great weight and preponderance of the evidence.
Where a contract does not fix a time for performance, a reasonable time is allowed.
See Heritage Resources, Inc. v. Anschutz Corp.,
Some courts have held that where a jury fails to find a vital issue in favor of a party having the burden of proof on the issue, that party, to complain on appeal, must show that the evidence “conclusively” established the issue “as a matter of law.”
See Pouncy v. Garner,
Thus, we do not follow the rationale of those decisions in this case, which involves a “factual sufficiency” complaint that the jury’s negative finding is against the great weight and preponderance of the evidence. We believe the proper standard of review in such a case is that enunciated in
In re King’s Estate,
Under the Supreme Court’s decision in
Pool,
and in view of the interpretation generally accorded to Judge Calvert’s article over the years, we conclude that we are required to follow the
In re King’s Estate
standard of review in all “factual sufficiency” cases, whether we review a negative or affirmative jury finding and regardless of whether the complaining party had the burden of proof on the issue. That is, where the complaining party asserts that either an affirmative or a negative finding is against the great weight and preponderance of the evidence, we must review all the evidence, both for and against the issue, and determine whether the finding is so against the great weight and preponderance of the evidence as to be manifestly unjust.
Pool,
The Texas Supreme Court in
Pool
also advised that intermediate courts, when reviewing factual insufficiency points, should detail all the evidence relevant to the issue. Thus, we are admonished in such cases to “clearly state why the jury’s finding is factually insufficient or is so against the great weight and preponderance of the evidence as to be manifestly unjust; why it shocks the conscience; or clearly demonstrates bias.” We are also instructed to specify in our opinions “in what regard the contrary evidence greatly outweighs the evidence in support of the verdict.”
Pool,
Under the circumstances of the case, which showed the standard procedures used in the trade, we conclude that the trial court did not err in denying a new trial, because it was not so against the great weight and preponderance of the evidence that Seminole did not provide the right-of-ways in an unreasonable amount of time so as to be manifestly unjust. The jury, as the trier of fact, was entitled to judge the credibility of the witnesses, assign the weight to be given their testimony, and resolve any conflicts or inconsistencies in the evidence.
See Taylor v. Lewis,
Point of error one is overruled.
In point of error two, appellant urges that the trial court erred in granting appel-lee’s motion for directed verdict on fraud.
A directed verdict is appropriate only when reasonable minds could reach but one conclusion under the available evidence.
See Vance v. My Apartment Steak House of San Antonio, Inc.,
To prevail on a cause of action for fraud, a party must show:
(1) that a material representation was made,
(2) that it was false,
(3) that when the speaker made it, he knew it was false or made it recklessly without any knowledge of the truth and as a positive assertion,
(4) that it was made with the intent that it should be acted on by the party,
(5) that the party acted in reliance upon it, and
(6) that the party thereby suffered injury-
Stone v. Lawyers Title Ins. Corp.,
If Sheridan introduced some evidence on each of the elements for fraud, then the trial court erred in granting Seminole’s motion for directed verdict.
See Koenning v. Manco Corp.,
Sheridan’s general manager testified that Seminole made no written representations about the status of its right-of-way acquisition prior to or at the time of signing the agreement, and that Seminole never made any oral representation that it had already obtained or would shortly obtain all of the right-of-ways. His testimony also indicates that the right-of-ways would have been acquired by the time Sheridan needed access to the property.
Failing to discharge a promise to do an act in the future is not fraud unless the promise is made with the intent not to perform.
See Mann v. Fitzhugh-Straus Medina Ranch,
The record does not indicate that Seminole made any oral misrepresentation about the agreement to acquire the right-of-ways, and on the contrary, the contract itself stated problems in acquiring the right-of-ways, and contained certain provisions that would compensate Sheridan if shutdown or extra work occurred due to Seminole’s failure to acquire the needed right-of-ways. Further, the evidence reveals that Seminole made full disclosure of the status of the right-of-ways and the efforts being made to acquire the rest of them on the first day of construction.
Sheridan failed to prove the elements of fraud, and the trial court did not error in granting a directed verdict against Sheridan’s fraud cause of action.
Point of error two is overruled.
In point of error three, appellant asserts that the trial court erred in granting appel-lee’s motion for directed verdict on quantum meruit.
Recovery on an express contract and on quantum meruit are inconsistent.
See Woodard v. Southwest States, Inc.,
To recover under quantum meruit, one must prove:
(1) valuable sendees were rendered or materials furnished,
(2) for the person sought to be charged,
(3) the services and materials were accepted by the person sought to be charged, and
(4) under such circumstances as would reasonably notify the person sought to be charged that the plaintiff, in performing such services was expected to be paid by the person sought to be charged.
Garza v. Mitchell,
The record reveals no evidence of the reasonable value of the work performed on the “move arounds.” A witness for Sheridan testified that he had been hired to substantiate the “cost overruns” on the project, but did not testify to the reasonable value of the work performed as beneficial services rendered. He stated that the $267,195 worth of damage claims were the result of both direct and indirect labor costs, and that Sheridan’s general manager had asked for the actual costs spent on the job. These calculations represented damages for breach of contract, not for quantum meruit.
In
Air Conditioning, Inc.,
The court in
Black Lake Pipe Line Co. v. Union Const. Co.,
The trial court did not err in granting a directed verdict on the quantum merit claim.
Point of error three is overruled.
The judgment is affirmed.
