60 Minn. 532 | Minn. | 1895
There is absolutely nothing in appellant’s assignments of error numbered from 1 to 4, inclusive. The fifth goes to the question of the sufficiency of the evidence to sustain the verdict in plaintiff’s favor.
The action «was brought to recover a balance claimed to be due him upon a contract for the building of two retaining walls, one on each side of a driveway leading from the street towards the rear of a lot owned by defendant. The defense was that neither of the walls was built as high or as long as agreed upon, and that one was constructed so that there was a bulge at its base, commencing some 15 feet from the street, extending about 30 feet to the rear, along the way, and about 4 feet above the surface of the ground. This bulge was at one place some 9 inches, so that at that point the driveway was but 9 feet wide, while at each end it was 9 feet 9 inches. From the testimony of the plaintiff, it appeared that he went' upon the ground with the defendant, and was then told to about what height the walls were to be built with reference to the surface of the lot on either side. He was also told that plans for the work were being prepared by a certain civil engineer, and to go and see them. He then called at the engineer’s office, and was shown plans for the elevations, complete in all respects, except that there was nothing to
We are of the opinion that on the evidence the- conclusion, of the jury that plaintiff had performed his contract in a good and workmanlike manner, as he had agreed to do, cannot-be sustained. He
Tn view of another trial, we will briefly allude to the claim of defendant that plaintiff did not build the walls as high and as long as required by his contract. If he did not, and as to this we need not express an opinion, we think that the evidence would have justified a finding that defendant waived his right to insist upon a strict compliance in this respect with the requirements shown by the plans.
Order reversed.