19 Mont. 548 | Mont. | 1897
The objection raised by defendant’s demurrer that the complaint is ambiguous and uncertain cannot avail him on this appeal. By answering after his demurrer was overruled, he waived it.
Does the complaint state a cause of action?
We think it does. However defectively, it nevertheless states a cause of action. Defendant filed his answer, and the case was tried on issues raised. In the answer, the defendant assumed that allegations were in the complaint which it should properly have contained, but did not; in other words, the answer supplied the omission in the complaint. See Hamilton v. Railway Co., 17 Mont. 334, 42 Pac. 860, and 43 Pac. 713.
Did the court err in instructing the jury that the failure on the part of plaintiff to complete the entire building by September 1, 1893, was no defense to the action?
Some evidence was offered in behalf of defendant to show that by reason of the noise that would result in connection with the completion of the lower part of the building after September 1, 1893, guests or lodgers who might be occupying rooms in the
There was no mixed question of lawr and fact. It was one of law alone, under the facts and the pleadings. Time was not expressly- made the essence of the contract by its terms. .The defendant did not expressly plead, and did not attempt
“In contracts for the sale of land, or for the performance of services, or the construction of buildings, time will be held of the essence if, from the nature of the property and the circumstances, it seems that the parties must have so intended, but generally, in such contracts, time is not of the essence. ’ ’
The question whether or not time was the essence of this contract, under the facts of this case, was for the court to determine, and not the jury. But the use of the word “building” in the habendum clause of the lease, was rather by way of description than otherwise. When the two upper stories were finished and ready for occupancy, the contract was substantially performed.
We are of the opinion that the lower court committed no error in this respect. If defendant had been damaged by plaintiff’s delay in completing the entire building, he could have pleaded wherein he was damaged. But he did not do so.
From the pleadings and from the . evidence, it clearly appears that defendant relied absolutely upon his right to reject and repudiate the contract, simply because the entire building had not been completed on September 1, 3893. This, as we have shown, he had no right to do.
The order denying the motion for a new trial and the judgment are both affirmed.
Affirmed.