119 So. 2d 58 | Fla. Dist. Ct. App. | 1960
This appeal is by an owner of real property from a final decree awarding material-man’s liens in favor of certain material-men and subcontractors who furnished materials and labor in the construction of a building erected on the property in question. Since the only issue on appeal involves an interpretation of a provision of the contract pursuant to which the improvements were made, a detailed statement of all the facts is not deemed necessary.
When the appellant-owner entered into the contract for the construction of improvements on the property involved herein, no performance bond was either demanded of nor furnished by the contractor. The contract consisted of a typewritten document entitled “Agreement”, a set of drawings, and a mimeographed pamphlet entitled “Specifications”. The agreement provides that it, together with the drawings and specifications, shall form the entire contract between the parties. The agreement sets forth the contract price of the improvements, and specifies ten different stages of the construction upon completion of which progress payments will be made in an amount not to exceed 80% of the contract price of each estimate The appellee-lienors were only furnished a copy of the specifications on which they, relied in furnishing the materials and performing the work which formed the subject matter of their claims. One paragraph of the general conditions contained in the specifications is as follows:
“24. Payments: (Applications for Payments)
“On or before the fifth day of each month, the Contractor shall submit to the Owner application for payment for work performed during the preceding month. Application shall list Subcontract material and labor accounts completely, and be supported by receipts, vouchers or waivers of lien,' filed with the Owner within 10 days from the receipt of any payment. Failure to submit receipts will be grounds for withholding further payments on the Contract. Title for materials stored on the site must be conveyed to the Owner upon payment for such materials by the Owner. * * * ”
The owner, in making periodic progress payments to the contractor, did not require that each application for payment list subcontract material accounts supported by receipts, vouchers or waivers of lien. The owner did, however, withhold 20% of each progress estimate as required by the Mechanics Lien Law.
The chancellor held that all progress payments made by the owner to the contractor subsequent to a certain specified date were improper payments within the purview of Sec. 84.05(8) of the Mechanics Lien Law. The chancellor’s conclusion that payments had been improperly made is based upon his interpretation of the above quoted section of the contract which he held had not been complied with prior to the making of such payments by the owner. Having so concluded, the chancellor held that after deducting from the con
Reverting to the provision of the contract on which the chancellor based his conclusion we find it provides that the contractor shall submit to the owner application for payment for work performed during each preceding month. It provides that each application shall list subcontract material and labor accounts completely, and be supported by receipts, vouchers or waivers of lien filed with the owner within ten days from the receipt of any payment. Failure to submit receipts will be grounds for withholding further payments on the contract. It is apparent that the court found and so held that this provision was one for the benefit of third parties such as the materialmen and subcontractors involved in this case, as well as for the benefit of the owner. Implicit in the court’s holding is the conclusion that by the provision of the contract the owner was lawfully precluded from making any payments to the contractor until the requirement set forth therein had been fully complied with.
Our construction of this provision of the contract is not in harmony with the interpretation placed thereon by the chancellor. From a literal reading of the contract provision it is clear to us that it is solely and exclusively for the benefit of the owner. Appellees have cited no authorities in their brief, and our research reveals none, which would support a contrary conclusion. Such a provision was reasonably necessary for the owner’s protection in light of the fact that no performance bond was being required of the contractor. The requirement that each application for progress payment be accompanied by a list of all subcontract materials and labor accounts incurred during the previous month and be supported by receipts, vouchers or waivers of lien, not being required by the Mechanics Lien Law for the protection of materialmen, could at the option of the owner either be insisted upon as a prerequisite for making progress payments, or could be waived by him. This is apparent from that sentence of this section which provides that failure to submit receipts will be grounds for withholding further payments on the contract. Implicit in this provision is the right of the owner to withhold progress payments under the contract unless the stipulated prerequisites have been met, and conversely the right to waive compliance with such-prerequisites and make progress payments if he considers it to be to his interest to do so. Payments so made cannot be considered as violative of the lienors’ rights under the law.
We therefore hold that the payments made by the owner to the contractor in compliance with Sec. 84.05(11) (a) were proper payments under the contract, even though the requirements of the general provisions of the contract calling for the sub
The decree appealed from is reversed with directions that an appropriate decree be entered in accordance with the views expressed herein.
Reversed.
. F.S. Sec. 84.05(11) (a), F.S.A.
. F.S. Sec. 84.04(1), F.S.A.
. All State Supply Co. v. McNair, Fla.1956, 89 So.2d 774.