169 Iowa 669 | Iowa | 1914
— I. On July 6, 1910, the Independent School District of Independence entered into a contract with George A. Netcott for the erection of a school building in the city of Independence. As a guaranty for the performance of his contract, Netcott gave his bond with sureties. Before the completion of the work, Netcott made an assignment for the benefit of his creditors to one Bain. At that time, there had been paid to the contractor on the work and for extras $38,-100.00. In addition to this, about two months after entering upon the work, Netcott purchased from the school district two old buildings for $202.50, which it was then agreed should be applied on the contract as part payment. Later, insurance was placed on the building at a cost of $90.00, for the one-third of which Netcott became liable, and this also, it was agreed, should be applied on the contract, payment of the entire amount of the insurance having been made by the district. October 5,1911, two days after the assignment to Bain, the school district served notice on the bondsmen to complete the work aecording'to the contract, which they refused to do. Thereupon, the officers of the school district took charge of the building, completed it according to the requirements of the contract, expending therefor the sum of $1,042.12 for materials, and $1,030.47 for labor. The contract did not in terms authorize the builder to complete the work upon default of the contractor. The contract price was $46,671.07. Pay
The contention of the plaintiff in the court below and here is:
1. That when the contract does not authorize the district to complete the work upon failure of the contractor to do so, the contract and bond must be- construed together so as to require the district to recover from the bondsmen the amount necessary to complete the contract, instead of deducting it from the contract price.
2. That the credit on the contract price of $232.50 for the old buildings and the insurance, being based on agreements made after the execution of the contract and the commencement of the work, was not contemplated by the contract and should not be allowed.
A third question was raised as to the sufficiency in form of plaintiff’s verified claim.
The trial resulted in a finding and decree against plaintiff and it appeals.
By reason of his insolvency and the assignment for the • benefit of his creditors, Netcott was unable to fully comply with the contract. As to this conclusion no question is raised in the record. The sureties on his bond refused to complete the building. It was then in effect a breached contract. The owner was entitled to the benefit of its bargain and to have the building completed at no greater cost to it than the contract price. Aetna Iron Works v. Kossuth Co., 79 Iowa 40; 6 Cyc. 74. Should the cost exceed the balance due, a question as to the liability of the bondsmen would arise, which is not now in this case. The right to complete the building under such conditions cannot be made to depend upon a provision of the contract authorizing such to be done, but rests upon the elemental ground that a party to a contract not broken through his fault is entitled to its benefits; and when an expenditure of money is necessary to protect and complete that which is already in his possession, as a result of part performance, such expenditure may be made and recovery had for it. This
On the whole record the judgment should be and it is— Affirmed,.