Opinion
The plaintiff, Seniel Lucien, appeals from the judgment of the trial court denying her application to discharge the mechanic’s lien filed by the defendant, McCormick Construction, LLC. On appeal, the plaintiff claims that the court improperly concluded that the defendant satisfied its burden of establishing that the plaintiff asserted violations of the Home Improvement Act (act), General Statutes § 20-418 et seq., in bad faith. We reverse the judgment of the trial court.
The parties stipulated to the following facts. In late 2005, the parties commenced negotiations on a contract for the defendant to renovate a residence in Chester that the plaintiff later purchased. On December 13,2005, the defendant sent a proposed contract to the plaintiffs representative, Arlene Boop, an attorney based in New York. The two sides negotiated the terms of the contract, and, on March 20, 2006, the defendant sent Boop a copy of the contract and other related documents, including a “ ‘notice of cancellation.’ ” The plaintiff, however, never signed the contract or any document acknowledging receipt of the notice of cancellation.
The defendant began work on the plaintiffs residence in early May, 2006. From May, 2006, through May, 2007, the defendant sent invoices totaling $323,917.99 to the plaintiff. Of this total, $207,453 represented the original contract price, and the $116,464.99 balance was the result of change orders. The plaintiff has paid the defendant a total of $211,781.28, and the defendant claims that the plaintiff owes it a balance of $82,698.36.
From at least March, 2007, the plaintiff has communicated to the defendant that she disputes the amount the defendant claims that she owes, the change orders and whether the contract was properly or fully performed by the defendant. Additionally, the plaintiff has maintained that the defendant was responsible for delays in performance under the contract, though the defendant contends that the plaintiff was to blame for any delays.
On or about May 16, 2008, the defendant filed a mechanic’s lien with the town of Chester claiming a lien in the principal amount of $99,824.85 against the plaintiffs
In its memorandum, the court noted that, based on the stipulated facts, it was unquestionable that the contract violated the act because it was not signed in violation of General Statutes § 20-429 (a) (2), a notice of cancellation was not attached to the contract in violation of General Statutes § 42-135a (2) and the contract failed to provide notice of the homeowner’s right to cancellation in violation of § 42-135a (1). Thus, the dis-positive issue was “whether noncompliance with the act is excused because [the] plaintiff has asserted this defense in bad faith.” After reviewing the facts, the court concluded that “under these circumstances, the defendant has satisfied [its] burden of proving that the plaintiff has acted in bad faith in asserting . . . violations [of the act]. While it is true that [the] plaintiff did make substantial payments on the contract, it is notable that she did not dispute any moneys owed, or the defendant’s performance, until shortly before the final balance was rendered in May, 2007. There is no record evidence to suggest that from the commencement of the construction process in March, 2006, until March, 2007, she registered any complaints about the invoice amounts, delays in performance or the quality of [the] defendant’s work. Further, it is undisputed that although the contract failed to comply with the [act]
in a number of material respects, no mention of noncompliance was raised until almost eighteen months after work on the project commenced. [The] [p]laintiff correctly points out that it would be unusual for a party to a contract to
On appeal, the plaintiff claims that the defendant failed to satisfy its burden of establishing that she asserted violations of the act in bad faith. Specifically, she argues that the bases supporting the court’s finding of bad faith—her failure to raise the violations of the act until after the completion of the project and that she was represented by counsel during negotiations— are not, without more, evidence of bad faith. We agree.
Prior to evaluating the plaintiffs claim, we must first articulate the relevant standard of review. “Because the parties have stipulated to the relevant facts, our review is plenary and we must determine whether the trial court’s conclusions of law are legally and logically correct and find support in the stipulated facts.” (Internal quotation marks omitted.)
Ace Equipment Sales, Inc.
v.
H.O. Penn Machinery Co.,
“The principles governing the . . . claim of bad faith are well established. In
Barrett Builders
v.
Miller,
[215
Conn. 316, 328,
As it was the defendant that
In
Wadia Enterprises, Inc.
v.
Hirschfeld,
The court also concluded that the plaintiff acted in bad faith on the basis that she waited until “the eleventh hour” to raise the violations of the act, which the
The judgment is reversed and the case is remanded with direction to grant the plaintiffs application to discharge the defendant’s mechanic’s lien.
In this opinion the other judges concurred.
Notes
The difference in the amount of the lien and the amount now claimed by the defendant is the result of a payment to a vendor after the initial calculation of the amount of the lien.
General Statutes § 49-35a (a) provides: “Whenever one or more mechanics’ liens are placed upon any real estate pursuant to sections 49-33, 49-34, 49-35 and 49-38, the owner of the real estate, if no action to foreclose the lien is then pending before any court, may make application, together with a proposed order and summons, to the superior court for the judicial district in which the lien may be foreclosed under the provisions of section 51-345, or to any judge thereof, that a hearing or hearings be held to determine whether the lien or liens should be discharged or reduced. . . .”
General Statutes § 49-35b provides: “(a) Upon the hearing held on the application or motion set forth in section 49-35a, the lienor shall first be required to establish that there is probable cause to sustain the validity of his lien. Any person entitled to notice under section 49-35a may appear, be heard and prove by clear and convincing evidence that the validity of the lien should not be sustained or the amount of the lien claimed is excessive and should be reduced.
“(b) Upon consideration of the facts before it, the court or judge may: (1) Deny the application or motion if probable cause to sustain the validity of the lien is established; or (2) order the lien discharged if, (A) probable cause to sustain its validity is not established, or (B) by clear and convincing evidence its invalidity is established; or (3) reduce the amount of the lien if the amount is found to be excessive by clear and convincing evidence; or (4) order the lien discharged or reduce the amount of the lien conditioned upon the posting of a bond, with surety, in a sum deemed sufficient by the judge to indemnify the lienor for any damage which may occur by the discharge or the reduction of amount.”
The defendant argues that the issue before that court was “whether there [was] probable cause to sustain the validity of the lien because of the plaintiffs bad faith.” The defendant provides no support for the proposition that he must provide only probable cause of bad faith, and we could find none. Although it is true that under § 49-35b (a); see footnote 3 of this opinion; the defendant needed only to show probable cause to sustain the validity of the lien, once this burden was met, the burden shifted to the plaintiff to “prove by clear and convincing evidence that the validity of the lien should not be sustained . . . .” General Statutes § 49-35b (a). It was at this point that the plaintiff raised the issue of the defendant’s noncompli- anee with the act, and, in order to defeat this claim and prevent the plaintiff from meeting her burden, the defendant asserted, and had to establish, the existence of bad faith.
Although we note that at a hearing to discharge a mechanic’s lien, “the [lienor] does not have to establish that he will prevail”; (internal quotation marks omitted)
36 DeForest
Avenue,
LLC
v.
Creadore,
The stipulation of facts does not make clear in what states Boop is admitted to practice law. It describes her only as “a New York based attorney.” On the basis of the stipulation, we cannot conclude that she is admitted to practice law in Connecticut and, thus, will not charge her with the burden of knowledge of the act.
The only case cited by the defendant to support its claim of bad faith is
Menillo
v.
Brian Calandro Associates, LLC,
Superior Court, judicial district of Fairfield, Docket No. CV-08-5014822 (July 30, 2008). The
Menillo
case, which held that failure to raise defects of a contract until after a contractor filed its mechanic’s lien was evidence of bad faith, is contrary to appellate precedent; see
Wadia Enterprises, Inc.
v.
Hirschfeld,
supra,
