MICHAEL LUCCHESI et al., Appellants, v CESAR PERFETTO et al., Respondents.
Supreme Court, Appellate Division, Second Department, New York
March 30, 2010
899 N.Y.S.2d 341 | 72 A.D.3d 909
Covello, J.P., Florio, Miller and Eng, JJ.
[Prior Case History: 2008 NY Slip Op 33119(U).]
Ordered that the order is modified, on the law, (1) by deleting the provision thereof granting that branch of the defendants’ motion which was for summary judgment dismissing the first cause of action to recover damages for nuisance, and substituting therefor a provision granting that branch of the motion only to the extent that it seeks damages for acts of nuisance alleged to have occurred more than three years prior to the commencement of this action, and otherwise denying that branch of the motion, and (2) by deleting the provision thereof granting that branch of the defendants’ motion which was for summary judgment dismissing the second cause of action to recover damages for trespass, and substituting therefor a provision granting that branch of the motion only to the extent that it seeks damages for acts of trespass alleged to have occurred more than three years prior to the commencement of this action, and otherwise denying that branch of the motion; as so modified, the order is affirmed, without costs or disbursements.
On September 5, 1996, the defendants purchased a vacant parcel of land in Staten Island. Over the next several months, the defendants constructed a new house on their property, which was completed in late 1996 or early 1997. During construction, a contractor deposited fill consisting of topsoil and dirt on the defendants’ property, which raised the elevation grade of the property approximately five to six feet. The defendants admit that some of the fill was also deposited on the adjacent parcel of property located to the southeast of their premises, which was vacant at the time they constructed their home. More than four years later, on August 14, 2001, the plaintiffs purchased the adjacent southeast parcel, and also constructed a new home on it.
On or about November 21, 2003, the plaintiffs commenced this action against the defendants seeking, inter alia, to recover
Contrary to the plaintiffs’ contention, the Supreme Court properly awarded summary judgment to the defendants dismissing the fifth cause of action to recover damages for negligence, which is predicated upon the defendants’ alleged failure to ensure that the elevation grade of their property was raised in a safe manner. The defendants made a prima facie showing that the negligence claim was barred by the applicable three-year statute of limitations (see
However, the Supreme Court erred in concluding that the
Furthermore, we reject the defendants’ contention that they are entitled to summary judgment dismissing the plaintiffs’ nuisance claim in its entirety upon the alternate ground that the sole proximate cause of the plaintiffs’ damages was their failure to install a retaining wall. Although the plaintiffs’ failure to install a retaining wall in accordance with the recommendations of their builder and architect may constitute culpable conduct, it is not a complete bar to recovery (see
The plaintiffs’ remaining contentions are without merit.
Covello, J.P., Florio, Miller and Eng, JJ., concur.
