LTTS Charter School, Inc. v. C2 Construction, Inc.LTTS Charter School, Inc. v. C2 Construction, Inc.
OPINION ON REMAND
Opinion By
In this interlocutory appeal, LTTS Charter School, Inc. d/b/a Universal Academy (“Universal Academy”) appeals the trial court’s denial of its plea to the jurisdiction based on immunity from suit. On original submission, this Court concluded it did not have jurisdiction over the interlocutory appeal because Universal Academy, which is an open-enrollment charter school, was not a “governmental unit” for purposes of an interlocutory appeal under section 51.014(a)(8) of the Texas Civil Practice and Remedies Code.
See LTTS Charter Sch., Inc. v. C2 Constr., Inc.,
We construe Universal Academy’s three issues on appeal to assert (1) the trial court erred by denying Universal Academy’s plea to the jurisdiction; (2) even if Universal Academy waived its immunity from suit by filing counterclaims, Universal Academy subsequently dismissed those counterclaims and thereby regained such immunity; and (3) the facts of this case do not meet the requirements for waiver of immunity by entry into a contract pursuant to chapter 271, subchapter I, of the Texas Local Government Code. See Tex. Loc. Gov’t Code Ann. §§ 271.151-.160 (West 2005 & Supp. 2010) (titled “Adjudication of Claims Arising Under Written Contracts With Local Government Entities”).
Appellee C2 Construction, Inc. (“C2 Construction”) raises five “cross points,” in which it argues (1) Universal Academy was performing, in part, a proprietary function, and any immunity of Universal Academy does not apply to such functions; (2) immunity from suit for charter schools is precluded by the fact that immunity from liability was granted by the Legislature’s enactment of section 12.1056 of the education code,
see
We affirm the trial court’s order, in part, and reverse, in part. Further, we render judgment granting Universal Academy’s plea to the jurisdiction, in part, and remand this case to the trial court for further proceedings in accordance with this opinion.
I. FACTUAL AND PROCEDURAL BACKGROUND
Universal Academy retained C2 Construction to construct school facilities at a site leased by Universal Academy in Dallas County (the “Project”). After construction proceeded for several months, a dispute arose over the amount owed by Universal Academy to C2 Construction.
On April 4, 2006, C2 Construction filed this lawsuit. In its last-filed petition at the time of the challenged interlocutory order, C2 Construction asserted claims against Universal Academy and Reklaw Partnership, Inc. (“Reklaw”),
1
the owner of the site leased by Universal Academy, for (1) breach of contract, (2) quantum meruit and unjust enrichment, (3) “enforcement of lien affidavit,” (4) interest, and (5) attorney’s fees. Additionally, C2 Construction asserted a claim against Universal Academy for violation of
Universal Academy filed a general denial answer in which it asserted several affirmative defenses, including sovereign immunity. Additionally, on that same date, Universal Academy filed counterclaims against C2 Construction for breach of con
Next, Universal Academy filed (1) a notice of non-suit without prejudice as to its counterclaims and (2) a plea to the jurisdiction on the grounds that Universal Academy is immune from suit on the claims at issue “based on the doctrine of sovereign immunity” and such immunity has not been waived by Universal Academy. In its plea to the jurisdiction, Universal Academy argued, in part, (1) “charter schools are granted the same governmental immunities as public school districts,” including immunity from suit; (2) any immunity waived by Universal Academy as a result of its counterclaims was restored when such counterclaims were withdrawn; and (3) the criteria for waiver of immunity by written contract under local government code section 271.152 have not been met in this case.
C2 Construction responded, contending,
inter alia,
(1) the only immunity Universal Academy has is that granted by the Legislature, i.e. immunity from liability pursuant to education code
Subsequently, Universal Academy filed a supplement to its plea to the jurisdiction in which it asserted C2 Construction’s
Following a hearing, Universal Academy’s plea to the jurisdiction was denied by the trial court. Universal Academy appealed to this Court pursuant to
After granting Universal Academy’s petition for review, the Texas Supreme Court stated the “narrow issue” to be addressed as follows: “Is an open-enrollment charter school a ‘governmental unit’ as defined in Section 101.001(3)(D) of the Tort Claims Act and thus able to take an interlocutory appeal from a trial court’s denial of its plea to the jurisdiction?”
LTTS Charter Sch.,
II. DENIAL OF UNIVERSAL ACADEMY’S PLEA TO THE JURISDICTION
A. Standard of Review and Applicable Law
Whether a trial court has subject matter jurisdiction is a matter of law that is reviewed de novo.
See Tex. Dep’t of Parks & Wildlife v. Miranda,
A party may challenge the trial court’s subject matter jurisdiction by filing a plea to the jurisdiction.
Miranda,
When a plea to the jurisdiction challenges the existence of jurisdictional facts, the trial court must consider the relevant evidence submitted by the parties when necessary to resolve the jurisdictional issue.
See City of Waco v. Kirwan,
B. Analysis
1. Universal Academy’s Governmental Immunity From Suit
Under the common-law doctrine of sovereign immunity, the state cannot be sued without its consent.
City of Houston v. Williams,
In its appellate argument pertaining to its first issue, Universal Academy contends the trial court erred by denying its plea to the jurisdiction because it is immune from suit by virtue of section 12.103(a) of the education code. That section provides in part that “an open-enrollment charter school is subject to federal and state laws governing public schools.”
C2 Construction responds, in relevant part, (1) the immunity from liability provided to charter schools in
We first address C2 Construction’s contention, asserted in its second “cross point,” that
Neither party asserts, and the record does not show, that the language of
At this juncture, we address the question raised in Universal Academy’s first issue as to whether, indeed, Universal Academy has immunity from suit. The parties have argued about whether the Legislature has purported to make a “grant” of immunity from suit to charter
In reversing this Court’s previous judgment in this case, the Texas Supreme Court stated, “[W]e reserve judgment on [Universal Academy’s] immunity from suit, an issue not before us.”
See LTTS Charter Sch.,
We decide in favor of Universal Academy on its first issue to the extent that issue asserts Universal Academy has immunity from suit. We decide against C2 Construction on its second “cross point.”
2. Proprietary Functions
Next, having concluded Universal Academy is entitled to governmental immunity, we consider C2 Construction’s first “cross point,” in which it asserts that even if Universal Academy is entitled to immunity from suit, such immunity is limited to those acts that further a governmental function. C2 Construction contends Universal Academy “carries out proprietary functions by using for private purposes a portion of the facilities that C2 built.” According to C2 Construction, (1) Universal Academy “subleases a significant portion of the facility to the Universal Satori Learning Center for a fee, even though Satori is operated by the same individuals who are on [Universal Academy’s] board”; (2) “[s]ince Satori existed prior to the Project, it is clear that [Universal Academy] intended for part of the Project to provide a home for the Satori school to be operated by the same individuals that run [Universal Academy]”; and (3) C2 Construction’s claims and liens extend to the space leased by Satori. Additionally, C2 Construction asserts “the facility in question is not a public facility” and the “compensation that C2 received” came predominantly from private funds.
In support of its argument, C2 Construction cites (1) documents listing the board members and staff of Universal Academy and the directors of Satori; (2) an affidavit of Janice Blackmon, Universal Academy’s director of administrative services, in which she testified, inter alia, that Universal Academy leases property from Reklaw and received funds from Reklaw for the Project; (3) an affidavit of Charles Coleman, president of C2 Construction, in which he stated, inter alia, that it was his understanding that Reklaw was funding the Project; (4) a request for admissions in which Universal Academy admitted that Reklaw paid C2 Construction for the work at issue; and (5) several printed pages stating the tuition, policies, and schedule of Satori.
Cities and towns have been recognized as exercising dual functions, to wit, governmental and proprietary.
See Tooke,
C2 Construction cites no authority, and we have found none, addressing the applicability of the proprietary-governmental dichotomy to open-enrollment charter schools:
Cf. Galveston Indep. Sch. Dist. v. Clear Lake Rehab. Hosp., L.L.C.,
We decide against C2 Construction on its first “cross point.”
3. Claim Pursuant to
In C2 Construction’s fifth “cross point,” it argues that even if Universal Academy “enjoys full governmental immunity” the trial court has jurisdiction to hear C2 Construction’s claim under
In a supplement to its plea to the jurisdiction, Universal Academy contended C2 Construction has not invoked the trial court’s jurisdiction as to its
On appeal, Universal Academy contends “the law does not recognize a viable action under [
Every person who, under color of any statute, ordinance, regulation, custom, or usage, of any State ... subjects, or causes to be subjected, any citizen of the United States or other person within the jurisdiction thereof to the deprivation of any rights, privileges, or immunities secured by the Constitution and laws, shall be liable to the party injured in an action at law.
The record shows that in its live petition, C2 Construction “incorporated by reference and reaverred” paragraphs one through fifty-five of that petition in its
We conclude the trial court did not err by denying Universal Academy’s plea to the jurisdiction as to C2 Construction’s
4. Effect of Counterclaims and Non-Suit
In its second issue, Universal Academy asserts that any immunity from suit that it may have “partially waived” by filing its counterclaims was “fully restored” when it dismissed those counterclaims. 7 C2 Construction argues Universal Academy should not be allowed to “avoid C2’s claims by simply withdrawing its counterclaim to revive its sovereign immunity defense” after more than fifteen months of litigation because that would be “fundamentally unfair” and “substantially prejudice” C2 Construction.
While this appeal was pending, the Texas Supreme Court issued its opinion in
City of Dallas v. Albert,
Then, the supreme court reasoned that because a governmental entity does not have immunity from suit as to claims in the first category once it files its counterclaims, it cannot “either ‘reinstate’ such immunity, or, put differently, in effect create it, by non-suiting.” Id. Rather, the supreme court concluded, a trial court retains jurisdiction over a plaintiffs claims to the extent it has acquired it. Id. at 375. However, the supreme court explained, although a trial court has jurisdiction over a plaintiffs claims that would have been offsets to a governmental entity’s counterclaims, after a non-suit of the governmental entity’s claims, the governmental entity no longer has claims for recovery that the plaintiffs claims could offset. Id. Thus, the supreme court reasoned, after the City’s non-suit, the Albert plaintiffs “could not prevail on their breach of contract claims because they could not recover a judgment for damages and the City was not pursuing a claim for damages to which an offset would apply.” Id.
We conclude Universal Academy has no immunity from suit as to claims of C2 Construction that would have offset, in
We decide against Universal Academy on its second issue.
5. Waiver of Immunity Pursuant to § 271.152
Now, we address whether Universal Academy’s immunity from suit was waived pursuant to Texas Local Government Code section 271.152.
“[E]ven if the State acknowledges liability on a claim, immunity from suit bars a remedy until the Legislature consents to suit.”
Learners Online,
Under section 271.152, which is contained in subchapter I of local government code chapter 271, “[a] local governmental entity that is authorized by statute or the constitution to enter into a contract and that enters into a contract subject to this subchapter waives sovereign immunity to suit for the purpose of adjudicating a claim for breach of contract.” Tex. Local Gov’t Code Ann. § 271.152;
Learners Online,
“Written” contracts may be embodied in more than one document.
See Williams,
In its third issue, while Universal Academy asserts it is a “local government entity” for purposes of section 271.152, it contends the criteria of that section have not been satisfied. Specifically, Universal Academy argues the requirements of section 271.152 are not met because the contract at issue is “oral,” not a “written contract,” does not state the “essential terms of the agreement,” and was not “properly executed.”
C2 Construction contends in. its third “cross point” that Universal Academy is not subject to section 271.152 because it is not a “local government entity” for purposes of section 271.152. C2 Construction argues that “charter schools are not included therein [section 271.151(3) ] and no statute otherwise equates charter schools or charter holders with public school districts for the purposes of such provisions.” Further, C2 Construction argues, even if Universal Academy qualifies as a “local government entity” for purposes of section 271.152, the record contains evidence that the conduct of Universal Academy’s board of directors and Blackmon “in approving the Project, retaining C2, receiving, but not signing a written contract, and acceptance of C2 Construction’s work” met the criteria for waiver of immunity from suit pursuant to that section.
The parties cite no ease law, and we have found none, specifically addressing whether an open-enrollment charter school is a “political subdivision” or “public school district” for purposes of the definition of “local governmental entity” in section 271.151(3).
See
Tex. Local Gov’t Code Ann. § 271.151(3);
ef.
In construing a statute, “[w]e presume the Legislature intended a just and reasonable result by enacting the statute.”
City of Rockwall v. Hughes,
In light of that conclusion, we next consider whether this case involves a “contract” as defined in section 271.151(2). See Tex. Local Gov’t Code Ann. § 271.151(2). The record reflects there is no dispute that, in fact, no written contract was signed by Universal Academy. C2 Construction pleaded, in relevant part, as follows: (1) “C2 and Defendants Universal and Reklaw entered into the Agreement which required C2 to perform certain specified work on the Project, and for Defendants Universal and Reklaw to pay for such work”; (2) “C2 performed the work required under the Agreement, but Defendants Universal and Reklaw failed to pay C2 in full for C2’s work on the Project”; (3) “[ajlthough C2 and Universal discussed the terms of a written agreement, Universal never signed the written agreement”; (4) “[a]s a result, C2 at least has an oral agreement to perform work on the Project and to receive payment for such work”; (5) “Universal never provided reasons why Universal did not sign the written contract for the project”; and (6) “Universal never advised C2 that C2 could not be paid because Universal did not sign the written contract for the Project.” Additionally, Coleman, president of C2 Construction, testified in an affidavit, inter alia,
At one point, when we met to discuss the cost of the Project and the Project budget, Ms. Blackmon told me that the school had $500,000 of its own money and $500,000 in matching money from Reklaw, setting the Project budget at $1 million.
[[Image here]]
Later, after Ms. Blackmon had expanded the Project still further, the cost of the Project rose to about $1,326 million. Mr. Akinwunmi [the architect] and I met with Ms. Blackmon to discuss that estimate and the Project budget, and to inquire as to whether we needed to trim the scope to match the money that the school had. When we met, Ms. Black-mon indicated that the financial arrangements had changed. Ms. Blackmon said to me and Mr. Akinwunmi that Reklaw was now funding the entire Project, and that the increased cost was not a concern. At that point, she no longer limited the amount of money that Reklaw was paying for the Project....
[[Image here]]
In July 2005,1 prepared a draft contract listing Universal as the owner of the Project, and submitted the draft contract to Ms. Blackmon at a meeting. Ms. Blackmon had comments and requested changes. Later in July 2005, I made the requested changes to the draft contract and resubmitted it to Universal. I still did not know with whom C2 would be contracting, and whether Universalor Reklaw would be signing the contract. As it turns out, neither Universal nor Reklaw signed the contract for C2’s work on the Project. On several occasions, I asked Ms. Blackmon how review of the draft contract was progressing. More than once, I asked Ms. Blackmon when the contract would be signed. Ms. Blackmon told me more than once that the lawyers were reviewing the contract. She never told me that Universal would not sign the contract.
C2 Construction argues the record shows the purported contract was “executed” because of the actions of Universal Academy’s board of directors. On January 13, 2005, Universal Academy’s board of directors unanimously passed a motion approving “the process of securing an appropriate facility” for its school campus for the 2005-2006 school year. Further, C2 Construction asserts that in response to C2 Construction’s second request for admissions, Universal Academy admitted (1) “Universal’s Board of Directors authorized Janice Blackmon to negotiate with C2 concerning the scope of the Project,” and (2) “Universal’s Board of Directors authorized Janice Blackmon to select a contractor for the Project.”
Responding, Universal Academy contends it “never saw or received a written contract from C2 Construction prior to or during the construction project” and “there is no written contract setting forth essential terms for this project.” Further, Universal Academy argues that its board “never considered a contract with C2 Construction,” no motion was passed approving of contracting with C2 Construction, and “no one on behalf of Universal Aeade-my executed any contract on behalf of Universal Academy.” Universal Academy cites deposition testimony of Blackmon that (1) with respect to C2 Construction, “We had an oral agreement”; (2) such agreement was that C2 Construction was hired to perform construction work at a price not to exceed $1 million; and (3) “We weren’t aware there was a contract ever produced until sometime after March and before May [2006].” 10
In support of its argument, C2 Construction cites Clear Channel Outdoor and asserts that case stands for the proposition that “where there is a written contract with a local government entity, although unsigned, and the governing board of the governmental entity has taken action to approve the contract, the written document and the governing board’s action taken together will constitute a written agreement.” However, that case is distinguishable.
In
Clear Channel Outdoor,
the City of Houston was engaged in a street repair project and needed an easement as to property on which a billboard sign owned by Clear Channel, Inc. (“Clear Channel”) was located.
See Clear Channel Outdoor,
On this record, we cannot conclude a fact issue exists as to whether a contract was “properly executed” on behalf of Universal Academy. See Tex. Local Gov’t Code Ann. § 271.151(2). Accordingly, there was no waiver of immunity from suit pursuant to that section as to C2 Construction’s claims. 11
We decide in favor of Universal Academy on its third issue and against C2 Construction on its third “cross point.”
6. Violation of Open Courts Doctrine
Finally, we address C2 Construction’s fourth “cross point,” in which it asserts that “[i]f Education Code
The “open courts” provision of the Texas Constitution “applies only to statutory restrictions of a cognizable common law cause of action.”
Peeler v. Hughes & Luce,
C2 Construction contends that, unlike sovereign immunity from suit arising out of common law, “the immunity conferred upon charter schools is solely a creature of statute,” specifically
Moreover, even assuming, without deciding, that the Legislature has authority to confer immunity from suit on charter schools, we cannot conclude
We decide against C2 Construction on its fourth “cross point.”
III. CONCLUSION
We conclude Universal Academy has governmental immunity from suit as to all claims of C2 Construction except (1) C2 Construction’s claim under
We decide in favor of Universal Academy as to part of its first issue and as to its third issue. Additionally, we decide in favor of C2 Construction on its fifth “cross point.” We decide each of the remaining issues and “cross points” against the asserting party.
We (1) affirm the portion of the trial court’s order denying Universal Academy’s plea to the jurisdiction as to C2 Construction’s
Notes
. Reklaw is not a party to this appeal.
. C2 Construction filed a motion to strike Universal Academy's supplemental plea to the jurisdiction on October 1, 2007. The record is silent as to the disposition of that motion.
. Immunity from liability was not asserted by Universal Academy in its plea to the jurisdiction and is not addressed in this opinion.
See Heard,
. The exceptions stated in
(b) An open-enrollment charter school is subject to this code and rules adopted under this code only to the extent the applicability to an open-enrollment charter school of a provision of this code or a rule adopted under this code is specifically provided.
(c) Notwithstanding Subsection (a), a campus of an open-enrollment charter school located in whole or in part in a municipality with a population of 20,000 or less is not subject to a municipal zoning ordinance governing public schools.
. As described above, Universal Academy asserts that in
. Additionally, the supreme court stated as follows respecting an argument made by the Solicitor General of Texas in a brief requested by that court:
[T]he Solicitor General pivots onSection 12.1056 ’s grant of immunity from liability to argue that if open-enrollment charter schools are not governmental units under the Tort Claims Act, then the Act does not apply. And if the Act does not apply, then an open-enrollment charter school’s immunity from tort liability is never waived. And if immunity is never waived, thenSection 12.1056 would suggest that open-enrollment charter schools are immune from all tort liability, unique among all governmental entities in the State. The Solicitor General sees this as an illogical and surely unintended outcome — traditional public schools exposed to tort liability but charter schools exempt from it. We do not consider today the scope or effect ofSection 12.1056 , but assuming arguendo the Legislature can grant immunity from liability, it would seem odd for lawmakers to imbue open-enrollment charter schools with greater tort immunity than cities, counties, school districts, and other purely governmental entities.
Id. (emphasis original).
. We construe Universal Academy's second issue to address only claims of C2 Construction to which immunity would otherwise attach. Therefore, because we concluded above that immunity from suit is not applicable as to C2 Construction's
. Pursuant to Albert, following Universal Academy's non-suit, C2 Construction cannot recover judgment for damages against Universal Academy based on the trial court’s limited jurisdiction resulting from Universal Academy's counterclaim because Universal Academy is no longer pursuing a claim for damages to which an offset would apply. See id. at 375. Therefore, no determination is necessary in this case respecting the extent to which C2 Construction’s claims are “offsetting.” See id. at 377 (after non-suiting counterclaims, governmental entity that had full immunity before making affirmative claims can "make both a motion for summary judgment and a motion to dismiss based on immunity from suit, and it should prevail on all the claims against it regardless of whether the claims against it were defensive, offsetting claims, or otherwise”).
. We refer again to legislation that identifies charter schools as having attributes of school districts. Charter schools enjoy immunity from liability "to the same extent as a school district.” See Tex Educ Code Ann.
. Additionally, Universal Academy cites its response to C2 Construction’s second request for admissions in which Universal Academy denied that "[i]n or about July 2005, C2 provided a proposed written contract to Universal for the Project.” However, "[a]dmissions are binding only against the party making the admission.”
See U.S. Fid. & Guar. Co. v. Goudeau,
. C2 Construction asserts no basis for waiver of immunity from suit other than section 271.152 as to any of its claims.
. C2 Construction does not explain, and the record does not show, the basis for C2 Construction's assertion respecting