LPS Construction Company, Inc. (LPS) brought the underlying
“On appeal from the grant of a motion for summary judgment, we review the record de novo to determine if the moving party has demonstrated there is no genuine issue of material fact and the undisputed facts, construed in a light most favorable to the non-moving party, warrant judgment as a matter of law. Gentile v. Bower,
In accordance with the State Purchasing Act, OCGA § 50-5-50 et seq., the DOAS invited sealed bids for the construction of a project at Fort Stewart, Georgia, on behalf of the DOD.
LPS submitted a timely, signed, and sealed bid on the form-required, offering a total contract price of $2,628,100. LPS’ president signed the proposal form, but it is undisputed that he did not read the proposal form. On the outside of the bid envelope, there was a handwritten notation which stated, “Alternate #6 Add 68,000.00 — Base Bid Add 7,000.00.” The handwritten notation was not signed or initialed. LPS contends that it received a last minute bid from one of its subcontractors which necessitated the revision on the bid envelope. LPS had estimated what the subcontractor would bid and that estimation was on the signed and sealed bid. As the subcontractor’s official bid was received only one minute before bid opening, LPS’ agent did not have time to make the revisions required by the bid rules.
On September 29, 1995, the DOAS accepted LPS’ offer by furnishing a purchase order awarding the contract to LPS in the amount of $2,628,100. DOAS regulations provide, “[a] written Purchase Order furnished to the successful bidder/offeror within the time specified in the solicitation document results in a binding con
By letter dated October 10, 1995, LPS’ president requested that the DOD and DOAS waive compliance with the “technicality on the Bid Proposal Form relating to revisions on the envelope.” The president’s letter further stated: “I therefore respectfully request that the technicality of no revisions on the envelope be waived and the contract amount be adjusted to $2,703,100. Whatever your decision, I do fully intend to honor my obligation to the Department of Defense regardless of the financial hardship I may face.” By letter dated October 11, 1995, the DOAS denied LPS’ request for a waiver.
On October 19, 1995, LPS’ president signed, “under protest,” a copy of a formal contract memorializing the September 29, 1995 agreement. Specifically, LPS added the following statement to the signature line: “Signed under Protest as Final Contract Price Subject to Outcome of Lawsuit filed 10/19/95.”
1. In Count 1 of its amended complaint, LPS contends that “LPS intended for its bid to include the $75,000.00 in envelope revisions” and that defendants either knew or should have known that LPS’ bid included the $75,000. However, LPS’ intent to include the envelope revisions is irrelevant considering the clear instructions that no envelope revisions would be considered. LPS’ bid was for the amount stated on the bid form and the defendants’ acceptance of the bid created a binding contract for the amount bid. See cf. Southeast Grading v. City of Atlanta,
LPS contends that someone in the bid room who worked with DOD waived the requirement that envelope revisions would not be considered. For this contention, LPS relies on hearsay testimony that an unidentified person claiming to work with the DOD said, “[w]ell, I’m with the Department of Defense, and the federal government does it all the time. I’m sure it’s all right.” Initially, we note that hearsay has no probative value in summary judgment proceedings unless it is part of the res gestae. See Real Estate Intl. v. Buggay,
LPS further contends that the day after its bid was submitted, DOD agents represented that the “technicality” regarding the envelope revisions would be waived. Furthermore, a DOD agent deposed that he had told LPS’ president that the envelope revisions would be
2. LPS’ final theory of recovery sounds in quantum meruit. LPS asserts that it is entitled to recover the $75,000 written on the face of the envelope because “[n]o state agency is allowed to take private property without due and adequate compensation.” However, as a valid express contract exists LPS cannot recover in quantum meruit absent a breach of the contract by the DOAS or DOD. See Classic Restorations v. Bean,
Judgment affirmed.
Notes
The trial court’s rendition of the facts is supported by the record, and we adopt them with minor additions.