61 Ct. Cl. 756 | Ct. Cl. | 1926
delivered the opinion of the court:
- The plaintiff on January 19, 1917, contracted to do certain construction work at the Rock Island Arsenal, Rock Island, Ill. The contract called for a concrete hollow-tile house, 350 feet of standard railroad, and one loading platform. The Government prior to soliciting bids for the work furnished blue prints and detail plans and specifications of what would be exacted in reference to the same, and the plaintiff had access to and examined the same. Among the blue prints furnished was a contour map. It disclosed the elevation of the dirt surface above a fixed point within the boundaries of the site selected for the location of the work. It did not within this area show the presence of
The contention is apparently based upon a misrepresentation and the cases of Hollerbach v. United States (233 U. S. 165) and Christie v. United States (237 .U. S. 234) are relied upon. The cases are inapposite. A contour map such as herein relied upon was designed to disclose no more than elevations of surface of the earth; it may not be construed into a warranty that every impediment to clearing the site for the performance of the work is clearly shown thereon. The plaintiff assumed the risk of encountering extraneous deposits which might exist above the surface of the ground. The specifications so warned him, for they provide as follows : “ The location and grade of the buildings shall be as indicated on the drawings. The site shall be cleared by the contractor for the reception of the structure and for that purpose should be examined by him before bidding.” The plaintiff having obligated himself to clear the site and been expressly warned to view the premises may not now complain that he came across difficulties which an observance of the specifications would have obviated and difficulties not unusual and to be anticipated. As well might he claim additional pay for removing trees and brush.
The next complaint centers around the blue prints furnished him as to the estimated quantities of rock excavation necessary to be made. The contention with respect to recovering for this item is identical with the preceding one. Two sets of blue prints disclosing in cross section the rock formation beneath the surface of the ground for foundation purposes were furnished the plaintiff. After the excavation
Specification 66 provides for roof construction. Specification 64 specified the quality of lumber to be used in woodwork. The plaintiff insists that he observed the specifications with reference to the quality of lumber in the construction of the roof, but that the same was rejected by the inspector as not in accord with the contract. Two insurmountable difficulties prevent a recovery for this item. First, the plain
The item embraced in Finding YII is concluded by what is said in disposing of the preceding item. The contract pointed out in express terms the precise manner of making changes in the contract work. The final paragraph of Article 10 recites: “No claim for addition or deduction on account of any change will be made unless the same was ordered in writing.” The plaintiff had an undoubted right to refuse to proceed with the work brought about by a change in the plans until he received the order in writing. We find no authority in the contract to waive'the provision. The plaintiff knew the provision was in the contract, and he was derelict in proceeding without the written order, and in greater fault in accepting what the defendant paid. Plum-ley v. United States, supra.
Finding VIII depicts a situation which clearly discloses the imposition upon the plaintiff of extra work and the furnishing of materials not required by the contract or specifications. The defendant, because of lack of available appropriations, was compelled to reduce the size of the concrete hollow tile building. The original plans provided for a building 180 feet in length, consisting of nine bays. In order to come within available funds the building was reduced to 140 feet in length and bays 1 and 2 eliminated to accomplish the same. The plaintiff reduced his bid accordingly and the contract as finally executed called for the smaller building. The specifications called for two down spouts attached to bays 1 and 2; i. e., there were six down spouts from the roof specified in the original plans and only four in the modified' plans. When bays 1 and 2 were eliminated it necessarily eliminated all that was required in constructing the same; but the defendant notwithstanding
The item claimed under Finding IX is not allowable. The same falls within the authority conferred by the contract on the inspector in Article 3 of the contract, a subject heretofore discussed.
The case of Crook v. United States, supra, determines the claim under Finding X. The final paragraph of Article 6 of the contract brings the same within the cited case. The contract provides as to delays: “ But none of the above causes shall constitute the basis for an action of damages against the United States.”
The petition is dismissed. It is so ordered.