OPINION
James and Diana Love appeal from the trial court’s grant of partial summary judgment in favor of Meyer & Najem Construction, LLC (Meyer Najem). The Loves present one issue for review: Did the trial court properly grant Meyer Na-jem’s motion for partial summary judgment upon determining that Meyer Najem did not owe a duty to James?
We reverse.
This case arises out of injuries that James Love sustained on May 13, 2008 while working for General Interiors, Inc. at the Brownsburg High School Classroom Renovation аnd Addition project (the Project). The Project included the addition of several choir and band practice rooms. Meyer Najem contracted with Brownsburg Community School Corporation (the Owner) to serve as the constructiоn manager for the Project. 1 Likewise, General Interiors directly contracted with the Owner to install acoustical panel ceilings, acoustical wall panels, and acoustical curtains in the choir and band practicе rooms. There was no contract between Meyer Najem and General Interiors.
To fulfill its responsibilities, Meyer Na-jem employed Andrew Slye to serve as a fulltime, on-site superintendent for the Project. James served as the person in charge and responsible for safety procedures for General Interior’s crew working on the Project.
In May 2008, the Project was nearing completion. On the day James sustained his injuries, he and another employee of Gеneral Interiors were hanging two acoustical curtains in a show choir classroom. The curtain track to which the curtains attached was approximately sixteen to twenty feet off of the floor above a narrow
According to James, Slye picked up a piece of carpeting and instructed Jamеs and his co-worker to put it under their ladders. James maintains that Slye actually helped position the carpet remnant, nap-side down, under the ladders. In contrast to James’s recollection of events, Slye stated in his depositiоn that James looked around and located the carpeting remnant and asked if it was suitable to use under the ladders. Slye indicated that the carpet, if used nap-side down, would protect the flooring and that he conditioned James’s choice of carpet as a barrier between the ladders and the floor by stating “as long as it doesn’t slide.” Appellants’ Appendix at 118. Slye then left the room. A few minutes later, Slye heard a commotion in the choir room. While working from the ladder to install the second curtain at a height of fifteen to sixteen feet, the carpeting under the ladder slid causing both James and the ladder to fall. James suffered permanent injury.
The Loves filed their complaint against Meyer Najem on February 5, 2009, alleging among other things that Meyer Najem “assumed a duty of safety by contract and its conduct at the SCHOOL construction site.” Id. at 16. Meyer Najem filed its answer on March 27, 2009. A year later, on March 30, 2010, Meyer Najem moved for summary judgment, arguing that it owеd no duty to Love by contract and that it did not assume a duty by conduct.
The Loves filed a response in opposition to Meyer Najem’s motion for summary judgment as well as a request for partial summary judgment in their favor. In their motion, the Loves clarified that their theory of the case was not that Meyer Najem assumed a duty for project-wide safety by contract or by its conduct on the jobsite. Rather, the Loves maintained that their theory of the case was that Meyer Nаjem assumed a duty to use reasonable care when it asserted control over the means and methods by which General Interior’s employees (i.e., Love and his coworker) could perform their work on the day in question.
On May 26, 2010, the triаl court held a hearing on the cross-motions for summary judgment. The trial court entered an order on June 16, 2010, granting Meyer Na-jem’s motion for summary judgment and denying the Loves’ cross-motion for summary judgment. The. trial court found that “[a]s a matter of law, [Meyеr Najem] did not assume, by contract or by conduct, a duty for project-wide safety at the construction site at issue in this cause, and therefore owed no duty to [James Love].” 2 Id. at 9. The Loves now appeal.
To premise a recovery on a theory of negligence, a plaintiff must establish three elements: (1) a duty on the part of the defendant to conform his conduct to a standard of care arising from his relationship with the plaintiff, (2) a failure of the defendant to conform his conduct to the requisite standard of care required by the relationship, and (3) an injury to the plaintiff proximately caused by the breach.
Webb v. Jarvis,
“ ‘Duty’ has been defined as ‘an obligation, to which the law will give recognition and effect, to conform to a particular standard of conduct toward another.’ ”
Blake v. Calumet Constr. Corp.,
In cases in which the existence of a duty is not previously established, Indiana courts analyze three factors in determining whether to impose a duty at common law: (1) the relationship between the parties, (2) the reasonable foreseeability of harm to the person injured, and (3) public policy concerns.
Webb v. Jarvis,
The Loves contend that when Meyer Najem (through its on-site superintendent, Slye) exerted direct influence and control over what equipment General Interiors’ employees could and could not use to perform their work and how such equipment could be used, it exceeded its con
In
McClure v. Strother,
The genuine issue of material fact is whether Mr. Strother refused to allow McClure to use “tie-offs” on the ladder. If he did not refuse to allow the “tie-offs”, he was under no duty and is, therefore, not liable. If he did refuse, however, he may have assumed control over the ladder, an instrumentality in the contractors’ control, thereby becoming liable for accidents stemming from the use of the unsecured ladder.
McClure v. Strother,
The sаme holds true here. A genuine issue of material fact exists as to whether Meyer Najem (through its on-site superintendent — Slye) assumed control over how the ladder could be used. According to James, out of concern for possible damage to the new flooring, Slye directed him and his co-worker to use the carpet, nap-side down, under their ladders and Slye actually helped put the carpet in place. Slye, on the other hand, maintains that it was James’s ideа to use the carpet and that he merely indicated that if used nap-side down it would protect the floor and that he further conditionally approved the carpet if it did not slide. The discrepancy between their stories is matеrial to this dispute and must be resolved by the fact-finder, not determined as a matter of law. Having concluded that a genuine issue of material fact exists, summary judgment was improper.
Judgment reversed.
ORDER
Appellants, James A. Love and Diana Love, by counsel, filed an Appellant’s Motion for Publication.
On June 9, 2011, The court issued an order that DENIED Appellant’s Motion for Publication.
Having reviewed the matter, the Court FINDS AND ORDERS AS FOLLOWS:
1. This Court’s order of June 9, 2011 is hereby VACATED and HELD FOR NAUGHT.
2. The Appellant’s Motion For Publication is GRANTED and this Court’s oрinion heretofore handed down in this cause in March 30, 2011, marked Memorandum Decision, Not for Publication is now ORDERED PUBLISHED.
FRIEDLANDER, MAY, MATHIAS, JJ., concur.
Notes
. Meyer Najems’s role as the construction manager involved reviewing the Owner's designs and specifications, preparing cоst estimates, developing a project schedule, coordinating safety plans of contractors, and coordinating the sequence of construction for the Project.
. The trial court further ordered that there was no reason for delay and thus deemed its order "final and appealable.” Id. at 10.
