MEMORANDUM OPINION
In this case, Plaintiff, Louisville Gas and Electric Company (“LG & E”), seeks to recover damages from Defendants, Continental Field Systems, Inc. (“Continental”) and Advanced Welding Services, LLC (“Advanced Welding”), arising from a broken fan shaft on an electrical generating unit at the LG & E Cane Run Road facility. The damages it seeks include the cost to replace the fan shaft and some nearby equipment as well as lost revenues, such as the cost of replacement power purchases and lost profits due to LG & E’s lost opportunity to sell excess electricity.
Prior to trial, Defendants have moved for dispositive resolution on three important issues. First, both Defendants have moved to dismiss the entire case due to LG & E’s role in spoliation of the fan shaft evidence. Second, both Defendants have moved to dismiss LG & E’s tort law claims as barred by the economic loss rule. Third, Advanced Welding has moved to *766 dismiss LG & E’s third party beneficiary contract claim. The Court will consider each motion in turn. In doing so, the Court has the benefit of excellent memo-randa and discussion of the issues with counsel at a conference.
I.
This case arises from a process of regular maintenance conducted at LG & E’s Cane Run Road facility. LG & E had contracted with Continental to provide various maintenance and repair services. As part of that maintenance program, LG & E officials noticed that water leakage may have caused pitting on the draft fan shaft located at Unit No. 6 in the facility. LG & E asked Continental for a repair recommendation and a cost estimate. To accomplish the repair, Continental recommended a process known as “sleeving.” After some discussion, LG & E apparently decided to prefer repair by welding overlay and requested Continental to perform the work in that manner. For purposes of these motions it is not necessary to determine who made the final decision as to method of repair. In any event, because Continental did not have the capability to perform welding of this complexity, it called upon Advanced Welding to perform the required work.
Continental and Advanced Welding performed the required welding and maintenance procedures. The unit returned to regular operation. Within several weeks of ordinary use the fan shaft broke in two pieces at the precise location that Advanced Welding had completed the weld. The break caused extensive damage to the fan shaft unit itself and perhaps to other nearby equipment as well. LG & E replaced the entire fan shaft and repaired the fluid drive at a cost of approximately $200,000. Due to circumstances that the parties dispute, Unit No. 6 remained off line for several months required for the repairs. LG & E says that the loss of plant operation cost another $1.8 million. Additionally, LG & E says that it lost approximately $5.2 million in power sales due to the plant down time.
LG & E has asserted a variety of claims. Count I asserts breach of contract against Continental; Count II asserts breach of warranty against Continental; Count III claims negligence against Continental for failure to use ordinary care in performing the repair work; Count IV states a third party beneficiary claim against Advanced Welding based on its breach of its contract with Continental; and Count V claims negligence against Advanced Welding. LG & E says that the fan shaft pitting was not a structural defect and neither caused nor contributed to the break. It says that Continental and Advanced Welding performed the weld repair improperly and that the repair actually weakened the shaft, causing it to break under the stress of normal operations.
After the accident and the filing of the lawsuit, LG & E took possession of the two rather large parts of the broken fan shaft. It delivered the part containing the weld section to its expert consultant, Metallurgical Services Company (“Metallurgical Services”). LG & E left the other piece outside in the weather where it gathered rust and wear. Metallurgical Services performed a variety of tests on the weld section, prepared an expert report detailing its opinions and then somehow misplaced it. Later on in the litigation, Defendants requested an opportunity to examine and test the fan shaft for themselves. After considerable searching, neither LG & E nor Metallurgical Services has been able to determine the shaft’s current whereabouts. They suspect that it was accidentally discarded.
*767 II.
Defendants have moved to dismiss the entire complaint due to the spoliation of the fan shaft evidence. Defendants say that without testing the lost piece of the fan shaft, it cannot properly rebut LG & E’s charges. Defendants make a number of valid arguments. The Court has closely considered all arguments to fashion the fairest remedy in the circumstances.
The Sixth Circuit has defined spoliation of evidence as “the intentional destruction of evidence that is presumed to be unfavorable to the party responsible for the destruction.”
Beck v. Haik,
The circumstances here present an evi-dentiary problem, not an occasion for sanctions or penalties. Federal law controls the admissibility of evidence, and the Court has broad discretion in controlling the admission or exclusion of evidence.
United States v. Wagner,
With the foregoing principles in mind, the Court turns to the present facts. The Court has carefully reviewed the expert testimony and makes the following findings relevant to its consideration of an *768 appropriate remedy. LG & E had a duty to preserve the important evidence in its possession. It failed in that duty, probably due to neglect by its own expert consultant, Metallurgical Services. Defendants share no fault for the lost evidence or its inability to examine that evidence. The weight of the evidence suggests that the repair work was in some way responsible for the fan shaft break. The primary issue in this case is likely to concern which party had most responsibility for determining the method of repairing the fan shaft and the method of cooling the weld. It is not clear whether analysis of the shaft is important as to this issue. It is improbable that the broken shaft resulted from a weakness that pre-existed the repairs.
Dismissal of LG & E’s case in its entirety is too punitive a sanction for acts which were not purposeful and which have an uncertain importance to the case. Therefore, the Court will instruct the jury in a manner similar to the following:
This instruction concerns the accidental loss or destruction of evidence. LG & E had possession of the broken fan shaft. Its expert, Metallurgical Services, took possession of the shaft, tested it, issued opinions concerning the accident and then misplaced the shaft. As a result of that misplacement, Defendants have been unable to examine and test the shaft or to fully explore and examine the opinions reached by Metallurgical Services. If you believe from the evidence that Defendants’ inability to test the shaft prevented Defendants from rebutting any particular element of LG & E’s claims, you may decide against LG & E as to that particular element. You may not consider spoliation of the evidence in any other fashion in connection with this case. 2
The Court provides the following additional guidance to counsel. Defendants may not argue that simply because LG & E lost the fan shaft, the jury should render a verdict in favor of Defendants. They may argue that their inability to inspect the shaft prevented them from proving their theory of the case or prevented them from rebutting LG & E’s theory of the case. LG & E may not argue that Defendants contributed in any way to the lost evidence or that the second piece was suitable for inspection. LG & E may argue that Defendants’ inspection would not have lead to a different result and that whatever theory Defendants proposed is so improbable that any testing of the missing part could not have proved it true. The Court reserves the right to reconsider its ruling based on the evidence actually presented at trial.
III.
Advanced Welding has moved to dismiss Count Y of the complaint and Continental has moved to dismiss Count III, each on the grounds that the economic loss rule bars any claim for economic damages and negligence that actually arises from breach of contract.
The economic loss rule has evolved through the years as a principle whose purpose is to preserve the valid distinctions between tort and contract claims.
Ohio Casualty Ins. Co. v. Vermeer Manuf. Co.,
In this case, however, the Court faces a proposed further extension of the economic loss rule. All parties seem to acknowledge that both Continental and Advanced Welding were providing a service to LG & E, rather than selling a product. As yet, no Kentucky court has specifically considered whether the economic loss rule should apply to the provision of services as well as the selling of a product. Defendant argues that it should so apply and that, therefore, LG & E’s claims in Counts III and V should be dismissed. For the reasons that follow, this Court disagrees.
Virtually every classic description of the economic loss rule pertains to and often limits its application to the sale of products. The cases make this distinction in order to preserve the distinction between the remedies available under the U.C.C. and those available in tort. Such a distinction would be immaterial here because the U.C.C. does not govern services. In the context of selling a product, the economic loss rule can limit its application to those circumstances in which the damage is solely to the product. Where services are involved, the rule could not be so easily or clearly limited. In addition, one providing a negligent service that damages related property appears to have breached a duty, rather than having breached a warranty. In such circumstances, the injured party has not suffered purely economic losses, but property damage recoverable in tort. All of these reasons suggest the conceptual difficulty of applying the economic loss rule to services.
None of the existing cases suggest that an expansion of the rule is likely. This Court’s previous discussion of the economic loss rule has assumed that its application is limited to circumstances involving the sale and provision of products.
Ohio Cas. Ins. Co.,
*770 This Court believes that it is on sound ground in predicting that Kentucky courts would apply the economic loss rule in its classic definition. However, it would be pure speculation to suggest that Kentucky courts would adopt the broader application of the rule discussed in the Presnell concurrence.
IV.
Advanced Welding has moved to dismiss Count IV of the complaint on the grounds that LG & E was merely an incidental beneficiary of the contract between Continental and Advanced Welding and, therefore, can make no contractual claim as a third party beneficiary.
Generally, only a party to a contract may bring an action to enforce it. However, a third party may enforce a contract made for its “actual and direct” benefit.
Sexton v. Taylor County,
Kentucky courts have not specifically adopted the Restatement (Second) of Contracts concerning intended and incidental beneficiaries. Nevertheless, the Restatement provides a logical starting point for the discussion since Kentucky courts have relied on other sections of the Restatement dealing with third-party beneficiaries.
See, e.g., Stevens v. Stevens,
(1) Unless otherwise agreed between promisor and promisee, a beneficiary of a promise is an intended beneficiary if recognition of a right to performance in the beneficiary is appropriate to effectuate the intention of the parties and either
(a) the performance of the promise will satisfy an obligation of the promisee to pay money to the beneficiary; or
(b) the circumstances indicate that the promisee intends to give the beneficiary the benefit of the promised performance.
(2) An incidental beneficiary is a beneficiary who is not an intended beneficiary.
Restatement (Second) of Contracts § 302.
Paragraph 1(b) of § 302 concerns what is often referred to as a donee beneficiary. In those circumstances the promisor obtains a promise from the promisee to pay money to a third party. Usually this promise represents a gift from the promis-ee to the third party. Under such circumstances, one can see that the third party is a very direct beneficiary of the agreement between the promisor and the promisee. That circumstance does not apply here. Our circumstance is more similar to what is often referred to as a creditor beneficiary. As described in paragraph 1(a) of *771 § 302 these are circumstances in which the promisee intends that the promisor’s performance will satisfy a monetary obligation of the promisee to the beneficiary.
The Restatement gives examples of promises “to perform a supposed or asserted duty of the promisee, a promise to discharge a lien on the promisee’s property, or a promise to satisfy the duty of a third person” as examples of a creditor beneficiary. After reading all the examples, the Court concludes that Continental’s oral agreement with Advanced Welding provided LG & E more of an incidental benefit, rather than a direct and intended benefit. Incidental beneficiaries are those who benefit in some way from the performance of the contract even though the promisor carries out his obligations not for the specific and direct benefit of the third party. In virtually every contract, some persons benefit in this manner. Although the Restatement’s illustrations are certainly not binding upon this or any other court, those illustrations have guided the Court in identifying the fault line between intended and incidental beneficiaries.
■As the following illustration shows, to discern the difference between intended and incidental beneficiaries in a contract for the discharge of debts, one need simply identify to whom payment is made:
B promises A to pay whatever debts A may incur in a certain undertaking. A incurs in the undertaking debts to C, D and E. If the promise is interpreted as a promise that B will pay C, D and E, they are intended beneficiaries under Subsection (l)(a); if the money is to be paid to A in order that he may be provided with money to pay C, D and E, they are at most incidental beneficiaries.
Restatement (Second) of Contracts § 302 cmt. b. Of course, the present case does not involve payment of money, but performance of a service. As such, it is not so easy to identify to whom performance is made. In this context the Court notes another illustration, this one bearing a remarkable similarity to the facts at hand:
A [Continental] contracts to erect a building for C [LG & E], B [Advanced Welding] then contracts with A [Continental] to supply lumber needed for the building. C [LG & E] is an incidental beneficiary to B’s [Advanced Welding’s] promise, and B [Advanced Welding] is an incidental beneficiary of C’s [LG & E’s] promise to pay A [Continental] for the building.
Restatement (Second) of Contracts § 302 cmt. d. This illustration seems to recognize that although third parties will often benefit from performance of service contracts, those third parties do not typically rise to the level of intended beneficiaries.
Thus, our circumstances are different than those describing an intended beneficiary in
Hendrix Mill & Lumber Co. v. Meador,
Ky.,
Our circumstances more closely resemble those in
Guarantee Elec. Co. v. Big Rivers Elec. Corp.,
Defendants argue that Kentucky cases suggest that the third party beneficiary must be specifically discussed or that its interests must be named in the written agreement before it can maintain a third party beneficiary action. As evidence of this, Defendants point to
King v. National Industries, Inc.,
Nevertheless, the Court does not find sufficient evidence of Continental’s intent that its agreement with Advanced Welding specifically and directly benefit LG & E. Continental owed many duties and obligations to LG & E. It contracted with Advanced Welding to perform a limited function as part of its overall obligations. Thus, Advanced Welding cannot be said to have promised performance of a direct and specific obligation that Continental owed LG & E. To be sure, LG & E was to benefit from the agreement. However, because that benefit was not direct and specific, the Court finds LG & E to be" only an incidental beneficiary and not an intended beneficiary.
The Court will enter an order consistent with this Memorandum Opinion.
ORDER
Defendants have moved to dismiss all counts of the complaint on various separate grounds. The Court has reviewed the various memoranda and have discussed these issues with counsel. Being otherwise sufficiently advised,
IT IS HEREBY ORDERED that Defendants’ motion to dismiss the case in its entirety due to spoliation of evidence is DENIED. The Court will issue the jury instruction concerning loss of the evidence as described in the Memorandum Opinion and will consider other further relief as the evidence requires.
IT IS FURTHER ORDERED that Defendants’ motion to dismiss certain claims based on the economic loss rule is DENIED.
IT IS FURTHER ORDERED that Advanced Welding’s motion to dismiss Count IV is SUSTAINED and-Count IV of the complaint is DISMISSED WITH PREJUDICE.
Notes
. "Instruction No. 1: Microbiological and surgical specimen evidence is missing in this case. If you believe its absence was caused by the unjustified or careless actions or inac-tions taken by Gilman Peterson, M.D., or Milton Slocum, M.D., then you may infer, but are not required to infer, that such evidence, if available now, would have been favorable to the Plaintiffs and been adverse to that Defen- • dant."
. The Court will consider modification of this instruction at a time closer to trial.
. Even if applied to services, the economic loss rule would not prevent Plaintiff from *770 recovering here, where Plaintiff alleges that Advanced Welding's negligence caused property damage and resulting consequential damages, rather than pure economic loss. In contrast, the plaintiff in Presnell alleged pure economic losses in the form of extra costs incurred in working on a construction project.
