Lead Opinion
The opinion of the court was delivered by
Plaintiff pleaded as in a concurso to compel the parties concerned to appear in court and assert their claims and rights over a fund of twenty-six hundred and forty-two and 5-100 dollars, which it deposited in court. It is alleged, in substance, by it, that in 189.6, by written contract, it entered into a contract with a contractor and builder to erect a five-story warehouse building for the price of thirteen thou■sand four hundred and forty-two dollars, to be paid on terms as stated in the contract; that the Fidelity and Deposit Company, of Maryland, became the surety of this contractor up to the amount before stated; that the contractor and plaintiff selected Louis A. Ganteii, an architect, as superintendent and supervising architect of the works, and notice of the selection was duly given to the Surety Company; that payments -were to be made to the contractor at the end of each month for all the work done during the month less twenty per cent., which was to be retained by it until the completion of the building; that the payments were- to be made on the certificates of the superintendent of construction, Ganter;,that the sum alleged, except the amount deposited as before stated, was all paid to the contractor, and a large portion was paid with the consent of the Fidelity Company, surety; that since the. payment of this sum, attested accounts by workmen and material men were ■served on it for material supplied, amounting to a large sum, about six thousand dollars; that after service of these accounts it refused .to make further payments; that it notified the defendant, the Surety Company, that the contractor was quite slow in performing his work; that on October 5th, 1896, plaintiff seeing that he would not complete it, gave him
Petitioner also alleges that after making payments as stated, it had a balance on hand which it did pay over to the depository of the court, as-before mentioned, less the sum of twenty-five dollars reserved for costs; that it was necessary to form a concurso and bring in all interested parties in order to settle tire right of each. The building contract, specifications, and the contract of the contractor with the Fidelity and Deposit Company are all in evidence containing the terms and conditions usually inserted in such contracts and the details usual in specifications. The material men who had recorded their claims were made parties by plaintiff. Five of these men had brought suit against the plaintiff alleging that plaintiff had made payments by anticipation which resulted in' their injury. These suits are all consolidated en concurso, and are before us for decision. Those who had not sued appeared’ on the day of trial and were permitted to prove their claim.
The Fidelity and Deposit Company pleaded the general denial, and,, also, specially averred that plaintiff had made an over estimate of the-work performed each month, and had, in consequence, overpaid the contractor each month and the' payment in anticipation had caused it to-lose a considerable amount, sufficient for it to claim its release and discharge on its bond. The creditors made parties joined in the concurso issue with those opposing their interests and claimed the amounts due-them. Defendant avers that after a large amount of costs had been incurred and it had proven that the tender of 'the before stated amount was insufficient, plaintiff deposited a further sum of twenty-three dollars, and, thereby, made a second tender.
The statement of facts shows that some time after having agreed upon a plan of the building, plaintiff entered into a contract with a builder to erect the five-story building in question in accordance with the draw7 ings and specifications identified with the contract, i. e. the plans and specifications were prepared by the architect sometime prior to signing-the contract with plaintiff. They were accepted by plaintiff and bids
The builder bound himself to furnish all the labor, tools, and materials of every description and to deliver the work complete, free from all liens for labor and materials, on the fifteenth day of September, 1896. Payments were to be made monthly, for all work done in one month. Payment was to be made at the end of each month, in amount twenty per cent, less than the value of the work done during that month. The twenty per cent, deduction was to be retained until the building was completed. The plan or specifications are, to some extent, defective, unless the defect be supplied by the following, copied from the specifications: “Iron Work — Furnish and erect in place all iron work required to finish the building, as follows, viz. Oast iron and all the ordinary cast iron plates, well plates, capitals, etc., as per detail. Wrought Iron — All wrought iron work in connection with carpenter’s work, such as joint bolts, anchor iron for floor guards and door frames, tie bolts, etc., as per detail. In addition to what is specified above, all iron of any description necessary for the proper construction of the building shall be furnished, by the contractor without extra expense to the company”. It is contended by the Surety Company that the specifications provided for the construction of the arches, under the head of brick work, and that it did not contain anything about iron lintels or anything of the sort. The contract also contained a stipulation that if the builder failed to comply with its terms then plaintiff was to have the right to put an end to the contract and complete the work at the expense of the builder without being liable or accountable for the manner whereby plaintiff completed the work.
The builder furnished a bond in favor of plaintiffs, signed by the Fidelity and Deposit Company, in accordance with the terms of the Stat
And that the change in the construction of the arches was necessary.
It is averred by the Surety Company that the building was constructed according to the plan and specifications, and that the Surety Company is not responsible for the defects therein, as it bound itself only to see that the builder would complete the building according to the plan and specifications. The Surety Company also complains of anticipated payments made to the builder, also of over estimates whereby the contractor received a larger amount than he should have received at the end of each month; that he was only entitled at the end of each month to amounts earned during that month. It is a fact that’in this case there was paid nine hundred and twenty-two 22-100 dollars on June 1st, for May’s labor account, four thousand and seventy-three 52-100 dollars on July 1st, for June labor account, and four thousand seven hundred and ninety-seven 76-100 dollars on August 1st, for July labor account, and that a lárge part of these amounts was paid with the consent of the general agent of the Surety Company. It is also a fact, as charged, that plaintiff sold old bricks to the contractor for two hundred and eighty dollars, which were collected only in Aug: ust, though the bricks were sold in May.
Judgment for the Louisiana Molasses Company was pronounced in the District Court accepting the sum of two thousand six hundred and ninety and 50-100 dollars, making up the two tenders and deposits as the amount due to the contractor, LeSassier, and the other parties in interest, and decreeing further in favor of plaintiff for all its costs, as stated in the judgment.
The plea of prescription filed by the Surety Company was not sustained and judgment was rendered against said company in favor of ■each creditor for the deficiency. There was a judgment rendered in favor of the Surety Company against those it called in warranty on their indemnity bond in favor of the surety. From the whole judgment the Surety Company appeals.
All the parties admit that the contractor and architect contracted to build a large brick building for plaintiff, and that the aforementioned 'Surety Company bound itself as his surety. It is also evident that there is no further issue among the parties growing out of the fact that plaintiff took possession of this building before it was completed, and after-wards completed it as alleged. We understand that possession of the building was taken with the consent of the Surety Company. The rights of the parties are not prejudiced by the act of possession of plaintiff. The only question regarding the construction relates to certain
The only remaining difference between the plaintiff and the Surety Company arises from the latter’s complaint that the former, the Louisiana Molasses Company, dic^ not guard itself against the specifications and plans furnished it by the architect, and also did not comply with the stipulations and- conditions of the bond.
In the first place we take up for decision the complaint of the Surety Company directed against the plan and specifications of the architect. The Surety Company insists that the defect in the wall over the arches was not caused from the defective construction of the building, but was-the result of the faulty plan, conformably to which the building was constructed.
The contention on its part is that although the plaintiff company entered into a contract with LeSassier bj' which he agreed to “erect, furnish, and deliver in a satisfactory condition and workmanlike manner one five-story warehouse, all per plans and specifications drawn by Louis LeSassier, architect and builder”, and although the Surety Company bound itself for the faithful carrying out of the building contract, nevertheless it did not bond him as an architect nor did it guarantee-that plans and specifications which had been prepared by him and accepted by the Louisiana .Molasses Company, long prior, were proper and sufficient. It bonded him as a builder. On this point we do not find that the position of the Surety Company is sustained by the facts, or the law. In our view, there is a difference in matter of the responsibility of an architect. If he has only furnished defective plans and specifications, he can be held bound and accountable only in case the building has been constructed strictly in accord with them when no fault is imputable to the builder or contractor. lie is then independent of the contractor and builder and one surety or the latter would not be bound for the error of the architect, but it must be different where the architect has taken charge of the execution of his plan. Here he had his own plan, selected his own sub-contractors, and his own workmen and the-materials which were used in the construction of the building. He then becomes responsible to the owner with whom he contracted. Architect
We believe, under the terms of the contract, the Surety Company is liable for all expenses for completing the building and repairing the cracks in the brick arches, including the charges of the experts whose employment was made necessary by the condition in which the building was. We leave these propositions (viz: touching the insufficiency of the specifications and the cracks in the wall) with the statement that though it may be true that whenever an owner takes bids on plans and specifications made for him by an architect, the contractor to whom the bid is awarded is not responsible for defects caused) by incorrect plans or specifications; the case is different where the contractor draws up his own plans and specifications as an architect. For that reason we do not accept, as applying, the decisions cited by the. Surety Company as precedents having bearing upon the .issue presented.
We take up the Surety Company’s next ground of complaint: That payments were not made in accordance with the terms of the contract, that is. the payments were not all made for all the work done in one month at the end of the month (less the twenty per cent mentioned in the contract). The first item falling within this objection, the Surety
The next item covers the claim of the Brackenridge Lumber Company for an account paid, the Surety Company asserts, before the architect had furnished any certificate. There is a conflict of testimony as relates to this claim and the claim of the Salmen Brick and Lumber Company. The two plaintiffs and the contractor testify that the purchase as made from the former was necessary and that the Surety Company consented. This is denied by the Surety Company. The district judge found that the preponderance of proof as to this claim was with the plaintiff. We do not find that in thus deciding, he was in error. The lumber was received and used in the construction of the building. We think that it was included in the estimate of the superintendent and covered by the certificate. This, with the consent of the Surety Company’s agents, if given as testified to by three of the witnesses, would answer the objection to payment in anticipation. One of the witnesses for plaintiff testified that the work was being delayed and that the company refused to deliver any more lumber unless the amount in question was paid, that tire matter was brought up before the bond company and it was agreed that it should be paid. Furthermore, there is the written evidence of the general agent of the Surety Company showing, as we think, its consent.
We now pass to the over-estimates alleged by the Surety Company. There is no question but that in' a controversy over the amount due the
The Surety Company charges that the superintendent admits that while he made the estimates for June 1st and July 1st, he permitted the contractor and builder himself to make the estimate on August 1st for the month of July. The testimony shows that a large amount was paid on the contract with the knowledge, and, as we take it, with the consent of the Surety Company. Plaintiff, in compliance with the request addressed to them by the Surety Company, made its checks for August on this contract, payable to LeSassier, contractor, and the Surety Company. These checks amounting to within a few hundred dollars of tho sum due for the work done in July, were received by the Surety Company, and the contractor jointly, but were turned over subsequently by the Surety Company to the contractor. The proceeds were not used as the Surety Company avers it had the right to have them used, but they, none the less, we must say, had control of the amounts, and, as we think, can not urge with any degree of plausibility that the plaintiff, as to these sums, made payments which it should not have made.
It must be borne in mind that payment was to be made on the certificate of the superintendent o£ construction, and that the superintendent had issued hisi certificate prior to each payment showing an estimate equal to the amount paid. In Rosselot vs. Kirwin, 8th Ann., 302, referring to such a certificate, the court said: “We consider the convention of the parties to have been an absolute one for the payment of the sum of twenty-five hundred dollars per month, provided the architect gave his certificate that there was such an amount due. We are further of the opinion that the appellants are protected in such payments by the certificate of the architect and that it is incompetent for the plaintiffs to go behind the certificate and to show that it did not state the truth.” We are decidedly of the opinion that the quotation is direct and determinative of the issues upon this point. Plaintiff has performed its part of the contract -by retaining the .twenty per cent, which it had bound itself to retain. This part of the stipulation looking to the guar
We pass to a consideration of the Surety Company’s plea of prescription on the limit of ninety days, contained in the Act 180 of 1894, during which unpaid material men and furnishers have a direct action. The contract entered into between plaintiff and the Surety Company •extended the time within which any suit might be brought to six months. Before the expiration of ninety days after the building had been completed, the concurso proceedings had been filed. The funds were deposited and prayer was made to cite all the creditors. Several •creditors did not file an appearance within the six months. There was, none the less, a standing acknowledgment in favor of all concerned. Moreover they were all joined, and, in law, considered parties to the •concurso and were called upon to divide, in proportion to their claims, the funds deposited.
For the purpose of the litigation and settlement, the rights of each, in the concurso, to an extent, are admitted.
Any debtor whose property is encumbered in favor of a number of •creditors may implead them, and bring about a settlement of their rights, one with the other.
A contesbatio litis, as it were, arises in ease of the estate of an insolvent under administration. Jurisprudence has sanctioned this method •of proceeding, and the legal effects must follow as in other similar cases. For instance, when the syndic files his tableau of account, though the creditors are not all actually cited, they are constructively in court. The time within which the tableau is before the court for approval cannot be computed as part of the basis for prescription. True, in the ease of insolvency, prescription is suspended by statute. But as relates to
. When the administrator files his account, every creditor whose claim is carried thereon is protected, without service, from the plea of prescription. The debtor, in the case before us for decision, has filed -a petition, in effect the same as, as relates to prescription, to the syndic’s tableau, or the administrator’s account. If it, the proceeding here, has any validity at all, it must have the weight and the power of the syndic’s tableau or administrator’s account.
The plea of prescription is sbricLi juris. It is not presumed. The onus to sustain it is with plaintiff, both as relates to the facts and the law. For this reason it has been held by the courts 'that the service of citation, with copy of the petition, though neither bears the impress of a seal, is sufficient to interrupt prescription. The want of jurisdiction and the many errors of form affording cause to reject the demand have none the less, prevented prescription from accruing.
Plaintiff alleged the liability of the Surety Company, and prayed the decree of the court. The action was pending before the delays had elapsed. Plaintiff has deposited the cash it owed and tendered its bond for the remainder, which is equivalent to cash. To obtain its discharge, in case the contractor defaults, if he have no bond, he would have been obliged to deposit the whole of his indebtedness to the mate-' rial men, which would have been an express acknowledgement of it. In* stead, he deposited the balance due by him and tendered the bond the law authorizes him to substitute to cash, in certain cases. Clearly, prescription does not lie against those named in the papers as creditors, with the right to share in the amount deposited and in the proceeds of the bond necessary to discharge the obligation.
We taire up for decision the defence of the want of tender made by the Surety Company. There was a deficiency of an amount which the plaintiff tendered and another tender was made. Be the cause of the mistake whatever it may, the law is peremptory that to avoid costs a tender must- be made. There is an exception arising when the one to whom the tender is made refuses to accept. None the less, the tender made at the time, must include the whole sum, including costs. That question was considered in a similar case and the court held that plaintiff should have deposited the whole amount she was bound to pay.. Allen vs. Wills, 4th Ann., 98. This rule is affirmed in McComas vs. Administrator, 4th Ann., 123.
It is ordered, adjudged and decreed that the judgment be affirmed except in two particulars, and, as to these, it is ordered, adjudged and decreed that plaintiff pay costs incurred in the District Court up to the date that the last tender was made by it, viz: November 21st, 1896, and also the costs of appeal.
It is further ordered, adjudged and decreed that the judgment in so far as Manion & Co. are concerned, be amended by reducing its amount from two hundred and eleven 45-100 dollars to one hundred and ninety 45-100 dollars, and that in so far as it is concerned, it is’ condemned to pay the costs of appeal.
The Cole Manufacturing Company, Lapiere and Foray, Manion & Company, A. Ledoux, Agent, Salmen Lumber Company, Limited, and William Hankins, have taken an appeal separate from the appeal taken in the Louisiana Molasses Company vs. Louis LeSassier et al. The brief in their behalf was filed in the cited case and their rights were therein considered and decided. In the case before us, no new issues are presented. The court can not be expected to pass twice upon the same questions among the same parties.
It is, therefore, adjudged, ordered and decreed that the judgment appealed from is affirmed save in the respects in which it is amended by the decree in the cited case — appellee to pay costs of appeal.
On Application op Louisiana Molasses Company por Reconsideration and Amendment op ti-ie Decree as Relates to Costs.
The amount which plaintiff failed to deposit being small as compared with the amount actually deposited, plaintiff invokes the maxim, De minimis non curai lex, as affording ground for deciding that the company does not owe costs to the date in the history of the litigation when the deficiency úAmatter of deposit was supplied by depositing the whole amount due.
Unquestionably it devolved upon the plaintiff to tender the whole amount it owed. Having failed in this, the costs are due as heretofore determined by us.
We must decline to amend the judgment.
Rehearing refused.
Rehearing
<On Application of the Defendant, The Surety Company, for a Rehearing.
We have carefully re-examined the grounds upon which our decision rests and have found no reason which we think would justify us in granting a rehearing.
Rehearing refused.