An action to foreclose a mechanic's lien. Judgment for plaintiff. Appeals were taken from the judgment and an order denying a new trial. *Page 461
The defendant Los Angeles Pacific Boulevard and Development Company is the owner of a brick building erected by defendants Brown Alcorn as contractors, defendant William Leonard being a subcontractor for the brickwork. Plaintiff furnished brick for the construction of the building upon the order of Leonard, and in due time served notice of doing so upon the owner in accordance with the provisions of section 1184 of the Code of Civil Procedure. At the time such notice was given there remained in the hands of the owner more than enough of the contract price, still unpaid to the contractors, to satisfy plaintiff's claim in full. The contractors, who were not notified of plaintiff's claim, had paid Leonard, their subcontractor, all that was due him before plaintiff notified the owner.
All parties to the appeal agree that but one question of law is involved in the appeal. Appellants state this as follows: "Under the mechanics' lien law must the contractor 'take care of' the claims of materialmen or employees of the subcontractor under such contractor?" Respondent states it in this wise: "Whether under the mechanics' lien law the contractor's payment to his subcontractor in full, without notice of the materialman's claim, prevents the materialman from collecting his claim from the owner, the owner having had due notice, and having in hand at the time of notice the means to pay the materialman in full." (The term "means" being evidently used in the sense of having on hand enough of the unpaid contract price.)
The right of a materialman to a lien upon the property for which he has furnished the material is of constitutional creation (Hampton v. Christensen,
The notice which constitutes an equitable garnishment of the funds in the hands of the owner is not required to be served on the contractor, and he is the only one of the persons named in section 1183 who cannot avail himself of the provisions of section 1184 The notice is required to be given only to the reputed owner, although the materials may have been furnished to the contractor or other person acting by authority of the reputed owner.
There is nothing in the spirit or the letter of the law which indicates that the laborer's or materialman's lien can be affected by the obligations which exist between the contractor and the subcontractor. Upon the notice being given as provided by section 1184, it shall be the duty of the reputed owner, or the person representing him in making the payments to the contractor, to withhold from the contractor "sufficient money due or that may become due to such contractor, or other person, to answer such claim," etc.
There is no uncertainty in the law in regard to the right of the owner to withhold the money to pay bills for material furnished at the request of the subcontractor. Appellants contend that the construction given the law by the trial court would work a hardship upon the innocent contractor, who has obeyed the law, merely because he has prematurely paid the subcontractor. This would be no greater than that which falls upon the owner who has made a premature payment to the contractor. It is always in the power of the contractor to protect himself by a contract with his subcontractor, but if the contention of appellants were sustained the laborer and materialman might be deprived of their compensation by the act of the contractor and be helpless to protect themselves or to enforce the lien given to them by the constitution.
Appellants' argument appears to be summed up in this paragraph: "No provision of the lien law seems to authorize him (the contractor) to withhold the contract price, or any part of it, from his subcontractor, and yet it is claimed that in effect he must do so, or else pay the subcontractor over again by paying his unpaid bills." *Page 463
The answer to this is that since the law does not authorize him to do so, it would appear to be a good business proposition for him to protect himself from a loss in this manner by exacting of the subcontractor a contract which would require him to show that his labor and material bills were paid before the money was paid to him, or provide that the contractor might see that the sums paid to the subcontractor were applied to the payment of such bills. There are some matters relating to buildings which are not yet covered by the lien law, and within this sphere any of the parties to the construction of houses and other improvements upon real estate may still exercise their contractual rights.
There is nothing in the opinion in Macomber v. Bigelow,
The principle upon which the decision in Dore v. Sellers,
The right of a materialman to a lien for the value of his goods for which he has not been paid is not affected by the failure of the contractor to protect himself from the misappropriation of funds by his agent, the subcontractor. As said in Humboldt etc. Co. v. Crisp,
While counsel for both parties have stated there is but one point involved in the case, appellants incidentally call to our attention the fact that an attorney's fee was allowed to plaintiff. The record discloses that the sum of $100 for that purpose was included in the judgment. This allowance was error. (Union Lumber Co. v. Simon,
The judgment is modified by striking therefrom the allowance for attorney's fees, and as so modified it is affirmed. The order denying the motion for a new trial is also affirmed.
Allen, P. J., and Shaw, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on March 23, 1908. *Page 465