*1219 MEMORANDUM OPINION AND ORDER
THIS MATTER comes before the Court on Plaintiff Los Alamos Study Group’s Objections to Magistrate Judge’s Proposed Findings and Recommended Disposition, filed January 20, 2011 [Doc. 33]. On November 17, 2010, the Court referred Defendants’ Motion to Dismiss for Lack of Jurisdiction [Doc. 9] to the Magistrate Judge for proposed findings of fact and a recommended disposition pursuant to the provisions of 28 U.S.C. § 636(b)(1)(B). See Doc. 15. On January 6, 2011, the Magistrate Judge filed his Proposed Findings and Recommended Disposition (hereinafter referred to as “F & R”), recommending that Plaintiffs Complaint be dismissed in its entirety based on the doctrine of prudential mootness. See Doc. 25. Plaintiff timely filed its objections. 1
Pursuant to 28 U.S.C. § 636(b)(1)(C), the Court has reviewed de novo the findings and recommendations to which Plaintiff objects. In addition to exhaustively reviewing the briefs and voluminous exhibits submitted by the parties, the Court held hearings on April 27, 2011 and May 2, 2011, at which both sides were heard and during which the parties submitted additional material. 2 Having carefully considered the Objections, briefs, relevant law, arguments of the parties at the hearings, and the submitted exhibits, and being otherwise fully informed, the Court finds that Plaintiffs Objections to the Magistrate Judge’s Proposed Findings and Recommended Disposition are not well taken and will be DENIED. Because this denial results in Plaintiffs Complaint being dismissed in its entirety, the Court does not reach Plaintiffs Motion for Preliminary Injunction [Doc. 13].
BACKGROUND 3
This action arises under the National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-4370(f) (“NEPA”), together with the implementing regulations for NEPA issued by the White House Council on Environmental Quality, 40 C.F.R. Part 1500-08, and regulations issued by the Department of Energy (“DOE”), 10 C.F.R. Part 1021. This action also arises under the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 701 et seq.
In its Complaint [Doc. 1], Plaintiff challenges the adequacy of the Department of Energy/National Nuclear Security Administration’s (“DOE/NNSA” or “NNSA”) analysis of potential environmental impacts from the construction and operation of the proposed Chemistry and Metallurgy Research Replacement Nuclear Facility (“CMRR-NF”) at Los Alamos National *1220 Laboratory (“LANL”). Complaint at ¶2. The NNSA is responsible for the management and security of the nation’s nuclear weapons, nuclear nonproliferation, and naval reactor programs. See Declaration of Donald L. Cook, attached as Ex. 1 to Deft. Mot. to Dismiss [Doc. 9] (hereinafter “Cook Decl.”) at ¶ 3; 50 U.S.C. § 2401(b). NNSA is also responsible for the administration of LANL. Id. at ¶ 4.
Plaintiffs Complaint seeks a declaratory judgment and mandatory injunction requiring Defendants to prepare a new Environment Impact Statement (“EIS”) regarding the CMRR-NF and also seeks to prohibit all further investments in the CMRR-NF project, including any funds for detailed design or construction, until a new EIS is completed. Complaint at ¶ 3. Specifically, in Count I, Plaintiff alleges that Defendants violated NEPA and the APA by failing to prepare an applicable EIS for the CMRR-NF. It claims that Defendants’ current proposal differs substantially from that considered in the project’s 2003 EIS and the accompanying Record of Decision (“ROD”) that was released in 2004, so that a new EIS must be prepared. Complaint at ¶¶ 52-64. In Count II, Plaintiff alleges that Defendants have failed to develop an EIS which addresses “connected actions” to the CMRRNF and that Defendants must prepare a new EIS to address them. Complaint at ¶¶ 65-71. In Count III, Plaintiff alleges that Defendants failed to provide required mitigation measures and a mitigation action plan in the 2003 EIS and the 2004 ROD and that they must prepare a new EIS which addresses reasonable mitigation measures. Complaint at ¶¶ 72-79. Count IV alleges that the Defendants’ decision-making processes for the CMRR-NF exceed the scope of the 2003 EIS and the 2004 ROD and that all activities should be stopped pending the completion of a new EIS and ROD. Complaint at ¶¶ 80-90. In Count V, Plaintiff alleges that the proposed CMRR-NF involves a much greater commitment of resources and has a far greater impact than what was analyzed in the 2003 EIS and the 2004 ROD. It alleges that the DOE authorized production of a Supplement Analysis which addresses the changed project parameters and allegedly determines if a Supplemental EIS (“SEIS”) or a new EIS should be prepared has not been made public or provided to Plaintiff. Complaint at ¶¶ 91-95.
Defendants filed a Motion to Dismiss [Doc. 9] which argues that (1) some of Plaintiffs claims are time-barred; (2) Plaintiffs claims are not ripe for review; (3) Plaintiffs claims are moot; and, alternatively, (4) Plaintiffs claims should be dismissed under the doctrine of prudential mootness.
In 2002, NNSA published a Notice of Intent to prepare the CMRR-NF EIS and invited public comment on the CMRR-NF EIS proposal. Cook Decl. at ¶ 9. At the time NNSA published the Notice of Intent, the Chemical and Metallurgy Research (“CMR”) building that Defendants sought to replace was over 50 years old and allegedly nearing the end of its useful life. Id. at ¶ 6. The CMR building is a facility which has “unique capabilities for performing special nuclear material analytical chemistry, materials characterization, and actinide 4 research and development.” Id. at ¶ 5. The CMR building supports various national security missions including nuclear nonproliferation programs; the manufacturing, development, and surveillance of pits (the fissile core of a nuclear warhead); life extension programs; dismantlement efforts; waste management; material recycle and recovery; and research. Id. *1221 NNSA’s proposal to construct the replacement facility, CMRR-NF, was to insure that NNSA could “fulfill its national security mission for the next 50 years in a safe, secure, and environmentally sound manner.” Id. at ¶¶ 7 and 8.
NNSA hosted two public meetings on the proposed CMRR project in August of 2002 and published a Draft EIS. Id. at ¶ 9. NNSA issued a Final EIS in November 2003. Id. NNSA published its Record of Decision (“ROD”) on the 2003 EIS in the Federal Register on February 12, 2004. Id. at ¶ 10; 69 Fed.Reg. 6967 (Feb. 12, 2004).
The 2004 ROD announced that the CMRR project would consist of two buildings: a single, above-ground consolidated special nuclear material-capable, Hazard Category 2 laboratory building (the CMRR-NF), and a separate but adjacent administrative office and support building, the Radiological Laboratory Utility Office Building (“RLUOB”). Cook Decl. at ¶ 10.
Defendants contend that, since the 2003 EIS and the 2004 ROD were published, new developments have arisen that require changes to the proposed CMRR-NF structure. Id. at ¶ 12. Specifically, a site-wide analysis of the geophysical structures that underlie the area occupied by LANL revealed new geologic information regarding the seismic conditions at the site. Id.; PI. Resp. to Deft. Mot. to Dismiss [Doc. 10] at 7-10. As a result of the new geologic information, as well as more information on the various support functions, actions, and infrastructure needed for construction, “changes were made to the proposed design of the CMRR-NF.” Cook Decl. at ¶ 12. In addition to addressing the seismic issues, other changes were made to “implement[] DOE’s nuclear safety management design requirements for increased facility engineering controls to ensure protection of the public, workers, and the environment.” Id. Also, “sustainable design principles have been incorporated to minimize the environmental impacts of construction and operation of the proposed CMRR-NF.” Id.
In light of the design changes, NNSA prepared a Supplement Analysis pursuant to 10 C.F.R. § 1021.314(c)(2) to determine (1) if the 2003 EIS should be supplemented, (2) if a new EIS should be prepared, or (3) if no additional NEPA document was required. Id. at ¶ 15. On July 1, 2010, counsel for Plaintiff wrote to the DOE and the NNSA and expressed concerns about the adequacy of NNSA’s NEPA analysis and the increased cost and scope of the CMRR-NF project. Plaintiff requested that DOE stop any and all CMRR-NF design activities, make no further contractual obligations, and seek no further funding until NNSA complete a new EIS for the CMRR-NF. Id. On July 30, 2010, NNSA informed the Plaintiff that it was preparing a Supplement Analysis. Id. Pri- or to NNSA’s completion of the Supplement Analysis of how to proceed with possible changes to the proposed design of the CMRR-NF, Plaintiff filed its Complaint on August 16, 2010. See Doc. 1.
On September 21, 2010, NNSA’s Deputy Administrator for Defense Programs, Donald L. Cook, decided “for prudential reasons” that the NNSA should complete an SEIS “to analyze the potential environmental impacts associated with the construction of the proposed CMRR-NF.” Cook Decl. at ¶ 16. A Notice of Intent to prepare an SEIS appeared in the October 1, 2010 issue of the Federal Register. See Ex. 2 attached to Doc. 9.
The preparation of the SEIS includes a public , scoping process which involves “two public scoping meetings to assist. NNSA in identifying potential impacts, alternatives, and mitigation strategies that should be analyzed in the SEIS.” Cook Deck at ¶ 17. Other federal agencies, as well as state *1222 agencies, Native American tribes, and the general public, including Plaintiff, are on notice of the NNSA’s intention to prepare an SEIS and are able to participate in determining the scope of the environmental analysis. On April 22, 2011, the NNSA released a draft of the SEIS to the public. See National Nuclear Security Administration, Draft Supplemental Environmental Impact Statement for the Nuclear Facility Portion of the Chemistry and Metallurgy Research Building Replacement Project at Los Alamos National Laboratory, Los Alamos, New Mexico (CMRR-NF SEIS) (DOE/EIS-0350-S1) (2011) (hereinafter “Draft SEIS”), available at http://www. nnsa.energy.gov/nepa/cmrrseis. Release of this draft began a comment period scheduled to last at least 45 days. All public comments must be considered in the preparation of the Final SEIS. Cook Decl. at ¶ 17.
Significantly, NNSA is still evaluating the aspects of relative sizing and layout of the proposed CMRR-NF, and the overall project design is less than 50 percent complete. Id. at ¶ 20. In fact, the Draft SEIS contains a new proposed design option for the CMRR-NF that requires significantly less excavation than the option that had been considered prior to the commencement of the SEIS process. See Draft SEIS at 2-14 to 2-19. Unquestionably, the CMRR-NF as currently envisioned will require an expenditure of resources and create a potential environmental impact greater than the project as envisioned in the 2003 EIS and 2004 ROD, prior to discovery of the seismic issues. However, no CMRR-NF construction is underway, and none will occur until after the SEIS is finalized. Cook Decl. at ¶21. If, after completion of the SEIS, NNSA decides to proceed with construction of the proposed CMRR-NF, the building is not expected to be occupied and operational until 2022. Id. at ¶ 23; PI. Resp. to Deft. Mot. to Dismiss [Doc. 10] at 11. Thus, no construction or other irrevocable actions appear to be ongoing while Defendants are engaging in the SEIS process.
ANALYSIS
A. Prudential Mootness
In his F & R, the Magistrate Judge found that Plaintiffs Complaint should be dismissed based on the doctrine of prudential mootness. Prudential mootness differs from the concept of the more common constitutional mootness. Specifically, prudential mootness - addresses a court’s discretion in the exercise of granting or withholding relief, rather than the power to grant relief.
See Southern Utah Wilderness Alliance v. Smith,
Under the prudential mootness doctrine, the central inquiry is whether “circumstances [have] changed since the beginning of litigation that forestall any occasion for meaningful relief.”
Fletcher v. United States,
The Magistrate Judge noted that Plaintiff seeks relief on the grounds that the project exceeds its scope as laid out in the 2003 EIS and 2004 ROD and that Plaintiff requests the Court to order Defendants to stop all activities in connection with the CMRR-NF pending completion of a new EIS and ROD. The F
&
R found that, because Defendants are currently in the process of undertaking an SEIS that would supercede the 2003 EIS and 2004 ROD by taking into account geological information and necessary design modifications that came to light after the completion of the 2003 EIS and 2004 ROD, “circumstances have changed since the beginning of litigation that forestall any occasion for meaningful relief,” and dismissal based on prudential mootness is appropriate. F & R ¶ 25 (quoting
Southern Utah Wilderness Alliance,
Plaintiffs Objections assert that the F & R misapplies the doctrine of prudential mootness because Defendants are engaged in ongoing NEPA violations, so that a promise to conduct NEPA analysis in the future cannot undo Defendants’ failure to comply with NEPA prior to irretrievably committing resources to the CMRR-NF project. Plaintiff contends that, with respect to NEPA claims, the doctrine of prudential mootness applies only when a project is so close to completion that any meaningful relief is precluded. See PI. Obj. [Doc. 33] at 4-5.
Plaintiff argues that, in this case, injunctive relief is appropriate because the project is still in its early stages and pausing the project to require Defendant to comply with its NEPA obligations would afford it meaningful relief. Plaintiff also characterizes Defendants’ preparation of an SEIS as a “smokescreen” to defeat an injunction, and alleges that Defendants will continue to be in violation of NEPA as they move forward with design and construction of the CMRR-NF project so that preparation of an SEIS cannot make its Complaint moot. Id. at 11-13.
Plaintiffs Objections rely on two fundamental assertions that do not bear up under scrutiny: first, that NEPA requires Defendants to undertake a new EIS from scratch before moving forward with the project, and second, that Defendants are currently moving forward with final design and construction in violation of NEPA. Because neither of these is correct, the *1224 Magistrate Judge properly applied the doctrine of prudential mootness to dismiss this case.
The record before the Court demonstrates that Defendants have followed an orderly process as contemplated by NEPA with respect to the project in question. Following the completion of a comprehensive EIS in 2003, the CMRR-NF project was approved in an unchallenged 2004 ROD. 5 Pursuant to the 2004 ROD, NNSA partially excavated the CMRR-NF site in 2006 to allow for site characterization and seismic mapping. New information developed from this excavation and corresponding new building safety requirements led to significant evolving design changes for the CMRR-NF. As a result of these design changes, prior to this lawsuit, NNSA began reviewing whether it should prepare an SEIS. Although the NNSA’s draft Supplement Analysis allegedly concluded that the potential environmental impacts from construction of the CMRR-NF in accordance with the evolving design changes were adequately bounded and addressed in the 2003 EIS, NNSA nonetheless committed to preparing an SEIS through a Notice of Intent published in the Federal Register.
Unquestionably, the scope of the CMRR-NF project has changed significantly since the 2003 EIS and 2004 ROD. Had Plaintiff come before the Court seeking an injunction requiring NNSA to complete an SEIS in the face of its continued refusal, the Court would be in a position of having to determine whether NEPA requires an SEIS under such changed circumstances. However, that is not the case currently before the Court. Defendants are proceeding with an SEIS, and are not moving forward with final design or construction pending completion of that process. Instead, Plaintiff contends that undertaking an SEIS does not satisfy Defendants’ NEPA obligations, because the changed circumstances are such that NEPA requires Defendants to prepare a new EIS from scratch for the CMRR-NF project. However, Plaintiff has come forward with no legal support for its claim that Defendants are in violation of NEPA for not having prepared a new EIS in the face of the project’s modifications.
Under 10 C.F.R. § 1021.314, which is part of the NEPA implementation procedures for DOE projects, “DOE shall prepare a supplemental EIS if there are substantial changes to the proposal or significant new circumstances or information relevant to environmental concerns,” and “DOE may supplement a draft EIS or final EIS at any time, to further the purposes of NEPA.” 10 C.F.R. §§ 1021.314(a), (b). In this case, whether doing so was voluntary or mandatory, Defendants are currently preparing a supplement to the initial EIS in response to changed circumstances, exactly as the NEPA regulations contemplate.
Plaintiffs contention that “[i]t is emphatically not the law that a NEPA case becomes moot when an agency states that it hopes, in the future, to fulfill its NEPA
*1225
obligations,” PI. Obj. at 3, and its reliance on
Blue Ocean Preservation Soc’y v. Watkins,
Plaintiffs contention that the doctrine of prudential mootness only applies in NEPA cases in which the project in question is substantially complete is similarly misguided. Plaintiff cites three cases from outside of the Tenth Circuit to make its argument:
Sierra Club v. U.S. Army Corps of Eng’r,
Plaintiff characterizes
Crutchfield
as holding that NEPA claims
“were not
prudentially moot because
work remained to be done on defendant’s .project.”
PI. Obj. at 4 (emphasis in original). However, it is misleading to suggest that
Crutchfield
uses project completion as the barometer for whether prudential mootness applies. The
Crutchfield
court did not find prudential mootness to be inapplicable to the dispute simply because work remained to be done on the challenged project; - instead it found that the case was not prudentially moot because the defendant county continued with construction on a wastewater treatment plant component prior to obtaining the necessary permit from the Army Corps of Engineers to dredge and destroy wetlands impacted by the project.
Plaintiffs reliance on
Sierra Club v. Babbitt
is similarly misplaced.
Babbitt
*1226
concerned the construction of a highway-through Yosemite National Park. Despite finding that the defendants had violated NEPA by failing to prepare an EIS for the project, the court declined to enjoin work on several portions of the road or to order that an EIS be prepared.
See
The three cases cited by Plaintiff related to substantial completion as a requirement for prudential mootness in the NEPA context are distinguishable in another way as well. All three of the cases concerned projects that involved ongoing construction and that either were, or could have been, rapidly completed. In the instant case, not only are Defendants holding off on construction of the CMRR-NF pending completion of the SEIS and accompanying ROD, but the project is expected to take at least ten years after the start of construction to become operational. See Cook Deck at ¶ 23. Thus, the danger of rendering an otherwise valid case moot through project completion is much reduced in this case compared to the cases cited by Plaintiff.
The Magistrate Judge correctly recognized that Defendants’ undertaking of an SEIS means that “circumstances have changed since the beginning of litigation that forestall any occasion for meaningful relief.” F
&
R ¶25 (quoting
Southern Utah Wilderness Alliance,
B. Ripeness
Although the Magistrate Judge did not base his decision on Defendants’ assertion that this case is not yet ripe for adjudication, this would have been an equally valid ground for dismissal. The doctrine of ripeness is premised on justiciability and is intended “to prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agen
*1227
cíes from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.”
Nat’l Park Hospitality Ass’n v. Dep’t of the Interior,
While the SEIS process is ongoing, there is no ripe “final agency action” for the Court to review pursuant to the Administrative Procedure Act, 5 U.S.C. § 704.
See, e.g., Coal, for Sustainable Res., Inc. v. U.S. Forest Serv.,
Plaintiff contends that the “final agency action” undertaken by Defendants was their implementation of the CMRR-NF project in violation of NEPA.
See
PI. Obj. at 7. For this contention, it cites
Catron County Bd. of Comm’rs v. U.S. Fish and Wildlife Serv.,
Plaintiff next contends that its claims are ripe because Defendants are currently engaged in making an irretrievable commitment of resources related to the CMRR-NF project.
See
PI. Obj. at 7 (citing
New Mexico ex rel. Richardson v. Bureau of Land Management,
In a closely related vein, Plaintiff also argues that Defendants have violated NEPA by predetermining the result of its environmental analysis, so that the SEIS process is essentially a sham. Predetermination occurs “only when an agency
irreversibly and irretrievably
commits itself to a plan of action that is dependent upon the NEPA environmental analysis producing a certain outcome,
before
the agency has completed that environmental analysis.”
Forest Guardians v. U.S. Fish & Wildlife Serv.,
Plaintiff relies heavily on
Davis v. Mineta,
Unlike
Davis,
in which the court had to rule on the adequacy of a final agency action (the issuance of a FONSI), the Court here is asked to step in while Defendants are still in the process of completing an SEIS as contemplated by NEPA. This action would be premature. Further, the continuation of design activities as part of the SEIS process is hardly a showing of predetermination of the type at issue in
Davis.
An agency may legitimately have a preferred alternative in mind when it is conducting a NEPA analysis.
See Forest Guardians,
Plaintiff also relies on the unpublished case of Los Alamos Study Group v. O’Leary, No. 94-1306-M (D.N.M. Jan. 26, 1995), for the proposition that “under NEPA regulations, it is illegal for an agency to continue an activity while an EIS is being prepared unless such action ‘will not prejudice the ultimate decision on the program.”’ O’Leary, Slip Op. at 19 (citations omitted). O’Leary also arises in a different context than this case. O’Leary concerned a project for which the DOE never conducted an EIS. Despite failure to complete an EIS, the defendant had already completed one phase of the project and was in the process of constructing the two remaining phases of the project. See id. at 2. The court enjoined construction of the project (but not planning or design), pending completion of the required EIS. In this case, NNSA has taken no action that was not already analyzed and approved in the 2003 EIS and 2004 ROD, and no CMRRNF construction is occurring. Thus, unlike the defendant in O’Leary, NNSA has followed the proper procedure of approving the project pursuant to an EIS and delaying construction while analyzing potential design changes in the SEIS.
*1230
Because the Court does not know what form the SEIS will ultimately take, and because Plaintiff has not demonstrated the type of irreversible and irretrievable commitment to a particular plan as discussed in the case law, the Court finds that any claim of predetermination is not ripe at this point. Significantly, even if the Court could make a finding of predetermination at this point, such a finding would not automatically mean that an agency’s analysis was arbitrary and capricious, it only means that a court reviewing the final agency decision “is more likely to conclude that the agency failed to take a hard look at the environmental consequences of its actions and, therefore, acted arbitrarily and capriciously.”
Forest Guardians,
CONCLUSION
In rendering its decision in this case, the Court has not considered any of the policy considerations raised in this action, such as whether the proposed new nuclear facility is necessary for national security, whether a delay in construction will be detrimental to research, or whether the existing facility can be modified sufficiently to serve LANL’s needs thereby eliminating the need for a new facility. Such policy debates are not relevant to this litigation. Instead, the Court bases its decision solely on what NEPA requires and where this case currently is in the NEPA process.
Plaintiffs interpretation of NEPA would condemn agencies to the role of the mythical Sisyphus, forever advancing projects up a hill, only to be forced to start over from scratch when they encounter new information that results in design challenges. This is not what NEPA requires. Instead, the NEPA regulations contemplate that agencies will address significant new circumstances through the issuance of an SEIS, just as Defendants are in the process of doing in this case. Some of the concerns raised by Plaintiff may be addressed by the issuance of the SEIS and accompanying ROD; it is too early to tell while the process is ongoing. On the other hand, it may well be that at the end of the process, Plaintiff will continue to have concerns about whether Defendants sufficiently considered alternative proposals and the potential environmental impacts of their chosen design. If so, judicial review of the agency’s final decision will be available at that point. The Magistrate Judge was correct in finding that Plaintiffs Complaint should be dismissed on the grounds of prudential mootness because Defendants are undertaking an SEIS. Dismissal is also appropriate because, until the completion of the SEIS process, this case is not yet ripe for review.
IT IS THEREFORE ORDERED that Plaintiffs Objections to Magistrate Judge’s Proposed Findings and Recommended Disposition [Doc. 33] are overruled, and that the Magistrate Judge’s Proposed Findings and Recommended Disposition [Doc. 25] is adopted. IT IS FURTHER ORDERED that Defendants’ Motion to Dismiss for Lack of Jurisdiction [Doc. 9] is hereby granted.
MAGISTRATE JUDGES’S PROPOSED FINDINGS AND RECOMMENDED DISPOSITION
THIS MATTER comes before the Court on the Honorable Judith Herrera’s Order of Reference filed on November 17, 2010, pursuant to the provisions of 28 U.S.C. §§ 636(b)(1)(B). [Doc. 15.] The District Court referred this matter to the under *1231 signed Magistrate Judge to submit proposed findings of fact and recommendations for disposition of Defendants United States Department of Energy, the Honorable Stephen Chu, the National Nuclear Security Administration, and the Honorable Thomas Paul D’Agostino’s Motion to Dismiss for Lack of Jurisdiction and Brief in Support filed on October 4, 2010. [Doc. 9.]
I.Procedural Background
1. This action arises under the National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-4870(0 (“NEPA”), together with the implementing regulations for NEPA issued by the White House Council on Environmental Quality (the “CEQ Regulations”), 40 C.F.R. Part 1500-08, and regulations issued by the Department of Energy (“DOE”), 10 C.F.R. Part 1021. [Doc. 1 at ¶ 1.] This action also arises under the Administrative Procedure Act (“APA”), 5 U.S.C.A. §§ 701 et seq. [Id.]
2. In its Complaint, Plaintiff challenges the adequacy of the Department of Energy/National Nuclear Security Administration’s (“DOE/NNSA” or “NNSA”) analysis of potential environmental impacts from the construction and operation of the proposed Chemistry and Metallurgy Research Replacement Nuclear Facility (“CMRRNF”) at Los Alamos National Laboratory (“LANL”). [Doc. 1 at ¶ 2.] The National Nuclear Security Administration (“NNSA”) is responsible for the management and security of the nation’s nuclear weapons, nuclear nonproliferation, and naval reactor programs. [Doc. 9, Ex. A, and 50 U.S.C. § 2401(b).] NNSA is also responsible for the administration of LANL. [Id.]
3. The Complaint seeks a declaratory judgment and mandatory injunction requiring Defendants to prepare a new Environment Impact Statement (“EIS”) regarding the CMRR-NF and also seeks to prohibit all further investments in the CMRR-NF. [Doc. 1 at ¶ 3.] Specifically, in Count I, Plaintiff alleges that.Defendants violated NEPA and the APA by failing to prepare an applicable EIS for the CMRR-NF. It claims that Defendants’ current proposal differs substantially from the 2003 EIS and the 2004 Record of Decision (“ROD”) and that a new EIS should be prepared. ■ [Doc. 1 ¶¶ 52-64.] In Count II, Plaintiff alleges that Defendants have failed to develop an EIS which addresses “connected actions” to the CMRRNF and that Defendants should prepare a new EIS which address these actions. [Doc. 1 ¶¶ 65-71.] In Count III, Plaintiff alleges that Defendants failed to provide required mitigation measures and a mitigation action plan in the 2003 EIS and the 2004 ROD and that they should prepare a new EIS which addresses reasonable mitigation measures. [Doc. 1 ¶¶ 72-79.] In Count IV, Plaintiff alleges that the Defendants’ decision making processes for the CMRR-NF exceed the scope of the 2003 EIS and the 2004 ROD and that all activities should be stopped pending the completion of a new EIS and ROD. [Doc. 1 ¶¶ 80-90.] In Count V, Plaintiff alleges that the proposed CMRR-NF involves a much greater commitment of resources and has a far greater impact than what was analyzed in the 2003 EIS and the 2004 ROD. It alleges that the DOE authorized production of a Supplement Analysis which addresses the changed project parameters and allegedly'determines if a Supplemental EIS (“SEIS”) or a new EIS should be prepared has not been made public or provided to the Plaintiff. [Doc. 1 ¶¶ 91-95.]
4.Defendants filed a Motion to Dismiss [Doc. 9] which argues that (1) some of Plaintiffs claims are time-barred, (2) Plaintiffs claims are not ripe for review, (3) Plaintiffs claims are moot, and alternatively (4) Plaintiffs claims should be dis *1232 missed under the doctrine of prudential mootness.
5. Having considered the pleadings, the exhibits, and the relevant law, the undersigned Magistrate Judge recommends that Plaintiffs Complaint be dismissed pursuant to the doctrine of prudential mootness.
II. Factual Background
6. In 2002, NNSA published a Notice of Intent to prepare the CMRR-NF EIS and invited public comment on the CMRR-NF EIS proposal. [Doc. 9-1 at ¶ 9.] The Chemical and Metallurgy Research (“CMR”) building which prompted Defendants to propose the CMRR-NF in 2002 was almost 60 years old and near the end of its useful life. [Id. at ¶ 6.] The CMR' building is a facility which has “unique capabilities for performing special nuclear material analytical chemistry, materials characterization, and actinide 1 research and development.” [Id. at ¶ 5.] CMR supports various national security missions including nuclear nonproliferation programs; the manufacturing, development, and surveillance of pits (the fissile core of a nuclear warhead); life extension programs; dismantlement efforts; waste management; material recycle and recovery; and research. [Id.] NNSA’s proposal to construct the replacement facility, CMRR-NF, was to insure that NNSA could “fulfill its national security mission for the next 50 years in a safe, secure, and environmentally sound manner.” [Id. at ¶¶ 7 and 8.]
7. NNSA hosted two public meetings on the proposed CMRR in August of 2002 and published a Draft EIS. [Id. at ¶ 9.] NNSA issued a Final EIS in November 2003. [M] NNSA published its Record of Decision (“ROD”) on the 2003 EIS in the Federal Register on February 12, 2004. [Id. at ¶ 10; 69 Fed.Reg. 6967 (Feb. 12, 2004).]
8. The 2004 ROD announced that the CMRR Project would consist of two buildings: a single, above-ground consolidated special nuclear material-capable, Hazard Category 2 laboratory building (the CMRR-NF), and a separate but adjacent administrative office and support building, the Radiological Laboratory Utility Office Building (“RLUOB”). [Doc. 9-1 at ¶ 10.]
9. Since the 2003 EIS and the 2004 ROD were published, Defendants acknowledge that new developments have arisen which require changes to the proposed CMRR. [Id. at ¶ 12.] A site-wide analysis of the geophysical structures that underlay the area occupied by LANL was prepared and revealed new geologic information regarding the seismic conditions at the site. [Id.; Doc. 10 at pp. 7-10.] As a result of the new geologic information, as well as more information on the various support functions, actions, and infrastructure needed for construction “changes were made to the proposed design of the CMRR-NF.” [Doc. 9-1 at ¶ 12.] In addition, other changes were made to ensure that the facility “implements DOE’s nuclear safety management design requirements for increased facility engineering controls to ensure protection of the public, workers, and the environment.” Also, “sustainable design principles have been incorporated to minimize the environmental impacts of construction and operation of the proposed CMRR-NF.” [Id.]
10. In light of the design changes, NNSA prepared a Supplement Analysis pursuant to 10 C.F.R. § 1021.314(c)(2) to determine (1) if the 2003 EIS should be supplemented, (2) if a new EIS should be *1233 prepared, or (3) if no further NEPA document was required. [Id. at ¶ 15.]
11. On July 1, 2010, counsel for Plaintiff wrote to the DOE and the NNSA and expressed concerns about the cost and adequacy of NNSA’s NEPA analysis for the CMRR-NF. Plaintiff requested that DOE stop any and all CMRR-NF design activities, make no further contractual obligations, and seek no further funding until NNSA complete a new EIS for the CMRR-NF. [Id.]
12. On July 30, 201Ó, NNSA informed the Plaintiff that it was preparing a Supplement Analysis. [Id.]
13. Prior to NNSA’s completion of the Supplement Analysis of how to proceed with possible changes to the proposed design of the CMRR-NF, Plaintiff filed its Complaint on August 16, 2010. [Doc. 1.]
14. On September 21, 2010, NNSA’s Deputy Administrator for Defense Programs, Donald L. Cook, decided “for prudential reasons” that the NNSA should complete an SEIS “to analyze the potential environmental impacts associated with the construction of the proposed CMRR-NF.” [Doc. 9-1 at § 16.] A Notice of Intent to prepare an SEIS appeared in the October 1, 2010 issue of the Federal Register. [Doc. 9, Ex. 2.]
15. The preparation of the SEIS includes a public scoping process which involves “two public scoping meetings to assist NNSA in identifying potential impacts, alternatives, and mitigation strategies that should be analyzed in the SIS.” [Doc. 9-1 at ¶ 17.] Other federal agencies, as well as state agencies, Native American tribes, and the general public, including Plaintiff, are on notice of the NNSA’s intention to prepare an SEIS and can participate in determining the scope of the environmental analysis. Thereafter, the NNSA will make a draft of the SEIS available to the public for a 45-day comment period and all comments will be considered in the preparation of the Final SEIS. [M]
16. NNSA is still evaluating the aspects of relative sizing and layout of the proposed CMRR-NF, and the overall project design is less than 50 percent complete. [Doc. 9-1, Ex. 1 ¶ 20.] No CMRRNF construction is underway, and none will occur while the SEIS is being prepared. [Id. at ¶ 21.]
17. Between October 2010 and June 2011, the expected SEIS period, the overall design is expected to advance by only approximately 15 percent. [Id. at ¶25.] Construction of the CMRR-NF will not occur until after the SEÍS is completed and a new ROD issued. [Doc. 9 at p. 27; Doc. 9-1 at ¶ 21.] If, after completion of the SEIS, NNSA decides to proceed with construction of the proposed CMRR-NF, the building is not expected to be occupied and operational until 2022. [Id. at ¶ 23; Doc. 10 at 11.] NNSA has expended money over the course of the past six years for the design of the proposed CMRR-NF. [Doc. 9-1 at ¶ 19.]
III. Legal Framework for Prudential Mootness.
18. Prudential mootness is a legal doctrine closely related to Article III mootness. However, prudential mootness arises from the doctrine of
remedial discretion. Southern Utah Wilderness Alliance v. Smith,
19. The Tenth Circuit has expressly recognized the doctrine of prudential mootness, and has stated that “it has particular applicability in cases ... where the relief sought is an injunction against the government.”
Southern Utah Wilderness Alliance v. Smith,
20. Under the prudential mootness doctrine, the central inquiry is whether “circumstances [have] changed since the beginning of litigation that forestall any occasion for meaningful relief.”
Fletcher v. United States,
21. “[E]ven if some remnant of the original controversy be still alive [sic], [circumstances may exist] where the courts, as a matter of prudence and sound discretion, should stay their hand and withhold drastic injunctive relief.”
State of New Mexico v. Goldschmidt,
22. The United States Supreme Court has stated that “sound discretion withholds the remedy where it appears that a challenged ‘continuing practice’ [of an administrative agency] is, at the moment adjudication is sought, undergoing significant modification so that its ultimate form cannot be confidently predicted.”
A.L. Mechling Barge Lines, Inc. v. United States,
23. Because the doctrine of prudential mootness is concerned with the court’s discretion to exercise its power to provide relief, the Court’s determination of prudential mootness is reviewed for an abuse of discretion.
Fletcher v. U.S.,
TV. Analysis
24. Plaintiffs Complaint seeks declaratory and injunctive relief with regard to the Defendants’ activities in connection with the design of the CMRR-NF on the grounds that the project exceeds its scope as defined in the 2003 EIS and the 2004 ROD.
25. Defendants are currently in the process of undertaking an SEIS, which would supercede the 2003 EIS and 2004 ROD, to ascertain how best to proceed
*1235
with the proposed CMRR-NF in light of newly discovered geological information as well as design modifications that came to light after the completion of the 2003 EIS and 2004 ROD. After the SEIS is completed, NNSA will decide, based on that study, how best to proceed with the proposed CMRR-NF. Thus “circumstances have changed since the beginning of litigation that forestall any occasion for meaningful relief.”
Southern Utah Wilderness Alliance v. Smith,
26. “The purpose of an injunction is to prevent future violations.”
United States v. W.T. Grant Co.,
27. The claims in the Plaintiffs Complaint seek declaratory and injunctive relief to ensure that Defendants’ design and planning of the CMRR-NF conform to Plaintiffs request for a court-ordered new EIS. However, because the Defendants are currently conducting an SEIS which has not yet been completed, it is premature for the Court to order the Defendants to prepare a new EIS. The SEIS may very well address the Plaintiffs concerns about CMRR-NF.
28. Plaintiff also requests that this court order Defendants to stop all activities in connection with the CMRR-NF pending the completion of a new EIS and ROD. [Doc. 1 ¶¶ 80-90.] Under the doctrine of prudential mootness, the district court has the discretion to withhold injunctive relief “even if some remnant of the original controversy be still alive.”
Goldschmidt,
29.Here, the doctrine of prudential mootness counsels against a court issued injunction to halt all work. The Defendants are in the process of changing their policy in that they are conducting an SEIS which will supercede the 2003 EIS and 2004 ROD. The expected duration for the completion of the SEIS is from October 2010 to June 2011. [Doc. 9 at p. 26.] In addition, any on-going activities pending the completion and publication of the SEIS are preliminary. [Doc. 10 at p. 10.] The actual construction of the CMRR-NF will not occur until after the SEIS is completed and a new ROD issued. [Doc. 9 at p. 27.] 2 Furthermore, construction will take more *1236 than a decade, and the facility is not expected to be occupied and operational until 2022. [Doc. 10 at p. 11; Doc. 9 at p. 16-17.] Plaintiff will have ample opportunity to renew its complaint if it finds it necessary when the SEIS is filed and before any construction begins.
RECOMMENDED DISPOSITION
For the reasons stated above the undersigned Magistrate Judge recommends that the District Court dismiss Plaintiffs Complaint in its entirety based on the doctrine of prudential mootness.
Timely objections to the foregoing may be made pursuant to 28 U.S.C. § 636(b)(1)(c). Within fourteen days after a party is served with a copy of these proposed findings and recommendations that party may, pursuant to § 636(b)(1)(c), file written objections to such proposed findings and recommendations with the Clerk of the United State District Court, 333 Lomas N.W., Albuquerque, NM 87102. A party must file any objections within the fourteen-day period allowed if that party wants to have appellate review of the proposed findings and recommendations. If no objections are filed, no appellate review will be allowed.
Notes
. Defendants also timely filed Objections to the Magistrate Judge’s Proposed Findings and Recommended Disposition [Doc. 32]. These Objections focus only on two minor inaccuracies in the factual section of the F & R, but do not object to the recommended disposition. The two minor inaccuracies are corrected in this Court’s statement of facts.
. At the April 27, 2011 hearing, Plaintiff presented the Court with three binders of materials: (1) Plaintiff’s Opening Statement Exhibits; (2) Gregory Mello Testimony Exhibits; and (3) Frank Von Hippel Testimony Exhibits. In addition, the Court received a copy of Defendants’ Draft Supplemental Environmental Impact Statement. While these materials were not formally moved into evidence, both counsel referred to the exhibits, as did the witnesses, and the Court considered them in making its ruling. Thus, they will be considered part of the record.
.This background section is taken largely from the Magistrate Judge’s thorough but concise summation of the facts as laid out in Doc. 25 at 1230-33.
. “Actinide” refers to the 14 elements with atomic numbers from 90 to 103. Uranium and Plutonium are actinides. See [Doc. 9 at 3 n. 1.]
. Defendants correctly point out that any challenges Plaintiff makes to the sufficiency of the original EIS and ROD are time-barred. NEPA claims are subject to the APA’s general six-year limitation period under 28 U.S.C. § 2401(a).
See Greater Yellowstone Coal. v. Tidwell,
. " 'Actinide' refers to the members of a series of elements that encompasses the 14 elements with atomic numbers from 90 to 103. Uranium and Plutonium are actinides.” [Doc. 9 at footnote 1.]
. Plaintiff states that "[t]he Infrastructure Package may begin in March 2011.” (Emphasis added.) [Doc. 10 at pp. 10-11.] Not only is this assertion qualified (infrastructure "may” begin), it is also unsupported. Moreover, even if Defendants should acknowledge that such infrastructure work will begin in March, the work described by Plaintiffs which "may” take place is not sufficient enough to alter the undersigned Magistrate Judge's recommendation that the doctrine of prudential mootness counsels against a court issued injunction to halt all work.