145 N.Y.S. 205 | N.Y. App. Div. | 1914
This action was brought to recover a balance alleged to be due and payable for work performed and materials furnished under a contract in writing, bearing date June 18, 1909, for bridge construction work. The amount earned and unpaid on the contract was not controverted, but the city pleaded that plaintiff was guilty of breaches of the contract in failing to take proper precautions to prevent damages by fire and thereby became responsible for causing two fires on the work, resulting in damage to parts of the bridge not constructed by plaintiff;
The city through its department of bridges was engaged in constructing the Manhattan bridge over the East river. It evidently first let the general masonry and steel construction work. On the 18th day of June, 1909, the structural construction work had so far progressed that the city through the department of bridges entered into a contract with plaintiff for certain surface construction work described in the specifications in general terms as follows, viz.: “Ingeneral this contract and the Specifications and plans forming a part thereof will cover the furnishing of all materials and workmanship necessary for the construction of the metal railings, stairways, grilles and tablets, the police shelters, benches, etc., the roadway pavement and underflooring, the sidewalk paving, the complete track work on lower deck and the complete lighting system, all as more fully specified hereinafter, for the suspended spans, towers, anchorages and approach spans of the Manhattan Bridge, included between the abutment at Division street, in the Borough of Manhattan, and the abutment at Sands street, in the Borough of Brooklyn; and the construction of the temporary roadway and footwalk approaches on the terminal property in the Boroughs of Manhattan and Brooklyn.”
The plaintiff maintained a night watchman on the work, but on the evening of November 12,1909, it discharged him, and that night a fire originated in its tool house or watchman’s shanty on the bridge, causing damage to the granite work to the extent
The specifications which became part of the contract provided under the heading “Damaged Parts,” that “All parts damaged during erection, as well as at any other time prior to the final acceptance of the work, shall be made good to the satisfaction of the Engineer and at the cost of the Contractor; ” and under the heading “Protection Against Fire,” that “During the entire erection of the work ample precaution shall be taken to protect it against injury by fire.” The contract proper provides, among other things, that the contractor “will not assign, transfer, convey, sublet or otherwise dispose of this contract, or his right, title or interest in or to the same or any part hereof, without the previous consent in writing of the Commissioner indorsed hereon or hereto attached; ” also that “The Contractor shall take proper precautions, under the directions of the Engineer, to protect the finished work from injury pending the completion of the entire contract. Such precautions shall not relieve the Contractor from the obligation to make good any damage which may be incurred during construction; ” and required the contractor to take the usual precautions by placing guards and lights to prevent accidents and injuries to persons and damage to property, and provided
It is further expressly provided in the contract that the city shall not be estopped by any certificate or payment “from demanding and recovering from the Contractor such loss as it may sustain by reason of his failure to comply with the specifications.”
I am of opinion that the provisions of the specifications quoted, which require the contractor to take ample precautions to protect the work against fire and requiring him to make good all parts of the work damaged during construction, should be construed as applicable to damages, for which he is responsible, to the construction work as a whole, viz., the entire bridge, and not merely to the particular part of the work which he contracted to perform. It is contended that a further provision of the specification under the heading “ Protection of Existing Work,” requiring the contractor to protect the masonry piers and anchorages by such means
On the same theory the plaintiff is liable for the damages caused by the second fire. It may be that plaintiff was not guilty of negligence in connection with that fire, and yet I think that presented a question of fact for the jury, for it knew the negligent manner in which the asphalt company was conducting the work and that' a fire had been caused in like manner a short time before the one in question, and it had been specially warned by the engineer. However, the consent which the commissioner of bridges gave “ to the employment ” of the asphalt company to perform the asphalting, did not release the plaintiff from its liability to the city. The letter of the commissioner, which it is claimed is a consent to plaintiff’s subletting the work, was written in answer to one from plaintiff, and so far as material is as follows: “I note that you have arranged to employ certain sub-contractors in the work of carrying out your contract for constructing the railings, stairways, etc., roadway and footwalk pavements, track and electrical equipments of the Manhattan Bridge.
“Pursuant to Paragraph (V) of your contract, I hereby consent to the employment of the said sub-contractors, namely: * * *
“ Barber Asphalt Paving Company,
“ Pennsylvania Steel Company. * * *
“It is expressly •understood that the consent to employ the aforesaid contractors is not a consent to the assignment by you to them of any part of your contract, or any of the moneys to become due and payable under your contract.”
It is quite clear, I think, that plaintiff thereafter continued
It follows that plaintiff was not entitled to recover, and that the judgment must be reversed, with costs, and the complaint dismissed, with costs, on defendant’s motion duly made at the close of the evidence.
Ingraham, P. J., McLaughlin, Dowling and Hotchkiss, JJ., concurred.
Judgment reversed, with costs, and complaint dismissed, with costs. Order to be settled on notice.