211 F. 453 | 6th Cir. | 1914
In the year 1908, the People’s Construction Company, an Iowa corporation (which we shall hereafter call the Construction Company), was awarded the contract for certain sewer construction in the city of Janesville, Wis. Following the award, the Reinforced Concrete Pipe Company (hereafter called the Pipe Company), a West Virginia corporation, having its “central office" at Jackson, Mich., entered into a written agreement (made at Janesville) with the Construction Company for the manufacture for the latter company of' upwards of 10,000 lineal feet of reinforced concrete pipe of different sizes, at an aggregate price of more than $11,000; the Pipe Company furnishing all the forms required for the construction, the steel reinforcement (which was both longitudinal and lateral), the-derrick for lowering the pipe into the trench, and a saddle (presumably for use in so lowering the pipe), as well as the superintendent; the Construction Company furnishing the cement and gravel required for the concrete, as well as the labor required in making, the pipe, which was to be manufactured in Janesville “along the line of sewer construction of said city”; the Pipe Company agreeing to use in the manufacture of the concrete given proportions of specified cement and gravel, and to reinforce the same “in keeping with the standard of reinforcement in use by” the Pipe Company; also to provide openings
The Wisconsin statute (section 1770b) provides that:
“No corporation, incorporated or organized otherwise than under the laws of this state * * * shall transact business or acquire, hold, or dispose of property in this state until such corporation shall have caused to be filed in the office-of the Secretary of State a copy of" its charter, articles of association or incorporation”
—the officer named being made the corporation’s attorney for the service of process. Failure to comply with the statute makes the corporation and those acting for it in the state liable to fine. It further provides that:
“Every contract made by. or on behalf of any such foreign corporation, affecting the personal liability thereof or relating to property within this state, before it shall have complied with the provisions of this section, shall be wholly void on its behalf and on behalf of its assigns, but shall be enforceable against it or them.”
A fee of $25, with an added percentage on capital employed in the state above a stated amount, is required. The Pipe Company never complied with this statute. The Construction Company paid the Pipe Company about $4,800 under the contract, failing to make further payments by reason of certain claims not important here. The Pipe Company assigned its right of action to the plaintiff, who brought suit upon the contract in a state court of Michigan, against the Construction Company and the Surety Company, on the theory that the bond inured to the benefit of the Pipe Company, as a furnisher of labor and materials for a public work. The suit was removed to the United States Circuit Court by reason of diversity of citizenship of the parties. The Construction Company was not served with’process, and did not appear; the Surety Company defended. At the conclusion ,of the trial the court directed verdict for defendant, upon the grounds, first, that the action, if it lay at all, must be brought in the name of the city of Janesville; second, that the Pipe Company was not a material-
“The trial court found as matter of fact that the subscription contract was made in Wisconsin, and that it affected the personal liability of the plaintiff. If there is sufficient evidence in the record to sustain this finding, the judgment must be affirmed. This result must follow regardless of whether the plaintiff was or was not transacting business in this state within the meaning of subdivision 2; § 1, of the 1905 law.”
We are thus brought to the question whether the statute makes the contract before us absolutely void, or whether it merely imposes some other penalty for failure to comply with it. Had it merely forbidden suit in the state courts, or merely imposed the liability of the corporation and its officers to penalties, without in terms declaring the contract void, it should be held that such prohibition or penalty was regarded by the Legislature as ample to effect the legislative object; and in such case the statute would create no impediment to suit in the courts of other states or in the federal courts. Cooper v. Ferguson, supra; Fritts v. Palmer, 132 U. S. 282, 289, 10 Sup. Ct. 93, 33 L. Ed. 317; Allen v. Alleghany County, 196 U. S. 458, 462, 25 Sup. Ct. 311, 49, L. Ed. 551; David Lupton’s Sons v. Automobile Club of America, 225 U. S. 489, 496, 32 Sup. Ct. 711, 56 L. Ed. 1177, and cases cited; Johnson v. New York Breweries Co., Ltd. (C. C. A. 2) 178 Fed. 513, 101 C. C. A. 639. And had the statute imposed both the prohibition and penalty referred to, perhaps the result above stated would equally follow. But if the
The statute provides that contracts of a foreign corporation which has not complied with the requirements of the section “shall be wholly void on its behalf and on behalf of’ its assigns, but shall be enforceable against it or them.” The Supreme Court of the state has construed the statute as making absolutely void all contracts made by foreign corporations affecting their liability, or relating to property within the state, before compliance with the statute (Ashland Lumber Co. v. Detroit Salt Co., 114 Wis. 66, 76, 89 N. W. 904; Allen v. Milwaukee, 128 Wis. 678, 687, 106 N. W. 1099, 5 L. R. A. [N. S.] 680, 116 Am. St. Rep. 54, 8 Ann. Cas. 392); and this court is bound by that construction, which also has been recognized and applied by the Supreme Court of the United States in Diamond Glue Co. v. United States Glue Co., supra. True the Supreme Court of the State, in Lanz-Owen & Co. v. Garage Equipment Co., 151 Wis. 555, 139 N. W. 393, decided since the contract in question was made (and, indeed, since the decision of this case below), has said of contracts made before compliance with the statute that they are not “absolutely void,” but are “void only at the election of the party dealing with the corporation,” but that decision again affirms that such contracts are “wholly void.on its [the foreign corporation’s] behalf and on behalf of its assigns,” and that “neither the corporation nor its assigns could enforce it against the other party.” •We think the expressions contained in this later opinion do not, so far as respects the instant case, change the rule before announced by that court. Indeed the right of the opposite party to enforce the contract was expressly written in the statute when previously construed by the Wisconsin decisions, as well as in Diamond Glue Co. v. U. S. Glue Co. The basis of plaintiff’s asserted right of action is, and must be, the contract between the Pipe Company and the Construction Company. The latter has not affirmed the contract; it is not in court; there is no limitation of time within which it must elect whether or not to enforce; and the Surety Company, if pursued, has, we think, as a party in interest, the right to assert the void nature of the contract as against the Construction Company. Hanna v. Kelsey Realty Co., 145 Wis. 276, 282, 129 N. W. 1080, 33 L. R. A. (N. S.) 355, 140 Am. St. Rep. 1075; Lanz-Owen & Co. v. Garage Equipment Co., supra.
It results from these views that verdict was properly directed for defendants. This conclusion makes it unnecessary to consider the other grounds upon which the action of the trial court is based; and we accordingly intimate no opinion thereon.
The judgment of the district court is affirmed, with costs.