196 Mass. 497 | Mass. | 1907
The defendant appealed from the interlocutory order overruling its demurrer to the bill, and its counsel have discussed some of the questions naturally arising thereon. As however all these questions are raised, and perhaps more advantageously for the defendant, upon the master’s report and the exceptions thereto, and as the appeal has not been argued specifically, it need not be considered at any great length. We think it plain that the bill as amended sets forth a good cause of action. It is drawn with a double aspect, seeking to obtain a cancellation of the contract of the plaintiffs with the defendant, first upon the ground that it was fraudulently obtained from the plaintiffs by giving to them as a basis for the proposed contract erroneous estimates of the work to be done, which largely understated the amount thereof, and keeping from the files of the town clerk of Athol and concealing from the plaintiffs the maps, drawings, profiles and specifications in accordance with which the contract was to be and in fact was made; and secondly upon the ground that the contract was made under a mutual mistake of both parties arising from the fact that the estimates upon which the plaintiffs made their bid and upon the faith of which they entered into the contract, which estimates were made by an engineer employed by the defendant for that purpose, and were given to the plaintiffs by the defendant as correct, were erroneous and materially underestimated the amount of the work tó be done. If the proof came up to the averments of the bill on either of these grounds it would entitle the plaintiffs to relief. It would be enough if either of the grounds alleged was made out. Redgrave v. Hurd, 20 Ch. D. 1. Davies v. London & Provincial Ins. Co. 8 Ch. D. 469. Newbigging v. Adam, 34 Ch. D. 582. Trail v. Baring, 4 DeG., J. & S. 3168, affirming S. C. 4 Giff. 485. Rawlins v. Wickham, 3 DeG. & J. 304. Daniel v. Mitchell, 1 Story, 172. Goodwin v. Massachusetts Loan & Trust Co. 152 Mass. 189. Motherway v. Wall, 168 Mass. 333. Keene v. Demelman, 172 Mass. 17. Boles v. Merrill, 173 Mass. 491. Paine v. Upton, 87 N. Y. 327. Winnipisseogee Lake Co. v. Perley, 46 N. H. 83. The bill could be maintained both for a cancellation of the contract and for the recovery of what
It sufficiently appears by the master’s report that, although no fraud was practised upon the plaintiffs, their contention that the contract was entered into under a mutual mistake caused by the error of the engineer employed by the defendant to make the estimate that was furnished by the defendant to the plaintiffs and other contractors for them to base bids upon, was proved. The plaintiffs had access also to correct profile maps and drawings and to printed specifications; and it would have been possible for a skilled engineer, by correctly scaling these plans, to ascertain and correct the mistakes made in the estimate furnished by the defendant to the plaintiffs and other
Upon these findings taken by themselves, under the circumstances which appear, here, it is manifest, upon the cases already referred to, that the plaintiffs are entitled to the relief which they seek, unless this should be refused to them by reason of some of the specific objections of the defendant, or unless it should appear, upon some of their exceptions, that there has been material error on the part of the master; and we proceed to consider these questions.
The defendant contends that there was no right of cancellation by reason of the issuing of the paper containing the inaccurate estimates, because this was put forth in good faith and its inaccuracy was unknown and unsuspected by the defendant’s officers until after the plaintiffs had begun their work, and because the plaintiffs in their contract expressly covenanted to do the work “ in strict accordance with the maps, drawings, profiles and specifications prepared therefor and on file in the office of the town clerk, ... all of which are to be considered as part and parcel of these presents, and to be construed therewith,” and further in the same contract in express terms admitted and agreed “ that the amounts and quantities of materials to be furnished and work to
It is contended also that the agreement should not be set aside by reason of this mistake, because it is not to be treated as a mistake of fact. The paper it is contended was given to the plaintiffs merely as an estimate ; the defendant, though believing it to be accurate, did not attempt to pass off its belief as knowledge ; Chatham Furnace Co. v. Moffatt, 147 Mass. 403; it did nothing to prevent a full investigation. Parker v. Moulton, 114 Mass. 99. It contends substantially in the language of this court in Schramm v. Boston Sugar Refining Co. 146 Mass. 211, 216, that a contract is not to be set aside merely because before the making thereof there may have been an honest expression of opinion, or an honest statement of a fact not purporting to be as of knowledge, that the thing contracted for will turn out better
Nor was there such negligence of the plaintiffs in accepting the erroneous estimate without employing the other means of knowledge furnished by the defendant as to bar their relief as matter of law. The master has found that the maps and plans were in the selectmen’s rooms, which were used also by the town clerk, that the plaintiffs saw them there and had full opportunity to inspect them and to scale them for the purpose of comparing them with the estimate, but that the plaintiffs were not grossly negligent in not examining the plans more minutely, and had a right to assume that the engineer’s estimate was at least approximately correct. The defendant relies here upon the many cases in which it has been held that one to whom fraudulent representations are made has no right to rely upon them if the facts are within his observation or if he has equal means of knowing the truth. Savage v. Stevens, 126 Mass. 207. Brown v. Leach, 107 Mass. 364. Salem India Rubber Co. v. Adams, 23
But it is argued that the contract cannot now be cancelled, because the defendant cannot be put in statu quo. The master’s finding as to this is that the plaintiffs “ could not by rescinding their contract place the defendant in the same condition that it was in before the beginning of the work, or in other words, could not undo the work of construction, so far as it had been done, and reclaim the materials furnished and labor performed.” This is far from being an unqualified finding that the defendant cannot be put in statu quo. If the contract is set aside and the defendant is held to pay the plaintiffs for the fair value of the materials and labor furnished by the latter, and no more, we do not see why the defendant is not in a legal sense put in statu quo. This was the rule adopted at law in Bailey v. Marden, 193 Mass. 277, Brown v. Woodbury, 183 Mass. 279, Posner v. Seder, 184 Mass. 331, 333, Simmons v. Lawrence Duck Co. 133 Mass. 298, and Fitzgerald v. Allen, 128 Mass. 232. The same rule has been adopted in equity. Franklin v. Greene, 2 Allen, 519. Davis v. Peabody, 170 Mass. 397. Weeks v. Currier, 172 Mass. 53. Old Dominion Copper Co. v. Bigelow, 188 Mass. 315, 329. The case comes really within the rule laid down in Snow v. Alley, 144 Mass. 546.
But the defendant contends that the cancellation of this contract and the consequent necessity of paying upon a quantum meruit for what has been done by the plaintiffs, prevents it in another way from being put in statu quo. The result of the work done by the plaintiffs was to show that the necessary excavation was more difficult and expensive than was anticipated; and the total expense of the work has been increased accordingly. The
It is contended that the master erred in ruling that the burden of proving why the plaintiffs complained about the extra depths of excavation and abandoned the contract, rested upon the defendant. But it does not sufficiently appear that he did so rule. In his report, after stating the defendant’s contention upon this subject, he says: “ I find that the defendant did not sustain the burden of that contention, . . . but I find that the real reason for the complaint and action of the plaintiffs was the result of the errors made by ” the engineer “ in scaling said profile plans and preparing said engineer’s estimate.” The latter part of this finding, which involved the real issue, seems to have been made independently of any question of the burden of proof. The master’s language in the opening of the sentence, though it perhaps may have contained an intimation that he wrongly threw the burden upon the defendant, does not seem to us to be decisive of this. If the defendant was apprehensive that he did so rule, it might have settled the question by a request for a ruling, and if that were refused might have filed an objection and an exception founded on it. O’Brien v. Keefe, 175 Mass. 274. It has not done so, and we cannot say that the master made the ruling of which it complains.
The exceptions to the testimony of ■ the witness McKenzie ought not to be 'sustained. It was competent to show that the
We do not find that any of the other exceptions to the rulings of the master in admitting or rejecting evidence should be sustained. The language of Bigelow, C. J., in Fisher v. Plimpton, 97 Mass. 441, 443, and of the present Chief Justice in Koplan v. Boston Gas Light Co. 177 Mass. 15, 23, as to the necessity of showing a really material error in this respect, such as has been prejudicial to the excepting party, is peculiarly applicable to evidence taken before a master in a case like this.
It is not necessary to consider the other exceptions to the master’s report in detail. Most of them are disposed of by what has been said already; and none of the others can be sustained. The master rightly refused to pass upon the additional questions of fact requested by the defendant. The contract having been avoided, the plaintiffs could recover upon a quantum meruit for all that they had done; and we do not find that any objection was made to the master’s settling this upon the basis of actual cost to the plaintiffs. Neither the cost nor the value of the so called extra work was material. The case was not like the cases in. which a plaintiff who has substantially but not exactly done the work called for by the terms of a contract to put a structure upon another’s land is allowed, within the limits of the contract price,T1 to recover for the benefit thus conferred upon the latter; for there the contract is not abrogated. Gillis v. Cobe, 177 Mass. 584. Blood v. Wilson, 141 Mass. 25. Hayward v. Leonard, 7 Pick. 181.
A decree should be entered overruling all the exceptions to the master’s report, ordering that the contract between the plaintiffs and the defendant and the bond accompanying the same be delivered up and cancelled, and that the defendant pay to the plaintiffs the sum found by the master with interest from the filing of the bill; and for costs.
So ordered.