*1 LONE MOOSE MEADOWS,LLC, Counter-Claim Defendant Plaintiff, Appellant, v. Michigan corporation,
BOYNE
d/b/a
USA, INC.,
Big Sky Ski & Summer Resort,
Counter-Claimant
Defendant,
Appellee.
No. DA 16-0636.
April
Submitted on Briefs
2017.
Decided June
2017.
For David M. Griffin B. PLLP, Fleck Bozeman. Opinion
CHIEF JUSTICE McGRATHdelivered the of the Court. Meadows, appeals summary judgment Lone Moose LLC from a ruling Boyne USA, in favor of Inc. We affirm. appeal We restate the issue on as follows: properly Boyne pursue
Did the District Court allow to successive claims contract? AND FACTUAL PROCEDURAL BACKGROUND (LMM) Meadows, Boyne USA, (Boyne) Lone Moose LLC Inc. corporations operating Big Sky, Boyne are Montana. is the owner operator Big Sky housing development LMM Resort. is a at the Big Sky operations In base of Resort. entered into an agreement pay Boyne LMM where would construct a ski lift and to operate operating it. annual maintenance and expenses, $50,000 yearly depreciation expense. as well as a agreement required pay any depreciation “[LMM] stated shall not be component operating expenses dollar until the 2002-2003 ski “replacement by season” and lifts will be constructed and owned Boyne.” 2002, Boyne operation In December sent a notice of lift expenses season, $50,000 for the 2002-2003 ski which included depreciation expenses. pay, stating LMMrefused to it was not pay depreciation expenses Despite until owned the ski lift. non-payment, Boyne operating lift, electing continued the ski to treat continuing. the contract as February 2008, Boyne filed suit for breach of contract.
asserted failed to make and demanded *3 payment years past payments: under the contract for the seven due 2002-03, 2003-04, 2004-05, 2005-06, 2006-07, 2007-08,2008-09. LMM obligated contended it was not to make until Boyne granted summary judgment owned the lift. The District Court Boyne, concluding obligated pay $50,000 LMM favor of was annually beginning appealed. LMM with the 2002-03 ski season. This I).1 upheld ruling (Boyne 2012, In Court the District Court’s October judgment against LMM the District Court entered a restated for seven depreciation expenses plus costs, fees, paid LMM and interest. $634,328.19 Boyne, satisfying judgment. appeal pending, LMM December while the above was against Boyne alleging engaged wrongful
filed an action it had respect judgment.2 Boyne collection efforts with to the first asserting LMM counterclaimed for breach of contract now owed depreciation expenses 2009-10, 2010-11, for the 2011-12 ski seasons. Boyne’s process, counterclaim also included claims for abuse of prosecution, punitive damages, third-party malicious as well as a against Dolan, claim LMM’sowner James Sr. The settled these voluntarily wrongful claims. moved to dismiss the collection only remaining claim and the District Court dismissed it. The issue Boyne’s Boyne breach of contract counterclaim. moved for summary judgment. hearing In October the District Court held a on
summary judgment any motion. it had not made payments, but that this breach of contract claim was barred preclusion, eliminating Boyne’s under the doctrine of claim thus judgment. granted Boyne’s entitlement to a new The District Court summary judgment motion. The District Court found that the second suit arose from facts not existence at the time of the first suit and Boyne had the to maintain successive actions for each new Boyne breach of the contract as arose. was not to sue for payments though material, future even LMM’s breach was and the pay depreciation District Court held LMM’s refusal to costs did not anticipatory repudiation agreement. amount to of the terms of the On 7,2015, judgment October the District Court entered favor of USA, Meadows, LLC, Inc. v. Lone Moose 2010 MT P.3d 1269. Restvedt, server, original complaint Tyler process included as a defendant. voluntarily dismissed him from the lawsuit.
510 $150,000, plus appeals. fees and interest.
STANDARD OF REVIEW
grant
summary
We review de novo a district court's
or denial of
¶7
judgment, applying the same criteria of M. R. Civ. P. 56 as a district
Pilgeram
Mortg. Funding, Inc.,
354, 9,
MT
court.
v. GreenPoint
2013
¶
373 Mont.
DISCUSSION properly Boyne pursue Did the District Court allow claims contract? of preclusion Boyne’s attempt LMM asserts claim barred to collect depreciation expense payments for three of and that the District determining preclusion in Court erred that claim did not bar claims this matter. contends their initial breach of the required contract was so severe that was to sue for all theory under the contract under a anticipatory repudiation. (“res preclusion judicata”) relitigation Claim bars the of a claim party opportunity litigate previous proceeding. had an Co., 184, 18, 78, 285 MT
Brilz v. Metro Gen. Ins.
366 Mont.
P.3d
¶
relitigated
judicata
long
An
494.
issue cannot be
under res
so
as the
parties
privies
same,
subject
present
or their
are the
matter of the
past
same,
actions is the
the issues are the same and relate to the
subject matter,
capacities
same
are the same to the
subject
them,
judgment
matter and issues between
and a final
on the
State,
MT
merits has been entered. Denturist Ass’n Mont. v.
119, 11,
383 Mont.
511
elementary
We are not convinced. “It is an
rule of law that where
claims, payable
times,
several
at different
arise out of the same
contract,
may
brought
liability
Clark,
suit
be
as each
accrues.” Cohen v.
(1911).
151, 155, 119 775,
44 Mont.
P.
777
The issues are not the same.
years Each law suit addresses different
the contract.
Significantly,
expressly grants contracting
Montana law
to maintain successive actions on the same contract.
Court,
State ex rel. Towne v. Second Judicial Dist.
Mont.
(1942);
Wolff,
(1962);
P.2d 161
Green v.
division of their
as well as care and
of their minor
Towne,
3-4,
child.
Mont. at
on the contract.
Mont. at
P.2d at 163-64
argument
obligation
pay
upon
the father’s
that “his
... is not based
action.”)
a contract but the decree of the court
the divorce
Green,
415,
a landlord leased a ranch to a tenant. 140 Mont. at
four-year contract,
treat the contract as breached and sue for
split
up
year’s
tenant could not then
the contract
and sue for each
damages.
rejected
argument, again finding
This Court
predecessor
§28-2-1501, MCA,
controlling.4
identical
parties’
parts.
contract “contained several divisible
It ran for four
year
separate phase
and each
... was a
to be
Green,
separately performed
and settled.”
never terminated and to sue for all litigation. under the contract the first
CONCLUSION regarding The District Court’s conclusions of law this contract 4 R.C.M.1947 93-8704. *7 argument
were correct. LMM’s fails to establish that claims by preclusion. were barred considerations of claim Because we have application 28-2-1501, MCA, dispositive determined that the of is of § case, arguments appeal. this we will not address LMM’s other on Further, ruling by under the terms of the contract and the this Court Boyne 1, Boyne attorney’s is entitled to reasonable fees it incurred appeal. on We remand to District Court for the determination of attorney’s fees. Affirmed. SHEA, McKINNON,
JUSTICES WHEAT and SANDEFUR concur. MCKINNON, concurring.
JUSTICE agree analysis regarding I with the Court’s decision and 28-2- § 1501, MCA, application proceedings. However, I and its to these feel compelled appears obvious, to add what to be but nonetheless overlooked; may not, breaching party, as the choose the remedy anticipatory gives wronged party, An for its breach. breach proceedings Boyne, in these to either rescind the repudiation breach, bring treat the as a or to suit after the time for performance passed. Anticipatory repudiation allows, has but does not require, wronged party a breach of contract action before the opposing party’s performance time the is due. STC, City Billings, 364, 370-71, We held Inc. v. of (1975), legal anticipatory 543 P.3d effect ofan 472(1), pp. 653-55, by
is described 17A C.J.S. Contracts this language: party by executory repudiates
Where a bound an contract or obligation performance renounces his before the time for promisee according great weight authority, option has to the an ended, performance to treat the contract as as far as further is concerned, damages and to maintain an action at once for by anticipatory breach, repudiation, occasioned such or renunciation, specific even the absence from the contract of a provision authorizing the maintenance of an action or the declaring of a forfeiture. Accordingly, would, analysis I in addition to the Court’s of 28-2-
1501, MCA, definitively reject attempt remedy LMM’s to choose the Boyne may anticipatory remedy elect for LMM’s breach. The anticipatory option wronged party, breach is at the which is not only precedent, consistent with our own but the universal rule and weight authority jurisdictions. from other reasons, I For these concur.
