41 Colo. 253 | Colo. | 1907
delivered the opinion of the court:
This is an action to recover a balance due under a written contract in accordance with whose plans and specifications plaintiff agreed to build for defendant part of an irrigating ditch. The complaint alleged that plaintiff had fully complied with all the terms and conditions of the contract which he was required to perform, and done all the work under it before action was brought.
Defendant by its answer admitted, making the contract, but denied that plaintiff had performed the covenants therein to be performed by him, and alleged that the banks of the ditch were not sloped as required by the written agreement, that the ditch was not on an even grade as indicated by the grade stakes, and it had not been completed. There was a trial to the court without a jury, which resulted in findings in favor of the defendant, followed by a judgment dismissing the action.
Numerous errors are assigned by the plaintiff, only one of which is argued by his counsel, which is that under the evidence judgment should have gone
The plaintiff sued upon a. special contract which is set out in full in the complaint. He alleged that he had fully complied with all its terms and conditions, and that all work under it was fully completed. The defendant, affirmatively pleaded the particulars in which it claimed the contract had not been performed and that the work had not been finished.
In McGonigle v. Klein, 6 Colo. App. 306, it was held that where a contract is in writing and entire, in order that the plaintiff may recover upon it he must show either performance or that the contract has been rescinded, or its performance rendered impossible as the result of defendant’s wrong. This case was referred to with approval in Cochran v. Balfe, 12 Colo. App. 75, where Wilson, J., says that the same rule is declared by this court in Cody v. Reynaud, 1 Colo. 272, and Walling v. Warren, 2 Colo. 434.
In Rockwell Stock Co. v. Castroni, 6 Colo. App. 521, at page 533, the court, by Bissell, J., said: “If the plaintiff declares on a special contract, and undertakes to prove it, he may not at the same time offer proof of the value of his services and recover according as the jury may conclude with reference to the matter.”
By the rules of the common law, where a party to a written contract sued to recover compensation
But the authorities seem to hold that for such substantial performance an action cannot be maintained on the special contract, but must be on a quantum meruit, and feuch was the holding in the Roclnvell case, supra. See, also, 9 Cyc. 687, and cases cited. In Robinson C. M. Co. v. Johnson, 13 Colo 258, 264, the court said: “As a rule, where there is an express contract, parties cannot abandon it and resort to an implied one.” And in Owl Canon Gypsum Co. v. Ferguson, 2 Colo. App. 219, the opinion at page 231 says: “When one seeks to cover for the performance of a contract, he must see that he has performed the contract which is the basis of his action.”
Applying the foregoing principles to the facts of this case, it is.clear that the plaintiff was not entitled to recover. He relied upon and proved a special contract, but signally failed to show full performance, as alleged. The grade of the ditch for over one-ninth of its length was not in accordance with its • specifications, and the slope of the upper
Charles v. Hallack Lumber Co., 22 Colo. 283, is cited by plaintiff in support of the point that under a complaint declaring on a special contract a recovery may be had for the reasonable value of the services performed. No such doctrine is announced in that case. Indeed, Justice Goddard, who wrote the opinion, expressly left undetermined whether in that action if defendant had elected to stand upon his technical rights under the contract, he might not successfully have resisted payment of the balance of the contract price until a -strict performance of all the conditions of the contract had been made by the plaintiff. It was not necessary in that case to pass upon the question, because the defendant elected to avail himself of the option given him by the contract to make good the omission and defects of the plaintiff and claim the cost of doing so as a set-off or counter-claim against the amount, if any, found due plaintiff upon the contract.
We do not deem it a harsh rule to restrict plaintiff in his evidence to the cause of action set up in his complaint, particularly where the defendant objects to the variance between the allegations and proof, as was the case here. It works no injustice
The judgment is affirmed. Affirmed.