33 P. 797 | Cal. | 1893
Action to enforce a lien upon a house owned by defendant Lasar for labor done upon an addition to said house for the defendant Sonneckson, who, as original contractor, constructed said addition. The judgment was in favor of the plaintiff, but the court granted a new trial, and this appeal is from the order granting a new trial.
Whether or not the plaintiff had filed his claim of lien within thirty days after the completion of the additional structure was the principal question at the trial, and is the only question presented on this appeal; it being admitted that the new trial was granted on the ground of insufficiency of the evidence to justify the finding that plaintiff’s claim of lien was filed within the time required by section 1187 of the Code of Civil Procedure, namely, within thirty days after the completion of the addition which the original contractor agreed to construct. The claim of lien was filed August 29, 1890, and I think a decided preponderance of the evidence is to the effect that the addition was completed on July 26, 1890. The addition to the house was a cellar under it. By the original contract, which was in writing, the defendant Sonneckson agreed to make the necessary excavation for the cellar, and to construct walls of concrete seven feet and six inches in height and steps to the street for $365. That all this work was done and accepted by the owner as completed on or before July 26, 1890, there is no controversy; but the .evidence shows that the placing of a door frame in the cellar
We concur: Searls, C.; Belcher, C.
For the reasons given in the foregoing opinion the order granting a new trial is affirmed.