Opinion
—These appeals follow the denial of motions to compel arbitration in a multiparty action arising out of the purchase of a newly built home. The trial court denied the seller parties’ motion to compel arbitration of the buyer’s causes of action for nondisclosure because there was a possibility of conflicting rulings if these claims were ordered to arbitration and the nonarbitrable causes of action by the buyer against the developer parties proceeded to trial. The court later denied the seller parties’ motions to compel their agents to arbitrate the agents’ cross-claims for indemnification on the ground the agents were not bound to submit those claims to arbitration by the arbitration clause in the purchase agreement. We affirm.
FACTUAL AND PROCEDURAL BACKGROUND
1. The Parties and Principal Actors
Richard Hume is a trustee of the Hancock Park Real Estate Trust (Hancock Park Trust); Nicolas Cage is the trust’s beneficiary.
Barbara Trent Lindemann is the trustee of the Bradford Lindsley Schlei Trust II (Schlei Trust); Bradley Lindsley Schlei is that trust’s principal beneficiary. The Schlei Trust purchased the home from the Hancock Park Trust in May 2003.
2. The Sale of the Home by the Hancock Park Trust to the Schlei Trust
a. Cage moves into the home but decides to sell it six months later
In February 2002 Nazarian, Chalke and a company retained by Levin to analyze the home’s plans conducted a preclosing walk-through of the property. The following day Chalke engaged an inspection service to perform a prepurchase physical inspection. Before escrow closed on February 22, 2002, The Lee Group agreed to provide, in addition to a limited construction warranty,
Soon after Cage moved into the Ocean Front Walk home, he encountered water intrusion, flooding and other problems. Cage informed The Lee Group, but they were unable to fix the problems. In mid-August 2002 Hume, at Cage’s direction, signed a listing agreement with Chalke to sell the home.
In mid-December 2002 Chalke received an offer from Hedy and Sarny Kamienowicz to purchase the home. Levin accepted the offer on behalf of the Hancock Park Trust. Also during December 2002 Nazarian received a photograph from a nearby property owner depicting exterior site flooding at the home. Chalke then provided the Kamienowiczs’ real estate agent with a disclosure statement noting, “There is a problem with the drainage system that is currently being addressed by the Lee Group (developer)”; a box was also checked indicating the seller was aware of “[fflooding, drainage or grading problems.”
During escrow the Kamienowiczs’ agent received a property inspection report noting sandbags had been placed along portions of the property and the finished floor of the house was below some areas of the exterior grade and only a little higher in other areas. The report recommended “[a] qualified drainage person should be contacted for further evaluation of the exterior drainage.” The report was provided to Nazarian, who engaged civil engineer Robert Anderson to assess the issue. After the Kamienowiczs’ agent spoke to Anderson, who explained there was no “quick fix” because any viable solution would require a storm drain line or storm retention system on city property, the Kamienowiczs disapproved the condition of the property and terminated escrow.
On February 14, 2003 Nazarian received a report from Anderson’s firm identifying several “remedial measures” to improve site drainage conditions, including installation of a larger sump pump, but noting they were “not a ‘fix’ and [would] not mitigate the site drainage problem.” The report further stated, “[A]ny owner will need to accept the risk associated with the drainage at the site. The site will need to experience large rainfalls to determine if the remedial measures work. . . . However, it appears that should these options be implemented, that the site should perform reasonably] except under the more extreme conditions. Under that scenario, we would expect that the entire region would be subjected to widespread flooding.”
In response to Anderson’s report, Nazarian sent Anderson a letter stating he had been at the home over the preceding several days during which a considerable amount of rain had fallen and there had been no “standing water accumulation or any related water problems.” Nazarian commented on the need for, and feasibility of, the remedial measures proposed by Anderson, concluding, “In my opinion, I would not include or refer to [items Nos. 3, 5, and 6] as part of a ‘minimal acceptable level of repair’ but rather have them
c. The sale of the home to the Schlei Trust; the engineers’ investigations
In May 2003 Lindemann made an offer to purchase the home, which Levin accepted. The purchase agreement signed by Levin as trustee of the Hancock Park Trust included an arbitration clause, paragraph 17(B)(1), which provides in part, “Buyer and Seller agree that any dispute or claim in Law or equity arising between them out of this Agreement or any resulting transaction, which is not settled through mediation, shall be decided by neutral, binding arbitration . . . .”
During escrow Chalke provided Lindemann with a disclosure statement, signed by Hume, describing as the only significant defect, “Wood floor in basement needs to be replaced in places.” With respect to flooding, drainage or grading problems, the disclosure statement noted, “There was a drainage problem at the front of the house at the boardwalk area. The problem was diagnosed by a hydrologist and subsequently remedied. No new problem has been discovered.” The report prepared by Anderson was not provided to Lindemann, nor was the existence and termination of the Kamienowicz escrow disclosed.
Escrow closed on May 23, 2003, The Lee Group’s construction warranties were transferred to the Schlei Trust and Schlei moved in. About a week later the neighbor in the adjacent home, also built by The Lee Group, told Schlei a larger sump pump might be required to drain surface water at the homes.
Lindemann’s real estate agent asked Chalke whether the drainage work mentioned in the disclosure statement would prevent future flooding. In response, Nazarian sent Schlei a letter stating, “[Wjhile we did have drainage problems, which flooded the side and front yard, I looked at that problem with The Lee Group, a consulting architect and finally a civil engineer/hydrologist. After careful study a plan recommended by the hydrologist was [ejffected by The Lee Group to prevent that situation from recurring.”
d. The complaints
In May 2009 Lindemann filed a complaint against The Lee Group and related parties (collectively, The Lee Group) asserting causes of action including fraudulent concealment, negligent nondisclosure and breach of express warranty. In June 2009 Lindemann filed a first amended complaint adding additional causes of action and naming as Doe defendants the Hancock Park defendants. In August 2009 Lindemann filed a second amended complaint. During October and November 2009 the Hancock Park defendants and The Lee Group filed cross-complaints against each other for indemnity.
On December 10, 2009, following successful demurrers to the second amended complaint by both the Hancock Park defendants and The Lee Group, Lindemann filed a third amended complaint, the operative pleading. It asserts causes of action against The Lee Group for (1) strict liability (construction defect); (2) fraudulent concealment, suppression of fact, nondisclosure; (3) negligent nondisclosure; (4) negligence per se; (5) negligence; and (6) breach of express warranties. It also asserts causes of action against the Hancock Park defendants for (1) fraudulent concealment, suppression, nondisclosure and (2) negligent nondisclosure predicated on the failure to disclose information pertaining to the drainage problem, including the property inspection report prepared in connection with the Kamienowicz escrow, the subsequent report prepared by Anderson and the existence and termination of the Kamienowicz escrow.
3. The Denial of the Hancock Park Defendants’ Motion to Compel Lindemann to Arbitrate
In January 2010 the Hancock Park defendants moved to compel Lindemann to arbitrate her nondisclosure causes of action against them pursuant to the arbitration clause in the purchase agreement. They argued Lindemann’s claims were only tangentially related to her construction defect causes of action against The Lee Group and thus there was little risk separate proceedings would result in conflicting rulings: “[Lindemann’s] claims against the
On June 9, 2010 the trial court denied the motion on the ground there was a possibility of conflicting rulings on common issues of law and fact if the nondisclosure causes of action against the Hancock Park defendants were ordered to arbitration and the litigation against The Lee Group proceeded in superior court. (Code Civ. Proc., § 1281.2, subd. (c).)
The Hancock Park defendants appeal from that order. Lindemann has cross-appealed, asserting the order denying arbitration may be affirmed on the alternative ground the Hancock Park defendants waived their right to compel arbitration by participating in the litigation for several months before filing their motion.
4. The Denial of the Hancock Park Defendants’ Motions to Compel Levin and Nazarian to Arbitrate
In late June 2010, after the trial court had denied the Hancock Park defendants’ motion to compel arbitration, Lindemann amended her third amended complaint by substituting Nazarian and Nazarian doing business as The Nickel Company (collectively Nazarian), Samuel Levin and related
On January 7, 2011, before Levin had filed his cross-complaint for indemnification against the Hancock Park defendants, the Hancock Park defendants moved to compel arbitration of Nazarian’s indemnification claims. They argued Nazarian is bound by the arbitration clause in the purchase agreement even though he did not sign it because he was acting as the Hancock Park defendants’ agent when he allegedly failed to make disclosures required pursuant to the purchase agreement. On March 3, 2011, after Levin had filed his cross-complaint, the Hancock Park defendants moved to compel arbitration of those claims, contending Levin was bound by the arbitration clause in the purchase agreement because he had signed it and was acting as their agent.
On April 11, 2011 the trial court denied both motions, finding, “[T]he language of the arbitration provision makes clear that it does not apply to the claims for indemnification. The actual provision provides for arbitration between ‘Buyer and Seller’ and claims ‘arising between them.’ The claims at issue of this motion are not between buyer and seller. They are between the various sellers.”
The Hancock Park defendants have appealed this order, as well. The trial court stayed all proceedings except certain construction defect site inspections during the pendency of the appeals.
DISCUSSION
The Order Denying the Motion to Compel Lindemann to Arbitrate
1. Governing Law
Section 1281.2 generally requires the trial court to order arbitration of a controversy “[o]n petition of a party to an arbitration agreement alleging the existence of a written agreement to arbitrate a controversy and that a party thereto refuses to arbitrate such controversy ... if it determines that an agreement to arbitrate the controversy exists.” Arbitration of a controversy
2. Standard of Review
An order denying a petition to compel arbitration under section 1281.2, subdivision (c), is generally reviewed for abuse of discretion. (Birl v. Heritage Care, LLC (2009)
3. The Trial Court Did Not Err in Denying the Hancock Park Defendants’ Motion to Compel Lindemann to Arbitrate
The Hancock Park defendants contend section 1281.2, subdivision (c), is inapplicable to their motion to compel arbitration of Lindemann’s nondisclosure claims against them because those causes of action and the construction defect causes of action against The Lee Group do not arise out of the same
As the Hancock Park defendants emphasize, Lindemann’s claims against The Lee Group stem from the allegedly negligent design and construction of the home, which occurred before the Hancock Park Trust purchased the property, while the nondisclosure causes of action against them arise out of their alleged failure to make required material disclosures in connection with the resale of the home three years later. Thus, they are correct the claims do not arise from the same transaction. Their further contention that the causes of action do not arise out of a series of related transactions, however, requires an unduly cramped view of section 1281.2, subdivision (c), that we reject.
The gravamen of Lindemann’s action is that she bought a newly constructed home with multiple construction defects and the Hancock Park defendants, although not the home’s developer, knew of at least one alleged defect—inadequate site drainage leading to flooding—but failed to disclose it as they had to the Kamienowiczs during escrow with them several months earlier. The Hancock Park Trust was not simply an intervening, unsophisticated buyer who had purchased the home from The Lee Group with no involvement in the construction process or knowledge of the alleged drainage defect. The Hancock Park Trust bought the home while it was still under construction. Before escrow closed, the Hancock Park defendants’ agents (including a general contractor, Nazarian), or companies engaged by them, analyzed the home’s plans, had a prepurchase physical inspection completed and were able to obtain from The Lee Group an additional 10-year warranty to remedy and repair damage resulting from water infiltration and flooding resulting from the improper installation of certain doors.
According to Lindemann’s complaint, the Hancock Park defendants’ role in discovering potential construction defects continued through the cancelled escrow with the Kamienowiczs. During that time Nazarian challenged Anderson’s conclusion as to what items should be included as remedial measures to address the site drainage problem. While any actual construction defects originated with the design of the home several years earlier, the transactions by which (a) the Hancock Park defendants first acquired the home from its developer, The Lee Group, following extensive discussions of possible water intrusion problems; (b) then unsuccessfully attempted to sell the property to the Kamienowiczs, an effort that foundered following disclosure of the drainage issues; and (c) finally resold the home to the Schlei Trust without making the same disclosures as had been made to the Kamienowiczs, were without question “related.” (See Birl v. Heritage Care, LLC, supra,
The Hancock Park defendants’ additional contention there is no risk of inconsistent rulings if the causes of action against them proceed to arbitration and the causes of action against The Lee Group are tried in superior court is similarly without merit. Contrary to the trial court’s finding, they contend the existence of a construction defect is not a threshold question in the action against them because an arbitrator could determine the drainage system at the home was neither defectively designed nor constructed, but the Hancock Park defendants nevertheless breached a duty to disclose the risk of flooding with severe rainstorms because of essentially inherent site conditions. In support, they note the Anderson report indicates the drainage problem at the home is part of a larger issue in the general area and not associated with a specific defect at the home. The Hancock Park defendants also contend the arbitrator could alternatively find the drainage system was defectively designed and/or constructed, but they had adequately disclosed the problems.
To be sure, whether or not the drainage system was defectively designed or constructed may not ultimately resolve whether the Hancock Park defendants failed to disclose a material condition of the property. The issue to be addressed under section 1281.2, subdivision (c), however, is not whether inconsistent rulings are inevitable but whether they are possible if arbitration is ordered. Here, that the arbitrator could find a design or construction defect existed as a predicate to holding the Hancock Park defendants liable for failing to disclose a material condition of the property and the finder of fact in the superior court action could reach a contrary conclusion is sufficient to satisfy that requirement. Indeed, the Hancock Park defendants and The Lee Group have filed cross-complaints for indemnification against each other, further increasing the risk of inconsistent rulings.
Finally, the Hancock Park defendants contend, even if section 1281.2, subdivision (c), is applicable, the trial court should have ordered arbitration and then stayed it pending a judicial determination whether the drainage
Although the Hancock Park defendants attempt to portray the issues in this case as discrete and segregable, we cannot say the trial court’s contrary conclusion exceeded the bounds of reason. (See Shamblin v. Brattain (1988)
The Order Denying the Motion to Compel Levin and Nazarian to Arbitrate
California law recognizes “ ‘a strong public policy in favor of arbitration[].’ ” (Madden v. Kaiser Foundation Hospitals (1976)
“Mutual assent is required for there to be an enforceable agreement to arbitrate disputes. ‘ “[Arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit.” ’ ” (Burch v. Premier Homes, LLC (2011)
As discussed, the arbitration clause in the purchase agreement between the Hancock Park Trust and the Schlei Trust broadly applies to all disputes or claims between the two trusts as seller and buyer arising out of the transaction. An additional provision permits the scope of the arbitration provision to be expanded to include disputes between either of the two trusts and the real estate brokers who assisted in the transaction. The Hancock Park defendants, on the one hand, and Lindemann, Levin and Nazarian, on the other hand, vigorously contest whether nonsignatories Levin
We need not resolve that dispute. Even if Levin and Nazarian are bound by the arbitration agreement and could be compelled to arbitrate certain disputes arising from the sale of the Ocean Front Walk property (for example, Lindemann’s claims against them for nondisclosure), their claims for indemnity from the Hancock Park defendants are outside the scope of the arbitration provision, which covers only disputes between the seller and the buyer, not internecine disputes among members of the seller’s team of advisors.
Westra v. Marcus & Millichap Real Estate Investment Brokerage Co., Inc., supra,
Although like nonsignatory broker/agent Marcus & Millichap in the Westra case Levin and Nazarian had a preexisting relationship with the Hancock Park defendants, nothing in the purchase agreement for the Ocean Front Walk property contemplates that disputes between one of the principals to the transaction and its own business advisors are subject to arbitration, whether or not those claims somehow relate to, or arise out of, the Schlei Trust’s acquisition of the home. The Hancock Park defendants could have included such a right in the purchase agreement (as they did for their real estate agent) or bargained for it when engaging Levin and Nazarian as business advisors, but apparently either chose not to or were unable to obtain their agreement. (Cf. JSM Tuscany, LLC v. Superior Court, supra,
DISPOSITION
The orders are affirmed. Lindemann is to recover her costs on appeal.
Woods, J., and Zelon, J., concurred.
Notes
The factual background is taken primarily from the third amended complaint and attached exhibits. The parties do not dispute the truth of the allegations for the purpose of resolving whether the trial court properly denied the motions to compel arbitration.
We refer to Cage and Hume collectively as the Hancock Park defendants.
The trust agreement includes a clause indemnifying the trustee for any “loss, damage, costs, charges, judgments, attorney’s fees or other sums which the Trustee may have paid out, suffered or incurred . . . .” It does not include a clause requiring the trustee and the beneficiary to arbitrate any disputes between them.
The limited construction warranty generally provides one- to two-year coverage for the home’s structural components, including the roof, walls, floors, foundation and ceilings.
The arbitration clause separately provides, in paragraph 17(B)(3), “BROKERS: Buyer and Seller agree to mediate and arbitrate disputes or claims involving either or both Brokers . . . provided either or both Brokers shall have agreed to such mediation or arbitration prior to, or within a reasonable time after, the dispute or claim is presented to Brokers.”
Statutory references are to the Code of Civil Procedure.
No cross-appeal is needed for Lindemann to make this argument. (See § 906.) In light of our decision affirming the trial court’s order denying the motion to compel arbitration of Lindemann’s claims, we need not address the issue of waiver.
In January 2011 the third amended complaint was again amended, this time to assert against Levin and Nazarian only the causes of action asserted against the Hancock Park defendants.
Lindemann alleges the home has a host of construction defects in addition to the site drainage problem that is the focus of her nondisclosure claim against the Hancock Park defendants. For example, she alleges the foundation was not constructed in accordance with the approved plans, the Los Angeles Building Code and convention for posttensioned concrete construction and likely will not provide adequate support for the home.
Levin signed the purchase agreement and initialed the arbitration clause as trustee of the Hancock Park Trust. He asserts, and the Hancock Park defendants dispute, that act does not bind him in his individual capacity. (See Benasra v. Marciano (2001)
We review the scope of an arbitration provision de novo when, as here, that interpretation does not depend on conflicting extrinsic evidence. (RN Solution, Inc. v. Catholic Healthcare West (2008)
Although section 1281.2, subdivision (c), was raised as a ground for denying the motion to compel Levin and Nazarian to arbitrate, the trial court did not rule on that issue. Lindemann’s contrary assertion is not supported by any citation to the record, and our own review of the record on appeal indicates the court discussed section 1281.2, subdivision (c), but did not base its decision on that provision.
