delivered the Opinion of the Court.
The plaintiff, Lincoln/Lewis & Clаrk County Sewer District, appeals the judgment of the District Court of the First Judicial District, Lewis & Clark County, finding that plaintiff was not entitled to a preliminary condemnation order for utility easements in defendants’ propertiеs. We affirm.
The plaintiff and appellant, Lincoln/Lewis & Clark County Sewer District (hereinafter “District”) was incorporated in 1980 following a vote in which approximately seventy percent of those voting approved the formation of the District. The Distriсt was formed for the purpose of designing, constructing and maintaining a new central sewer system for the unincorporated town of Lincoln, Montana. Title 7, Chapter 13, parts 22 and 23, MCA, governs the District.
The District instituted this action to acquire easement in defendants’ properties in order to construct and maintain septic tanks and service lines running from the tanks to collection mains which have already been installed. Easements from over 220 of the landowners have been acquired through negotiations and agreements. This eminent domain action involves approximately twenty-five parcels of propеrty within the District whose owners have refused to grant easements.
Two prior actions have been maintained regarding this District. In Lewis & Clark County cause No. 48930, District Judge Gordon Bennett decided in favor of the District on the validity of the creation and the existence of the District. In Lewis & Clark County cause No. 49137, District Judge Henry Loble determined that the project was in the public interest, that there was a public need and neсessity for land for the purpose of constructing, laying and maintaining *238 the collection lines, and that the District Court was entitled to a preliminary condemnation order. No appeal was taken by any defendants in either action.
The current sewage disposal needs of the community are met by the use of individually owned and constructed drainage systems. The most common type is a septic tank in which solid wastes are separated from liquid wastes with the solid wastes remaining in the tank. The liquid wastes are then piped into underground drainfields and treated by a “leaching” process where they pass through the soil surrounding the drain field. The solid wastes remain in the tank and must be removed from time to time depending on the amount of use the system receives.
County health regulations require at least four feet of unsaturated soil belоw the drainfield for the sewage to receive the necessary treatment before reaching the groundwater. The drainfield is usually one to three feet below the surface. These regulations arе based on generally recognized nation-wide standards designed to prevent outbreaks of disease and protect groundwater quality. The groundwater elevation in Lincoln generally ranges from two tо six feet or possible more, depending on the time of year a measurement is made. The average is about four feet from the surface. The evidence presented at trial did not show that the dеfendants’ septic systems were defective or that they caused any groundwater contamination, seepage or other present problems. There was no evidence of any foreseеable risk of contamination posed by the defendants’ systems.
The issues presented for review are:
(1) What is the scope of authority of a trial court’s review in a condemnation action and did the trial court exceed the authority?
(2) What is thе burden of proof in a condemnation action and who carries that burden?
(3) Was there necessity for utility easements in defendants’ properties under these circumstances?
Courts generally do not have the power to determine what public improvements shall be constructed, where they shall be located, and when the power of eminent domain shall be exercised. These are exclusively within the power of the legislature. Nichols on Eminent Domain, section 4.11(1). Courts are also without power to interfere with a board’s discretionary action when exercising eminent domain power on the sоle basis that the action shows poor judgment or a lack of wisdom.
State Highway Commission v. Crossen-Nissen Co.
(1965),
Where there is an abuse of discretion, or arbitrary, capricious, fraudulent or bad faith action in the exercise of eminent domain power, however, there is a call for the protection of the courts. Nichols on Eminent Domain, section 4.11(2) and
Crossen-Nissen,
Prior cases, along with the statutes mentioned, clearly reflect that the trial judge has the power to determine necessity and make findings оn whether the public interest requires the taking in an eminent domain proceeding.
State Highway Commission v. Yost Farm Company
(1963),
The trial court made two findings that are outside its scope of authority. Those findings are that “[t]here is no showing of need for a $2.6 Million Dollar sewer system in Lincoln” and “[t]hat the public interest does not require an elaborate sewer system as proposed.” The two prior District Court actions had already made these determinations. In addition, the issuеs before this Court involved only the necessity of taking the particular property of these few defendants for septic tanks and connection lines. Since these two findings exceeded the trial court’s authority they are set aside.
The burden of proof in a condemnation action “rests upon the shoulders of one seeking to show that the taking has been excessive or arbitrary.”
Crossen-Nissen,
The condemnor, however, must initially produce sufficient evidence to establish facts indicating the taking is necessary. This is illustrated in
Yost,
Although at first glance these cases appear inconsistent with the cases cited above, they are reconcilable.
DeWolf
and
Yost
are both concerned with the condemnor’s production of evidence at the outset of a proceeding. Once sufficient evidence to establish necessity has been introduced, the burden shifts to the one who opposes the taking to show by clear and convincing proof that the condemnor’s action was excessive or arbitrary. Fоr example, where the location of an improvement is chosen based on the expertise and detailed consideration of the condemnor and the evidence is introduced at the hearing, the choice may be overturned if the opposing party shows the condemnor failed to consider least private injury between routes equal in terms of public good.
Bokma,
In the present casе, the trial court found that the District, the condemnor, had not shown necessity for the taking of defendants’ properties because they failed to demonstrate a reasonable present need оr even need in the reasonably foreseeable future to connect defendants to the sewer. This is similar to DeWolf, in that the con *241 demnor has not carried the burden of introducing sufficient evidence of necessity. The second part of the inquiry, whether the defendant can show the taking, even though necessary, is arbitrary or excessive, is not reached in the case at bar.
“The requirement that the condemnor must show necеssity for the property taken does not mean that it must be indispensable to the proposed project. Rather the word ‘necessary’ . . . means that the particular property taken be reаsonably requisite and proper for the accomplishment of the purpose for which it is sought under the peculiar circumstances of each case.”
Crossen-Nissen,
We therefore affirm the order of the trial court.
