No. 395 | D. Mont. | Mar 31, 1916

BOURQUIN, District Judge.

Action by a builder of a bridge against the contractor’s surety. Defendants’ objection to any evidence “for the purpose of the record, * * * simply a formal matter,” no defect in the complaint being pointed out, was overruled as. of a class disfavored, in that it tends to defeat justice rather than to promote it, the court stating if the complaint was defective, amendment would be allowed. If necessary, amendment is deemed made to conform to proof.

The complaint is that the contractor, the Coast Bridge Company, failed to perform its contract, in that it did not drive the center pier piles as required by. specifications, and because of which the pier undermined and with the bridge fell. The answer is of denials only. The structure was a highway bridge of 18-foot floor width and two1 220-foot spans, supported by a center pier. It was at Rexford, Mont., and over the Kootenai river, a swift mountain stream over 400 feet wide, the water stages varying in depth from 12 to 30 feet.

The contractor agreed to. provide “all material, labor and other things of every description” to build the bridge “in good workmanlike and substantial manner * * * so as to make it a perfect bridge according to the plans and specifications” furnished by it. These plans were indefinite in the matter of the depth of the center pier, extent of concrete, and whether or not piles would be used therein, the contractor leaving “that open to be determined after” excavation. *470The specifications provided that all piers would “be sunk to the elevation called for on the plans,” and “piles shall be driven inside if so ordered by the engineer”; that piles would be round, not less than 12 inches at the larger end and 9 at the smaller, and of the “length called for on the plans,” though the contract, of which the specifications were a part, stated the length “shall be specified and determined by the county or its representative”; and that the piles would be shod and ringed if necessary, and driven with a hammer of not less than 2,000 pounds, and under the last blow falling 20 feet, the penetration not to exceed one-half inch.

References to “the engineer” are ambiguous, save in one instance to “the local engineer.” If construed to import the builder’s engineer (though these were the contractor’s specifications), there was no stipulation obligating the builder to secure an engineer. It was optional, and the builder secured none. For the center pier the contractor excavated about 8y2 feet deep in sand and gravel. Its superintendent testified the bottom was then tested with an inch pipe and a maul and by four piles 8 inches square, which were driven until destroyed, “probably 4 feet” deep. He ordered like piles 22 feet long, and 62 of them were driven, it would seem, to depths varying from 3 feet S inches to. 3 feet 11 inches.

When the driving commenced the water was about 18 feet deep., and gradually rose, each pile being driven until its top was practically at water level. They were not ringed nor shod, and broomed little, if any. Around and upon them the concrete center pier was constructed. About six months later the water undermined the pier, so that it overturned and the bridge fell. A diver found that about 16 piles at the downstream end of the pier were intact, the others having been sheared off. Without further detailing the evidencé and conflicts in facts and opinions, the finding is that the piles were not driven in accordance with the contract and to refusal, and that because thereof the pier and bridge fell.

[1] It is probable as urged by defendant that these smaller piles would not endure driving strictly as specified. But for all that appears the builder did not order them, and their use was the contractor’s choice. Even if maintainable that the builder had knowledge and acquiesced, in that one Of its board of commissioners at least saw the piles after they were driven, it had no knowledge that they were not driven as nearly as possible in accordance with specifications and to refusal. And this view of the piles was from the falsework, nothing appearing that it sufficed to and did disclose smaller piles had been driven. Furthermore, the board member was in substance told by the contractor’s superintendent that the piles had been driven 7 feet and to refusal, and so satisfied. Since the undermining refilled and its extent is not definitely known, it is-urged that it may have been so great that in any event the result would have been the same. The failure to drive the piles to refusal is a sufficient and reasonable cause for the destruction of the bridge. It is clear the undermining was so great that these piles could not resist it. That it might also have been so great that these piles, driven to whatever unknown depth, would *471have been refusal could not have resisted it is mere conjecture and not permissible.

Curiously enough, defendant introduced evidence, and contends that the excavation for the pier should have been deeper and no piles used; that the damage is due to defective plans and poor engineering. To concede it would not seem to- better defendant’s case, for the contractor was responsible for both plans and engineering. And if necessary, the complaint would be deemed amended to conform to this contention and proof, involving no change in the cause of action, hut only in the particulars thereof.

[2—4 ] The contract provided it would not take effect until Congress authorized the bridge, and the War Department approved the plans and specifications. Congress authorized the bridge (see 37 Stat. 71) to be built in accordance with Act March 23, 1906, c. 1130, 34 Stat. 84 (Comp. St. 1913, §§ 9961-9968). This latter act provides that a bridge over navigable waters authorized by Congress, shall not be built until the plans and specifications have been approved by the Secretary of War and the Chief of Engineers. Violation of the act is a misdemeanor punishable by fines, and the bridge may be removed.

For the purposes of this case the contract and acts' of the parties suffice to establish that Kootenai river is navigable. There is neither allegation nor direct evidence that the approval aforesaid was secured. Because thereof defendant urges that the contract did not take effect, that the bridge was built unlawfully, and that the surety is not liable. The contract was lawful; and, since it has been performed, it must be presumed it was, as it could be, lawfully performed—that the contingency happened (the necessary approval) upon which it was to become effective. Then, too, so far as this action is concerned, the obligation to secure such approval, if not more, was as much the contractor’s as the builder’s. The former could not lawfully perform its contract prior to approval. A surety engages its principal will lawfully perform. And if the latter unlawfully performs its contract, the surety is not discharged unless the builder knew mí and acquiesced in such unlawful performance. And upon the surety is. the burden to prove this.

[5] It is admitted payments were made to the contractor “out of the order” of the contract, and were “anticipated”; but this does not serve to show that substantial departure from the contract which alone may discharge a surety in that it may injure him. If the payments were made out of the order stipulated, it may be the contingencies upon which payments were due happened out of the order anticipated, and that the payments were properly made. Again, county warrants seem to have been referred to as payments, and it does not appear when the money was paid or the warrants even delivered.

[6,7] The builder accepted the bridge. This waived all the contractor’s defaults discoverable by reasonable inspection, like failure to paint the completed bridge (which, however, does not appear to have been of the contract), but not those not so discoverable, like the defective piles. For the latter, hut not the former, the surety is liable.

There remains but the amount of damages. The contract price paid *472was $29,345.40. The bond is in the sum of $30,000. Of the bridge the shore piers and approaches alone remain. The county has not rebuilt. It may not. It would not seem bound to do so and to incorporate these remnants to mitigate damages. Under the circumstances, such action well may be imprudent and impracticable. Its right is to refrain or to build of a new design and materials. See U. S. v. Fidelity Co., 236 U. S. 526, 35 Sup. Ct. 298, 59 L. Ed. 696" court="SCOTUS" date_filed="1915-02-23" href="https://app.midpage.ai/document/united-states-v-united-states-fidelity--guaranty-co-98383?utm_source=webapp" opinion_id="98383">59 L. Ed. 696; 3 Suth. Damages, § 699. The loss is total. Any salvage is the contractor’s.

Plaintiff does not claim or suggest it is entitled to interest, and the judgment will be for the contract price paid and costs.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.