231 F. 468 | D. Mont. | 1916
Action by a builder of a bridge against the contractor’s surety. Defendants’ objection to any evidence “for the purpose of the record, * * * simply a formal matter,” no defect in the complaint being pointed out, was overruled as. of a class disfavored, in that it tends to defeat justice rather than to promote it, the court stating if the complaint was defective, amendment would be allowed. If necessary, amendment is deemed made to conform to proof.
The complaint is that the contractor, the Coast Bridge Company, failed to perform its contract, in that it did not drive the center pier piles as required by. specifications, and because of which the pier undermined and with the bridge fell. The answer is of denials only. The structure was a highway bridge of 18-foot floor width and two1 220-foot spans, supported by a center pier. It was at Rexford, Mont., and over the Kootenai river, a swift mountain stream over 400 feet wide, the water stages varying in depth from 12 to 30 feet.
The contractor agreed to. provide “all material, labor and other things of every description” to build the bridge “in good workmanlike and substantial manner * * * so as to make it a perfect bridge according to the plans and specifications” furnished by it. These plans were indefinite in the matter of the depth of the center pier, extent of concrete, and whether or not piles would be used therein, the contractor leaving “that open to be determined after” excavation.
References to “the engineer” are ambiguous, save in one instance to “the local engineer.” If construed to import the builder’s engineer (though these were the contractor’s specifications), there was no stipulation obligating the builder to secure an engineer. It was optional, and the builder secured none. For the center pier the contractor excavated about 8y2 feet deep in sand and gravel. Its superintendent testified the bottom was then tested with an inch pipe and a maul and by four piles 8 inches square, which were driven until destroyed, “probably 4 feet” deep. He ordered like piles 22 feet long, and 62 of them were driven, it would seem, to depths varying from 3 feet S inches to. 3 feet 11 inches.
When the driving commenced the water was about 18 feet deep., and gradually rose, each pile being driven until its top was practically at water level. They were not ringed nor shod, and broomed little, if any. Around and upon them the concrete center pier was constructed. About six months later the water undermined the pier, so that it overturned and the bridge fell. A diver found that about 16 piles at the downstream end of the pier were intact, the others having been sheared off. Without further detailing the evidencé and conflicts in facts and opinions, the finding is that the piles were not driven in accordance with the contract and to refusal, and that because thereof the pier and bridge fell.
Curiously enough, defendant introduced evidence, and contends that the excavation for the pier should have been deeper and no piles used; that the damage is due to defective plans and poor engineering. To concede it would not seem to- better defendant’s case, for the contractor was responsible for both plans and engineering. And if necessary, the complaint would be deemed amended to conform to this contention and proof, involving no change in the cause of action, hut only in the particulars thereof.
For the purposes of this case the contract and acts' of the parties suffice to establish that Kootenai river is navigable. There is neither allegation nor direct evidence that the approval aforesaid was secured. Because thereof defendant urges that the contract did not take effect, that the bridge was built unlawfully, and that the surety is not liable. The contract was lawful; and, since it has been performed, it must be presumed it was, as it could be, lawfully performed—that the contingency happened (the necessary approval) upon which it was to become effective. Then, too, so far as this action is concerned, the obligation to secure such approval, if not more, was as much the contractor’s as the builder’s. The former could not lawfully perform its contract prior to approval. A surety engages its principal will lawfully perform. And if the latter unlawfully performs its contract, the surety is not discharged unless the builder knew mí and acquiesced in such unlawful performance. And upon the surety is. the burden to prove this.
There remains but the amount of damages. The contract price paid
Plaintiff does not claim or suggest it is entitled to interest, and the judgment will be for the contract price paid and costs.