155 F. 77 | 6th Cir. | 1907
After making the foregoing statement of the case,
delivered the opinion of the court.
“A contract to buy all that one shall require for one’s own use in a particular manufacturing business is a very different thing from a promise to buy all that one may desire, or all that one may order. The promise to take all that one can consume would he broken by buying from another, and it is this obligation to take the entire supply of an established business which saves the mutual character of the promise.”
To the same effect and directly in point are the cases of Cold Blast Transp. Co. v. Kansas City Bolt & Nut Co., 114 Fed. 77, 52 C. C. A. 25, 57 L. R. A. 696, Minnesota Lumber Co. v. Whitebreast Coal Co., 160 Ill. 85, 43 N. E. 774, 31 L. R. A. 529, and Wells v. Alexandre, 130 N. Y. 642, 29 N. E. 142, 15 L. R. A. 218.
2. Among the findings of fact was the following:
“(10) Throughout the United States it is a custom among manufacturers of steel eastings, such as were to be manufactured for defendant by plaintiff, to make all agreements contingent upon strikes, accidents, and other unavoidable delays, and all contracts for the manufacture of such castings were made with reference to and conditioned upon such custom, which said custom was well known to defendant when said agreement was entered into, and was made with reference to said custom.”
The court also found that the contract itself was contained upon the printed letter head of the plaintiff, which, among other things, had printed thereon these words: “All agreements contingent upon strikes, accidents and other unavoidable delays, beyond our control.”
That nothing will excuse the performance of a contract except an act of God or the public enemy is equally clear. Whether the plain agreement to supply the defendant with all the castings which its business should require is not contradicted by a custom or usage which would excuse the performance upon the contingency of a strike or accident is a very grave question, and one which we pretermit because we do not find that the plaintiff was prevented from performing its contract by the occurrence of any accident or other contingency included by the alleged custom or usage in the steel casting business. It is true that the plaintiff’s furnace was shut down from August 1st to November 15th for the purpose of making necessary repairs. But the facts found show that the want of repair which necessitated going out of blast for repairs August 1st was a condition which existed at the time this contract was executed, and had existed for some months before. The' output had been severally affected for months by a- defective operation, the cause of which was not understood. Various efforts were made to remedy the matter, but without results. In this existing .crippled condition plaintiff entered into the contract here involved and continued to operate until some time in June, matters growing worse, when notice was given of a shutdown August 1st to overhaul and repair. It was after the work of overhauling had begun that the cause.of the bad draught which had troubled the operation was discovered and remedied. The “accident” or “unavoidable delay” excused by custom or usage must be confined to accidents and delays due to- causes originating after the contract. Plaintiff knew when it made this contract that its furnace was working badly, and that normal results could not be relied upon. They did not then know the cause of the- trouble, but that the trouble was more vital than they then suspected, and would take longer to remedy is a misfortune that cannot be cast.upon the defendant-as an “accident” excused by custom or usage.
3. The “requirements” for defendant’s business- for November and December were in. excess of requirements of preceding months. The defendant in error says, .that on October 24th it gave plaintiff in error notice that on -or before November 19th its furnace would be in running order, and that if furnished patterns they could put them in sand and be ready to turn out work on or before that day. The facts found show that the castings required were made upon patterns supplied by defendant, and that when plaintiff shut down these patterns were necessarily returned and placed with other founders, and so were in the handá of other contractors. When this notice was given, defendant notified plaintiff that it had been forced to make arrangements with) other’ founders for- its requirement's for the remainder of the y'earpand that its' patterns were in the possession of such other con
Judgment reversed, with directions to enter judgment in accordance with this opinion.