184 Mo. App. 296 | Mo. Ct. App. | 1914
The plaintiff, a contractor, sues the city of Eolia for furnishing the materials and constructing 834,837 square yards of first-class brick pavement with concrete base upon the streets of such city. It is alleged that this work was done at the special instance and request of the defendant city, at the places designated by the defendant, during August and September, 1910; that’on October 3, 1910', by resolution of its board of aldermen, the defendant accepted such work and materials and argeed to pay plaintiff $2.34 per square yard, making a total of $1953.53; and that on October 12, 1910, defendant agreed in writing to pay said sum in three equal annual installments. An itemized statement is filed, giving these items: 1 ‘ For the paving in front of the governments lots, $766.87. For the extras as follows: For paving the south half of the intersection of Sixth street and Pine street, $272.38. For paving the east half of the intersection of Eighth street and Pine street, $234.50. For the cross walks, all on Pine street between Sixth and Tenth streets, $679.78, making a total of $1953.53.”
It will be noted that the petition does not allege the furnishing of materials and the doing of this work under a written contract,, by ordinance or otherwise, previously made by the parties upon a consideration wholly to be performed or executed subsequent to the making of the contract, as required by section 2778, Eevised Statutes 1909. The allegation of doing the work at the special instance and request and at the places designated by defendant and' the subsequent acceptance and agreement to pay for same in writing plainly implies the contrary and such the evidence shows to be the fact. The court found for the^plaintiff and entered judgment for the amount sued for.
The plaintiff put in evidence an ordinance of said city, approved June 2, 19101, accepting the bid of plaintiff for paving Pine street in said city from the center of Sixth street to the center of Tenth street, and award
It is conceded that this is the only contract made in writing at any time and the only one authorized by any ordinance prior to the time of doing this work. As to the claimed ratification by ordinance or resolution after the work was done, we shall speak later.
Two of the items sued for here, for the paving in front of the government lots, $766.87, and for paving the east half of the intersection of Eighth street and Pine street, $234.50, are embraced in the paving of Pine street from curb to curb from the center of Sixth street to the center of Tenth street provided for by the ordinance and contract above mentioned. To complete and comply with his contract plaintiff must do the paving which is sued for in these two items, and, under the contract, the city is not liable therefor, except to issue special tax bills covering the same-. It should be said in explanation of these items that the
The basis of plaintiff’s claim for recovery against the city, in addition to its ratification after the work was done, is a parol contract with the mayor and members of the city council, constituting the street committee, authorizing the doing of this work at the expense of the city. The evidence shows that, as to the paving fronting on the government property, the plaintiff declined to sign the contract above mentioned until these city authorities assured him and agreed with him, verbally of course, that the city would pay for this part of the paving. It is also shown that it was not contemplated that the old paving at the intersection of Eighth street and Pine' street should be torn up and replaced, but, during the progress of the work, the different grades and, perhaps, other reasons necessitated or made this highly desirable and these same city officials assured the plaintiff and agreed with him that the city would pay for this work. Likewise,
Under these facts the plaintiff cannot recover. No one can recover against a municipal corporation for work done or materials furnished except under a valid contract made in the manner authorized by law. [State ex rel. v. Dierkes, 214 Mo. 592, 113 S. W. 1081.] The power of such corporations to contract is limited and restricted both as to substance and form. The basis of such limitations and restrictions is our statute, section 2778> Revised Statutes 1909', and it has been ruled time and again that contractors, and others, when dealing with municipal corporations are charged with notice of the restrictions which the law imposes on such corporations and their officials in making contracts. [Keating v. City of Kansas, 84 Mo. 415, 419; Pryor v. City of Kansas, 153 Mo. 135, 142, 54 S. W. 499; Thornton v. City of Clinton, 148 Mo. 648, 659, 50 S. W. 295; Cheeney v. Brookfield, 60 Mo. 53; Anderson v. Ripley County, 181 Mo. 46, 64, 80 S. W. 263.] This statute, section 2778, requires all contracts with cities, including the consideration, to be in writing and while an ordinance of the city and a written acceptance of the same by the other party may be a sufficient compliance with the statute to constitute a valid written contract, Water Co. v. City of Aurora, 129 Mo. 540, 578, 31 S. W. 946, yet, a contract not in writing is absolutely void. [Cotter v. Kansas City, 251 Mo. 224, 230, 158 S. W. 52; Anderson v. Ripley County, 181 Mo. 46, 80 S. W. 263.] In Cook & Son v. City of Cameron, 144 Mo. App. 137, 144, 128 S. W. 269, where a
Not only is a verbal contract made by city officials void and affords no basis for a recovery by one doing work or furnishing materials thereunder, but such a dead contract cannot be subsequently ratified so as to breathe vitality into it. Thus it is said, in Compressed Air Co. v. Fulton, 166 Mo. App. 11, 30, 148 S. W. 422: ‘‘Section 2778' of the Revised Statutes, 1909, distinctly provides the method by which cities may contract, it being provided, among other things, that the contract shall be in writing, and it has been held that a contract made by an agent of a city not in accordance with the statute is void ab initio and cannot be ratified. [See Savage v. City of Springfield, 83 Mo. App. 323; Perkins v. Independent School Dist. of Ridgeway, 99 Mo. App. 483, 74 S. W. 122.]” And, in Clay v. City of Mexico, 92 Mo. App. 611, 618, the court said: “If such work is done without an ordinance providing for it, the city can not be bound by a ratification of the work after it has been done by any action of the city council. [Kolkmeyer & Co. v. City of Jefferson, su
Cities cannot be made liable, either on the theory of estoppel or implied contract, by reason of the accepting and using the benefits derived from void contracts, Heidelberg v. St. Francois County, 100 Mo. 69, 76, 12 S. W. 914; Perkins v. School Dist. of Ridgeway, 99 Mo. App. 483, 488, 74 S. W. 122, nor because the special tax bills are valueless because issued illegally or- authorized by a void contract or for other reasons. [Cotter v. Kansas City, 251 Mo. 224, 158 S. W. 52.] As there stated, Fisher v. St. Louis, 44 Mo. 482, is no longer the law on this point.
The reason that courts must and do hold that cities cannot ratify a contract not in writing or authorized by a valid ordinance is found in the statute, section 2778, supra. That statute requires that such a contract in order to be valid must be upon a consideration to be performed after the making of the contract. A contract, however formal and authorized by a valid ordinance, to pay for work or materials already performed or furnished, is void and no recovery can be based thereon. In Crutchfield v. Warrensburg, 30 Mo. App. 456, 461, the court held that: “The whole legis
The acts of ratification on which plaintiff relies as authorizing a recovery here are that after the work was all done, the city passed a resolution accepting as satisfactory the paving done by the plaintiff on Pine street between the centers of Sixth and Tenth streets. Evidently this resolution only had reference to the work done by plaintiff under the written contract for which special tax bills were to be issued, because it excludes part of the work now sued for. The city also, after such work was done, passed an ordinance apportioning the costs thereof and levying and direct
Plaintiff calls our attention to this provision of the written contract for paving Pine street and issuing special tax bills therefor: “Any work not herein specified which may be fairly implied as included in this contract of which the engineer shall be the judge, shall be done by the first party without extra charge. The first party shall also do such extra work, in connection with the contract, as the engineer specially directs, and if it shall be of a kind for which no price is stated in the contract, such price shall be fixed by the engineer, but no claim for extra work shall be allowed, unless the same was done in pursuance of special orders, as aforesaid, and the claims presented as soon as practicable after the work is done and before the final estimate.” It is then urged that this provision of the contract is sufficient to warrant the doing of the additional and extra work now sued for at the direction of the city officials. However that may be, it must be borne in mind that this written contract was entered into under sections 9403 and 9406, Revised Statutes 1909', and provides that all work done thereunder shall be paid for in tax bills and in no event is the city to be held liable therefor. It is evident, therefore, that any additional or extra work thereby, authorized must be such as can be included in the special tax bills to be issued thereunder. This is not a contract for work to be paid for by the city and we cannot so construe a contract expressly ex-
This case is unlike Heman v. City of St. Louis, 213 Mo. 538, 547, 112 S. W. 259, which involved a contract authorized by the charter of that city covering all work to be done during a year’s time in a large section of the city and providing that the payment for “extra work” should be made by the city. There the contract made the city liable; here it exempts it. Nor is Whitworth v. Webb City, 204 Mo. 579, 103 S. W. 86, in point, as the city’s' liability for extra work was not involved and all that is there said applies to a contract ’ obligating the city to pay personally for work done.
Nor does this suit involve the liability of defendant city growing out of its violation of a contract or its refusal to perform or permit the performance of a contract made by it. The suit is not brought nor was it tried on any such theory. Defendant is sued for an initial liability under the contract, not a consequential liability for its violation. Chambers v. City of St. Joseph, 33 Mo. App. 536; Oster v. City of Jefferson, 57 Mo. App. 485, and Ash & Gentry v. Independence, 79 Mo. App. 70, and similar cases are not applicable. [See Thornton v. City of Clinton, 148 Mo. 648, 662, 50 S. W. 295.]
The apparent hardship and injustice resulting to one who has acted'in good faith arising, from enforcing the strict rules laid down by our statutes in making contracts with public corporations has often been weighed against the abuse and squandering of public money growing out of a disregard of such restrictions. We refer any interested reader to Crutchfield v. Warrensburg, supra, and Cotter v. Kansas City, supra. It is sufficient to say that this State has tried both systems and'until the Legislature sees fit to adopt
The result reached is that the petition does not state a cause of action and none is shown by the evidence. Other questions are discussed in the able briefs of learned counsel on either side, but wh$t we have said disposes of the case adversely to plaintiff' and the judgment of the trial court is reversed.