Lighting & Power Services, Inc. v. RobertsLighting & Power Services, Inc. v. Roberts
Case Information
*1 Before LOKEN, Chief Judge, HEANEY and HANSEN, Circuit Judges.
________________
HANSEN, Circuit Judge.
Lighting & Power Services ("LPS") filed suit against Wayne M. Roberts, Inc.
("Roberts") to recover additional construction costs pursuant to the Miller Act,
I. Background
This dispute stems from a government construction project at Jefferson Barracks in St. Louis, Missouri. Roberts was the general contractor for the United States government; LPS was Roberts's electrical subcontractor. The construction contract required Roberts to obtain a payment bond under the Miller Act to protect subcontractors and suppliers. [2] The renovation was scheduled for completion in six months, but ultimately took over twenty-two months. Both parties conceded that the government caused the delays.
*3 LPS filed suit under the Miller Act, seeking to recover the additional costs it incurred as a result of the delay. [3] LPS used the total cost method to calculate its damages and sought $110, 641.00. The district court instructed the jury as follows:
Instruction No. 5
In this case, the plaintiff seeks to prove its alleged damages by evidence of its total costs of performing its subcontract with Wayne M. Roberts, Inc. In order to establish damages in this way, the plaintiff must prove by a preponderance of the evidence that:
1. It is impracticable for the plaintiff to prove its actual losses directly;
2. The plaintiff's bid that was accеpted by Wayne M. Roberts, Inc. was reasonable;
3. Plaintiff's actual costs were reasonable;
4. Defendant has some responsibility in causing plaintiff's actual losses; and
5. Plaintiff incurred damages as a consequence. (Appellant's App. at 129.) The jury returned a verdict in favor of Roberts. On appeal, LPS argues that subpart four of the instruction was given in error because the Miller Act permits LPS to recover its additional costs of labor and materials regardless of *4 Roberts's responsibility for causing those costs. Roberts responds that subpart four of the instruction was required by the law of this circuit because LPS chose to calculate its damages using the total cost method.
II. Standard of Review
A district court has broad discretion in formulating jury instructions.
Generally, we review jury instructions given by a district court for abuse of
discretion. Hartley v. Dillards, Inc.,
After carefully reviewing the transcript, we hold that LPS's objections to
instruсtion five were sufficient for the purposes of
We note that
III. Jury Instruction 5
We first address the question of whether, in order to recover delay damages under the Miller Act, a subcontractor is required to show that the general contractor was at least partially to blame for the subcontractor’s actual losses. We hold that the Miller Act does not require that the general contractor be at fault in order for the subcontractor to recover on the Miller Act payment bond.
This court first addressed this question in Consol. Elec. & Mech., Inc. v. Biggs
Gen. Contracting, Inc.,
Several circuits have interpreted the Miller Act to allow full recovery by a subcontractor when the general contractor is not wholly at fault for the delays . Wе agree with the reasoning of these circuits. The Miller Act favors allowing full recovery from a general contractor regardless of *7 fault because general contractors have privity of contract with the government and can thus recover delay damages directly from the governmеnt, while subcontractors cannot.
Id. at 434-35(citations omitted) (emphasis added). See also Mai Steel Serv. Inc. v.
Blake Constr. Co.,
The second issue is whether the use of the total cost method to calculate damages requires a showing that the general contractor was at least partially responsible for the subcontractor's losses, even though the Miller Act does not require such a showing. We also answer this question in the negative, and we hold that the total cost method can be used to calculate damages under the Miller Act, regardless of the fault of the general contractor.
Undеr the total cost method, the "total cost" is defined as the actual cost minus
any cost already paid on the contract.
[5]
Moorhead Constr. Co. v. City of Grand Forks,
*8 The acceptability of the (total cost) method hinges on proof that (1) the nature of the particular losses make it impossible or highly impracticable to determine them with a reasonable degree of accuracy; (2) the plaintiff's bid or estimate was realistic; (3) its actual costs were reasonable; and (4) it was not responsible for the added expenses.
Id. at 1016 (citations omitted). In the presеnt case, Instruction 5 did not require the
jury to find that LPS "was not responsible for the added expenses," as in Moorhead,
but instead required the jury to find that "[Roberts] ha[d] some responsibility in
causing plaintiff's actual losses." Relying on Neb. Pub. Power Dist. v. Austin Power,
b. The bid or estimate of Austin Power was realistic; c. The actual cost incurred by Austin Power was *9 reasonable;
d. Austin Power was not responsible for the amount sought to be recovered above the amount previously paid under the contract; and
e. The costs which make up the amount sought to be reсovered were proximately caused by [Nebraska Power's] breaches of contract.
Id. 965-66. The jury awarded Austin breach of contract damages. Id. at 966. This court affirmed, holding that the district court had properly submitted total cost evidence to the jury. Id. at 968.
Austin Power is readily distinguishable from the case аt hand, principally
because Austin Power is not a Miller Act case. Austin Power involved state law
negligence and breach of contract claims. Id. at 963-64. The instruction given by the
trial court in Austin Power was suited to a breach of contract case where a jury must
also find cause in fact. Such an instruction would not fit a Miller Act claim because
the Miller Act does not govern actions by a subcontractor against a general contractor
for breach of contract. Consolidated,
There are cases that interpret the final factor of the total cost method to require
a subcоntractor to prove not only that it was not responsible for the added expenses,
but also that the defendant was responsible for them. See, e.g., Youngdale & Sons
Constr. Co. v. United States,
For the reasons stated, we reverse the judgment of the district court and remand for further proceedings not inconsistent with this opinion.
______________________________
Notes
[1] Formerly codified at
[2]
[3]
[4]
[5] In non-Miller Act cases, the “total cost” may generally include reasonable lost profits. Neb. Pub. Power Dist. v. Austin Power,773 F.2d 960 , 965 (8th Cir. 1985); Layne-Minnesota p. r., Inc. v. Singer Co., 574 F.2d 429, 434 (8th Cir. 1978). However, the Miller Act does not encompass recovery for lost profits. Consolidated ,167 F.3d at 436 .