The plaintiff, James T. Lichoulas, Jr. (plaintiff), commenced this action in the Land Court challenging the validity of the city of Lowell’s eminent domain taking of the plaintiff’s dormant hydroelectric power plant. The Land Court dismissed the complaint for want of subject matter jurisdiction. The plaintiff has appealed.
1. Background. In 1986, the plaintiff was licensed by the Federal Energy Regulatory Commission (FERC) to operate the
On April 25, 2006, the defendant, the city of Lowell (city), as part of an urban renewal and revitalization plan, took the Appleton Mill Property by eminent domain. The order of taking cited “the applicable provisions of Massachusetts General Laws, Chapter 79 and Chapter 121B and also Chapter 610 of the Acts of 1967, and of any and every other power granted or implied” as authority for the city’s exercise of power. The city notified FERC of the taking and requested that it inspect the project. On March 21, 2007, FERC issued a “Notice of Termination by Implied Surrender and Soliciting Comments, Protests, and Motions to Intervene,” initiating proceedings to terminate the plaintiff’s Federal license.
2. Prior litigation. The plaintiff initially brought suit in the United States District Court for the District of Massachusetts, where he sought a return of the property and a declaration that the city’s taking of the project violated the Federal Power Act (FPA), 16 U.S.C. §§ 791a et seq., which, he claims, prohibits the taking by eminent domain of a Federally licensed power plant by a municipality that is not competent to, nor actually undertakes to, maintain and operate the plant thereafter (Federal court FPA claims). The plaintiff alternatively sought, under that court’s supplemental jurisdiction, compensation for the taking pursuant to G. L. c. 79, § 14 (Federal court compensation claim).
The Federal District Court dismissed the complaint, without prejudice to refiling, on March 31, 2008. Lichoulas vs. Lowell, U.S. Dist. Ct., No. 07-10725-RWZ (D. Mass. March 31, 2008). That court concluded that “the validity of the plaintiff’s license lies at the heart of this case,” and that resolution of the plaintiff’s claims should therefore await conclusion of the FERC proceedings at which the status of the plaintiff’s license would be
While the plaintiff’s appeal to the United States Court of Appeals for the First Circuit was pending, on September 18, 2008, FERC concluded its proceedings by finding that the plaintiff had impliedly surrendered his Federal license by failing to operate the project, and ordered the license terminated. See Lichoulas v. Lowell,
On January 30, 2009, the United States Court of Appeals for the First Circuit affirmed the Federal District Court’s judgment of dismissal without prejudice. Id. at 14. The court stated that, under the circumstances, “the district court was entitled, as a matter of judicial judgment, to await the outcome of a FERC proceeding that likely would eliminate any warrant for intervention by a federal court.” Ibid. Noting FERC’s termination order, and the plaintiff’s appeal therefrom, the court explained that “the evident prospect that FERC would revoke the license made clear that the federal interest, such as it was, would likely be mooted; and any objection to the taking, or deficiency in adequate compensation, could be and preferably is to be done in state proceedings.” Id. at 13.
3. This lawsuit. On March 23, 2009, the plaintiff brought this action in the Land Court.
Sections 35 and 37 are contained within a subchapter of c. 164 entitled “Municipal Lighting Plants.” Section 35, entitled “Vote of a city to acquire plant,” states, “A city shall not acquire such a plant until authorized by a two thirds vote of its city council . . . passed in each of two consecutive municipal years and thereafter ratified by a majority of the voters at an annual or special city election” (emphasis added). G. L. c. 164, § 35. Section 37 then sets forth the process by which the town clerk must certify and transmit the records of a vote taken in compliance with § 35 to the Department of Telecommunications and Energy.
The FPA states in relevant part: “[T]he right of the United States or any State or municipality to take over, maintain, and operate any project licensed under this chapter at any time by condemnation proceedings upon payment of just compensation is expressly reserved.” 16 U.S.C. § 807(a). Under the FPA, a “municipality” is defined as “a city, county, irrigation district, drainage district, or other political subdivision or agency of a State competent under the laws thereof to carry on the business of developing, transmitting, utilizing, or distributing power.” 16 U.S.C. § 796(7). It is the plaintiff’s second contention that the
The Land Court dismissed the action for lack of subject matter jurisdiction pursuant to Mass.R.Civ.P. 12(b)(1),
On May 28, 2010, while this appeal was pending, the United States Court of Appeals for the District of Columbia Circuit affirmed the termination by FERC of the plaintiff’s license on the ground of implied surrender. Lichoulas v. Federal Energy Regulatory Commn.,
4. Discussion. Under its statutory grant, the Land Court has jurisdiction over “[a]ll cases and matters cognizable under the general principles of equity jurisprudence where any right, title or interest in land is involved.” G. L. c. 185, § l(k). In determining whether the plaintiff has presented such a case, and therefore whether dismissal was appropriate under rule 12(b)(1), we accept as true all factual allegations of the plaintiff’s complaint, as well as any favorable inferences reasonably drawn therefrom, see Ginther v. Commissioner of Ins.,
Consequently, it is well established in this Commonwealth that one whose private property has been taken by an exercise of the power of eminent domain may bring an action in equity to challenge the validity of that taking. See, e.g., McAuliffe & Burke Co. v. Boston Housing Authy.,
One basis on which such suits have successfully been brought is for “fail[ure] to comply with the procedural requirements of G. L. c. 79.” Cumberland Farms, Inc. v. Montague Economic Dev. & Industrial Corp.,
The city contends that the taking at issue is not within the scope of c. 164, §§ 35 and 37, and that the taking was therefore properly authorized, both because the project was not functional when taken and was therefore not a “plantQ for the manufacture or distribution of . . . electricity” within the meaning of G. L. c. 164, § 34, and because the city does not intend to maintain or operate the project for the manufacture or distribution of electricity. (The city did assert at oral argument its authority to sell the subject property to, e.g., a developer who would use the plant for electrical power generation.)
These arguments do not go to the Land Court’s subject matter jurisdiction, and we express no opinion on them. “Subject matter jurisdiction is ‘jurisdiction over the nature of the case and the type of relief sought.’ ” Middleborough v. Housing Appeals Comm.,
b. Federal law. The judge also concluded that the Land Court was without jurisdiction to consider the plaintiff’s claim involving the FPA. Section 825p of 16 U.S.C. provides:
“The District Courts of the United States . . . shall have exclusive jurisdiction of violations of this chapter or the rules, regulations, and orders thereunder, and of all suits in equity and actions at law brought to enforce any liability or duty created by, or to enjoin any violation of, this chapter or any rule, regulation, or order thereunder.”
Because the Federal courts have exclusive jurisdiction over claims of violations of the FPA, dismissal of the complaint insofar as it sought relief for such a violation was proper. The plaintiff points to language in the First Circuit decision that in his Federal case he was “simply seeking to have the federal court derail a state takings proceeding in which — given the Supremacy Clause — he could presumably raise his objections.” Lichoulas v. Lowell,
To the extent the Land Court’s order dismissed the plaintiff’s State law cause of action, it is reversed; to the extent it dismissed the plaintiff’s FPA action, it is affirmed. The order denying the
So ordered.
Notes
The defendant argues that the decision of the Federal District Court was res judicata to this action. “ ‘Dismissal without prejudice’ is a dismissal that does not ‘operate as an adjudication upon the merits,’ [Fed. R. Civ. R] 41(a)(1), and thus does not have a res judicata effect.” Cooter & Gell v. Hartmarx,
The defendant contends on appeal that the plaintiff’s State-law challenge to the validity of the taking was insufficiently pleaded. The complaint does include only two instances in which the plaintiff makes an allegation of invalidity under Massachusetts law, and it does so without identifying the statutory provision violated. Nonetheless, Mass.R.Civ.P. 8(a),
Now the Department of Public Utilities. St. 2007, c. 19, §§ 21, 54.
The defendant argues that any right to enforce the provisions of c. 164 is vested in the Department of Public Utilities by G. L. c. 164, § 69H. But that section does not grant exclusive enforcement authority. Nor does a statutory extension of standing to one who is not otherwise injured normally imply a denial of standing to those who are. Cf. Maffei v. Roman Catholic Archbishop of Boston,
We express no opinion on what the subsidiary questions will be, something that will turn on the manner in which the parties litigate the case on remand, or on how they should be answered.