This is аn, appeal from an order denying a motion to stay this action pending arbitration. We affirm.
FACTS
On July 27, 1998, Liberty Builders, Inc. contracted to build a house for William Gregory Horton and Andrew G. Horton. The construction contract provided for arbitration as follows: “All disputes hereunder shall be resolved by binding arbitration in accordance with rules of the American Arbitration Association.” 1 Disputes arose near the end of construction regarding certain change orders. When the Hortons refused to pay for these changes, Liberty filed for a mechanics’ lien. Liberty then filed this action to foreclose on that mechanics’ lien on January 31,1995.
Liberty amended its cоmplaint on November 2, 1995. The Hortons answered and counterclaimed on March 19, 1996. Because the Hortons’ counterclaim alleged Liberty used defective materials in construction, Liberty brought a third-party suit against suppliers on March 29,1996. The third-party suit was dismissed pursuant to a consensual summary judgment, and the complaint was agаin amended in late 1997 to include a cause of action for breach of contract.
The parties pursued this litigation for two and one-half years before Liberty moved, on June 5, 1997, to stay the circuit court action in favor of arbitration. In an order filed February 23, 1998, the circuit judge concluded Liberty’s delay prejudiced the Hortons and Liberty therefore waived its right to arbitrate. Liberty appeals. 2
Liberty contends the circuit judge erred by finding Liberty waived its right to arbitrate arguing the parties contractually stipulated that participation in litigation would not be deemed a waiver. We disagree and hold the circuit judge correctly ruled that Liberty waivеd its right to arbitrate.
Standard of Review
While we found no South Carolina case specifically addressing the standard of review applicable to an order denying a motion to stay an action pending arbitration, we believe the circuit judge’s factual findings should be given some deference. This conclusion accords with the standard of rеview applied in other pretrial motions.
See, e.g., City of Chester v. Addison,
Other jurisdictions have specifically addressed the issue of what standard of review to apply to a trial judge’s findings on motions to stay litigation and compel arbitration, arriving at different, but nonetheless deferential, standards. The federal сourts decide motions to stay under the Federal Arbitration Act. 9 U.S.C.A. § 3 (1999). “The federal circuits are united in holding that the
ultimate
determination of waiver is reviewed de novo, as a matter of law,” but the factual findings of the lower court are accorded some deference and reviewed for substantial evidence, a standard analogous to the clear error test.
J.L. Steele v. Lundgren,
The state courts have generally followed the federal courts.
3
See, e.g., D.M. Ward Constr. Co. v. Electric Corp. of Kansas City,
Still other jurisdictions make no explicit distinctiоn between the ultimate legal question of waiver and the underlying factual findings of prejudice.
See, e.g., Shultz v. Lujan,
A final group of jurisdictions apply the strictest standard of review and require the reviewing court to accept the trial
We now join the majority of jurisdictions granting deference to a circuit judge’s factual findings made when deciding a motion to stay an action pending arbitration. We acknowledge that determining whether a party waived its right to arbitrate is a legal conclusion subject to de novo review; nevertheless, the circuit judge’s factual findings underlying
Law/Analysis
It is generally held that the right to enforce an arbitration clause may be waived.
Hyload, Inc. v. PreEngineered Prods., Inc.,
In order to establish waiver, a party must show prejudice through an undue burden caused by delay in dеmanding arbitration.
Sentry Eng’g & Constr., Inc. v. Mariner’s Cay Dev. Corp.,
The circuit judge found Liberty’s delay in asserting its right to arbitrate prejudiced the Hortons. 9 We agree.
The Hortons were forced to answer Liberty’s complaint and respond to discovery in thе circuit court, most of which would not have been necessary or available if Liberty had pursued
In respоnse to the waiver contention, Liberty cites the American Arbitration Association rules which were incorporated into the parties’ contract and provide that “[n]o judicial proceeding by a party relating to the subject matter of the arbitration shall be deemed a waiver of the party’s right to arbitrate.” Rulе 48(a), Construction Industry Arbitration Rules of the American Arbitration Association. While this rule may appear to preserve the right to arbitrate even in the face of litigation, 10 it has not been interpreted so broadly.. A California appellate court recently explained:
Among the difficulties we have with [the argument that this rule preserves the right to arbitrate notwithstanding extensive discovery and litigation] is the fact that no other court has accepted such an expansive interpretation of the AAA rule. At most, the courts which have addressed the issue have held that AAA’s “no waiver” rule means that participation in a judicial proceeding, will nоt by itself give rise to a waiver. Indeed, one court has expressly held that a “no waiver” rule does not prevent a waiver where participation in a judicial proceeding has caused prejudice to an adversary.
McMillin Dev., Inc. v. Home Buyers Warranty,
Liberty attempts to justify its initial resort to the court system by contending the time constraints imposed by the mechanics’ lien statute required instigating a court action to preserve its rights. 11 However, when Liberty contracted with the Hortons, it agreed to resolve “all disputes hereunder” through binding arbitration. This language is broad enough to encompass Liberty’s dispute regarding payment by the Hortons. Thus, we do not believe that Liberty was required to institute this suit in order to obtain payment. Furthermore, rather than pursue litigation for two and one-half years, Liberty could have immediately filed a motion to stay its suit and compel arbitration in order to protect its arbitratiоn rights while complying with the time requirements for mechanics’ lien.
AFFIRMED.
Notes
. The circuit judge found, and Liberty concedes, the arbitration clause failed to conform to the South Carolina Uniform Arbitration Act’s requirements. However, the circuit judge concluded the Federal Arbitration Act could have applied to enforce the arbitration clause if Liberty had not waived its right to compel arbitration.
. An order refusing to stay an action pending arbitration or compel arbitration is immediately appealable. 9 U.S.C.A. § 16(a)(1)(A) & (C) (1999); S.C.Code Ann. § 15-48-200(1) & (2) (Supp.1998).
. In addition to applying state statutory schemes, state courts must apply the Federal Arbitration Act (FAA) when a contract affects interstate commerce.
See, e.g., Soil Remediation Co. v. Nu-Way Envtl., Inc.,
.
See also Central Nat’l Ins. Co. of Omaha v. Lerner,
.
See also Nettleton v. Edward D. Jones & Co.,
. Some courts applying the abuse of discretion standard are addressing a petition for writ of mаndamus which already utilizes an abuse of discretion standard of review.
See Ex parte Parker,
.
See also Saxon Fin. Group, Inc. v. Goodman,
. This conclusion accords with the standard of review employed by South Carolina courts when reviewing other preliminary trial motions.
See, e.g., City of Chester,
. Even members of the American Arbitration Association’s Panel of Arbitrators for Construction Industry Disputes concede prejudicing a party warrants finding a waiver. See Robert M. Wright & Howard D. Venzie, Jr., Arbitration Waiver by Judicial Proceedings and the Effect of the Construction Industry: Arbitration Rules of the American Arbitration Association, 8-APR Constr.Law. 5, 35 (1988) ("Waiver should not be found unless there is an obvious ... prejudice to one of the parties.”).
. See generally Wright & Venzie, supra note 8, at 35 ("Construction Industry Rules are an important tool which should be fully used by counsel in attempting to [arbitrate] the merits regardless of the pretriаl stage to which the judicial proceedings may have advanced." (emphasis added)).
. S.C.Code Ann. § 29-5-90 (Supp.1998) ("Such a lien shall be dissolved unless the person desiring to avail himself thereof, within ninety days after he ceases to labor ... on such building or structure, serves upon the owner ... a statement of a just and true account of the amount due him____”); S.C.Code Ann. § 29-5-120 (1976) ("Unless a suit for enforcing the lien is commenced ... within six months after the person desiring to avail himself thereof ceases to labor on ... such building or structures, the lien shall be dissolved.”).
