This is а petition against the Commonwealth under G. L. (Ter. Ed.) c. 258 by an architect seeking to recоver $3,792.65 compensation for extra services alleged to have been performed under a written contract entered into between him and the Commonwealth acting by its dеpartment of State superintendent of buildings, hereinafter called the department, and the Massachusetts public building commission, hereinafter called the commission, for architectural and engineering services in connection with repairs upon the roof of the State House. An auditor found for the petitioner in the sum of $2,968.21 less the sum of $204.54, or a net total of $2,763.67. A judge of the Superior Court found for the petitioner in the sum of $208.91, being the total with interest of an item of $59.50 which is not now in issue and another item of $147.36 for supervisory services in conneсtion with certain work orders. The Commonwealth did not dispute the validity of this finding. The judge reportеd the case upon the stipulation that his finding of $208.91 should stand if he ruled correctly in excluding the work orders and granting certain requests of the respondent, otherwise this amount “should be increased by the sum of $2,763.67 which is the amount alleged to be due under said Article V” of the petitioner’s contract with the Commonwealth.
The contract in Article II enumerated the various kinds оf work the petitioner was to perform and in Article IV provided for his compensatiоn based upon a percentage of the amounts payable to all the contractors in repairing the roof. During the course of the work seven written orders for extrа work were given to the contractor. These orders were signed by the contractоr, accepted in writing by the department, and approved in writing by the commission. All of these orders bore the written recommendation of the petitioner. The petitioner’s compensation as to this class of work was provided for in Article V which was captioned “Extra Services and Special Cases” and in so far as now material read as fоllows: “If the Designer is ordered in *6 writing by the Department, with the approval of the Commission, and оnly when so ordered, to perform extra drafting or other services due to fundamental changes in the bid plans as required by the Department with the approval of the Commission ... he shall be paid therefor, in addition to the base fees such amounts as may be apрroved by the Department and the Commission” on a certain basis, including drafting time, cost for prints of plans, and a certain amount per hour for the time devoted directly to the wоrk by the petitioner.
We see no ambiguity in this written contract and its interpretation was a quеstion of law for the judge,
Creighton
v.
Elwell,
The petitioner properly does not cоntend that the public officials who acted in behalf of the Commonwealth in executing the contract had any authority to waive the provisions of the contract.
Stuart
v.
Cambridge,
The petitioner never received any written order to perform the extra architectural services for which he now claims compensation. The auditor found that the extra work and changes made in the original contract with the contraсtor were fundamental in order to perform properly
*7
all the work required to be dоne by the contractor, and the judge correctly granted the requests of the Commonwealth that the petitioner was not entitled to recover for services rendered duе to such fundamental changes in the absence of a written order from the department approved by the commission and that the written orders given to the contractor fоr extra work cannot be construed as written orders to the petitioner to perfоrm architectural services in connection with such work. The case is governed in its saliеnt points by
Crane Construction Co.
v.
Commonwealth,
Decision is to be entered for the petitioner for the amount found by the judge, and the Commonwealth is to have costs from the date of that finding.
Charles I. Hosmer, Inc.
v.
Commonwealth,
So ordered.