49 F. 708 | U.S. Circuit Court for the District of Eastern Missouri | 1891
(after stating the facts as above.) For the information of counsel the court states the conclusions it has reached concerning the various questions of law and fact that have arisen in this case as follows:
First. The second clause in the contract, declaring that the engineer’s measurements and calculations of the quantity and amount of the several kinds of work, and also that his classification of the material contained in excavations, shall be “final and conclusive,” is a valid provision, and is binding upon the parties to the agreement. Therefore there can be no recovery in excess of the engineer’s final estimate, unless such estimate is successfully assailed lor fraud, gross errors, or mistake. Railroad Co. v. March, 114 U. S. 549, 5 Sup. Ct. Rep. 1035; Wood v. Railroad Co., 39 Fed. Rep. 52, and citations; Sweet v. Morrison, 116 N. Y. 19, 22 N. E. Rep. 276; Brush v. Fisher, 70 Mich. 469, 38 N. W. Rep. 446.
(а) The court will relieve against mistakes in measurements and calculations that are apparent on the face'of the estimate, or that' are clearly proven, though not so apparent.
(б) If it is satisfactorily shown that the engineers failed, through oversight, to measure or estimate any particular part of the work, the court wall grant relief as to such mistakes.
■ (c) If it appears that the engineer in charge put a wrong construction on any provision of the contract, the court will correct any substantial errors resulting from such mistake, for the reason that the parties did not make the decision of the engineer as to the proper interpretation of the contract final,and conclusive. It is the province of the court to construe the agreement. Bridge Co. v. City of St. Louis, 43 Fed. Rep. 768.
(d) But in determining the kind of material found in the several cuts, the engineers were called upon to exercise their judgment. That was a matter, as the contract in substance recites, which involved the exercise of special skill and attention as the work progressed, and for that reason-the parties selected an umpire, by wrhose judgment they agreed to be bound. Ranger v. Railway Co., 1 Eng. Ry. Cas. 1; 13 Sim. 368. The court will not undertake to revise the decision of the engineer on questions of that character if it appears that he acted in good faith. The utmost it can do is to correct errors of classification that may have resulted from an erroneous interpretation of the contract.
(e) Slight discrepancies in measurements made by the respective parties must also be disregarded; and even when there are discrepancies of some magnitude the court must accept measurements made by the engineers of the railway company, unless the proof clearly shows that they are erroneous. The presumption is that all measurements made by such engineers are correct, and the burden is on the plaintiffs to overcome that presumption. Torrance v. Amsden, 3 McLean, 509; Bumpass v. Webb, 4 Port. (Ala.) 65; Pleasants v. Ross, 1 Wash. (Va.) 156.
Third. After an attentive consideration of the question, the court concludes that the engineers put a wrong construction on the second clause of the specifications, in so far as they construed the “plowing test ” to be applicable to shale, soapstone, cemented gravel, and hardpan, as well as to other hard, earthy substances. The right interpretation of the clause is as follows: Shale, soapstone, cemented gravel, and hardpan were known substances, and were known to be hard to handle. Therefore it was declared that they should be classified as loose rock. And, inas
But the court is of the opinion that the practice pursued by the engineers of estimating loose rock by percentages was justifiable and proper. Under all the circumstances of tlie case, that seems to have been the only fair and practicable method of classifying much of the material when the plowing test was applied. The evidence satisfies me that the material handled varied much in consistency and hardness, and lay in irregular strata. By far the largest portion of all the material found in the various cuts, except the rock cuts, was broken up, I think, by the use of a team of not more than six horses. Probably that was the most practicable and economical method of working the cuts, as an eight-horse team is usually cumbersome. Nevertheless, if the engineers had classified every cubic yard of earth that was so broken up with six horses “'as earth excavation,” it would not have accorded with the spirit of the contract. The application of that rule to the work of those contractors who had much hard material to handle, and very little easy plowing, would have been manifestly unjust. On the other hand, it would have been contrary to the spirit of the agreement, and equally unfair to the railway company, io have classified all of such material as loose rock. In short, the contract must he interpreted in a reasonable manner, with a due regard for the rights of both parties, and with a proper appreciation of tlie nature and magnitude of the undertaking, and the difficulties encountered in applying the plowing test to the subject-matter. In the light of such considerations as these, the specifications will not admit of the construction that it was tlie duty of the engineers to draw a rigid line, under all circumstances, between earth and loose rock, and to classify a given material as all loose rock, unless a six-horse team was able to plow therein continuously, from day to day, and to turn a full ten-inch furrow. As the contract did not define what should be esteemed plowing, or describe to what extent it should be impossible to plow with six horses, to entitle the contractor to loose rock classification, there was a grave difficulty in applying the force test to much of the material, and upon the whole I am satisfied that the engineers properly solved that difficulty in accordance with the spirit of the agreement by allowing a given percentage of loose rock, basing the percentage upon their observation of bow the material was handled, and the difficulties actually encountered in moving it. This conclusion is fortified by the fact that these plaintiffs did not object to the method of classification by percentages while the work was in progress. Such objections as they made were to the amount of the allowance, rather than to the method by which it was ascertained. Finally, while expressing
Fourth. Having announced some general propositions in accordance with which the court has considered the evidence, I may as well say -at the outset that there is very little testimony in the case tending to show that any of the engineers in charge of the work intentionally "underestimated it. I am well satisfied, and accordingly find, that the chief engineer and his assistants intended to deal fairly with the contractors, and that in making measurements, computations, and classifications for the final estimate they aimed to allow them all that was due under the terms of the contract as they construed it.
Fifth. The evidence in the case fails to satisfy me that there are any substantial errors in the measurements or calculations as made by the engineers. By this I mean to say that the gross contents of the excavations and embankments, the total haul and overhaul, and the total amount of clearing, grubbing, and close chopping, seem to have been ascertained with substantial accuracy. At all events, the testimony is insufficient, at this late day, co warrant a contrary conclusion. Nor has it been shown to the satisfaction of the court that the engineers failed, through oversight or otherwise, to measure or estimate any work that was actually done by the plaintiffs.
■Sixth. In view of the unsatisfactory character of the testimony, I have not felt at liberty to allow any of the claims for extra work. I can only take time to mention a few of the more important items of this kind.
(a) The rock ditch on section 192 was a part of the contract work, and was properly estimated and paid for at contract rates. It was a hard job, and the contractors undoubtedly lost money on the work; but the court cannot, for that reason, allow the claim.
("b) I have found it impossible to determine from the testimony before me how much material was handled in the spring of the year 1888 in filling up and finishing the house track at Revere station. It is most probable, I think, that the final estimate was based on measurements that included that work; and that it was work necessary to be done to complete the contract.
(c) With reference to the claim for cárrying and piling up rock ballast on section 193, it will suffice to say that the railway company paid rock prices for the excavation and haul, and the evidence leaves it uncertain whether any piling was in fact done, or whether it was merely dumped from cars.
(d) The company seems to have made the contractor an allowance for the broken rock placed in cut No. 2 to bring it up to grade, and I am unable to say that the allowance for that work was inadequate.
“The classifications which you give for cuts on sec. 187 to 191 are, we think, uniformly too low; much lower than classifications elsewhere on the work. To these we wish to cali your particular attention.”
Then, alter suggesting a considerable increase in the classification of certain cuts, (which was not allowed,) they say of the proposed increase, this “is as low as we think any competent and lair man who saw the work done would put them. * * * This part of the work was distant from Mr. Lamborn’s office, and not often soon by him in its progress.” McArthur Bros, appear to have been fair-minded men, and to have acted very impartially in the course of all tho disputes that arose concerning questions of classification. They had also had large experience in railroad construction, and were thoroughly conversant with the subject to which they alluded. 1 am satisfied that they expressed their honest convictions in the paragraphs of the letter above quoted, and their views under the circumstances are entitled to great weight. The result has been that the court has determined to raise the classification
On cut 5 to 60 per cent, of the total contents of the cut. « ^0 it. « 41 Ct 44 44 44 44 44 44 ^0 44 44 44 44 41 44 44 44 44 44 00 41 44 44 44 44 44 44 44 44 44 4Q 44 44 44 44 44 44 44 44 44 "50 ** W ** ** ** M 44 44 44 00 44 04 44 44 44 44 44 44 44 9 10 .11 13 14 & 15 16
The other cuts were estimated with substantial accuracy and fairness. The court has taken Mr. Brooker’s estimate of the total contents of these cuts, and has ascertained the amount already paid according to the old classification, and has also computed the amount due according to the new classification. The sum due is found to be $3,578.19, for which amount and interest from the time this suit was brought a lien is allowed.