LEWIS ELECTRIC CO., Appellee, v. Ronald E. MILLER and Kathleen F. Miller, Appellants.
No. 08-2008.
Supreme Court of Iowa.
Dec. 17, 2010.
792 N.W.2d 691
TERNUS, Chief Justice.
We have taken this breach-of-contract matter on further review to consider the contention of appellee, Lewis Electric Co., that the court of appeals’ instructions on remand require further clarification. See Anderson v. State, 692 N.W.2d 360, 363 (Iowa 2005) (“On further review, we can review any or all of the issues raised on appeal or limit our review to just those issues brought to our attention by the
I. Background.
Lewis Electric is an electrical contractor in Sioux City. Miller owns The Tool Depot, a store with locations in Sioux City and Le Mars. At various times during 2003 and 2004, Lewis Electric provided electrical services on a time-and-material basis in Miller‘s Sioux City store, billing Miller $4164.53 for this work. In 2003, Miller hired Lewis Electric to perform electrical work in the Le Mars store, which was in the process of opening. The parties’ agreement as to the scope of this work was set forth in two bid documents. Lewis Electric was to be paid $49,200 for this work. After Miller had paid Lewis Electric $30,000 for electrical services at the Le Mars store, a dispute over Lewis Electric‘s performance arose. This dispute primarily involved the number of light fixtures to be installed and the foot-candles the fixtures would provide.
The parties attempted to resolve their dispute. As a result of these efforts, Lewis Electric deducted a small amount from the remaining balance on the contract price for work it conceded it did not do, bringing the amount it claimed under the contract to $18,871.64.
When the parties could not reach a full resolution of their dispute, Lewis Electric brought a breach-of-contract action seeking payment of $4164.53 for the services performed at the Sioux City store and $18,871.64 for services rendered at the Le Mars store. Miller asserted that no money was owed on the Le Mars account because Lewis Electric‘s work was defective. In addition, Miller filed a counterclaim under a breach-of-contract theory, seeking recovery for the cost of repairs to Lewis Electric‘s defective work at the Le Mars store. Miller did not dispute the work or amount owed with regard to the Sioux City store.
At the bench trial of this action, Lewis Electric presented evidence in support of its breach-of-contract damages. Likewise, Miller submitted evidence of its damages, specifically that it had paid $4045.15 for engineering services to design a fix for Lewis Electric‘s defective work and $18,930 for electrical installation services to make the fix, for total damages of $22,975.15.
The district court found that Lewis Electric had not breached the Le Mars contract. Accordingly, it awarded damages to Lewis Electric on its claim and denied Miller‘s counterclaim. With respect to the Le Mars contract, the district court reduced Lewis Electric‘s damages from $18,871.64 to $16,927.50 to reflect additional work the court found Lewis Electric had not performed. The court also entered judgment in favor of Lewis Electric on the Sioux City account in the sum of $4164.53.
Miller appealed, challenging only the rulings with respect to the Le Mars contract.2 Miller claimed there was not sub-
The portion of the judgment for the Sioux City account, separate from the Le Mars account, is affirmed in the sum of $4164.53. The remainder of the judgment ($16,927.50) is vacated, and the matter of the Le Mars account and the defendant‘s counterclaim is reversed and remanded for resolution. We assess appellate court costs one-half to Miller and one-half to Lewis Electric.
Lewis Electric seeks further review of the court of appeals’ decision on two grounds. First, Lewis Electric contends it was error to reverse, as there was substantial evidence supporting the district court‘s judgment with respect to the Le Mars contract. Second, Lewis Electric contends the instructions on remand were insufficiently specific in that they did not direct the action to be taken by the district court to resolve the parties’ claims on remand. As stated above, we have taken the case to consider the second ground.
II. Analysis.
As stated above, the district court found that Lewis Electric had substantially performed its contract with Miller, with the exception of a few minor deviations that the court deducted from the contract price. See Farrington v. Freeman, 251 Iowa 18, 23, 99 N.W.2d 388, 391 (1959) (“[W]here substantial performance has been proven by the builder, he is entitled to his contract price less deduction for the value of any defects in performance.“). The court of appeals held there was not substantial evidence to support the trial court‘s factual finding that Lewis Electric did not breach the Le Mars contract. Although not expressly stated in its opinion, the court of appeals held, in essence, that the record showed as a matter of law that Lewis Electric did not substantially perform the Le Mars contract due to its defective performance.3 To address the appropriate scope of the remand ordered by the court of appeals, it is necessary to understand the rules governing recovery under the circumstances presented here.
We begin with the potential recovery by Lewis Electric for its performance under the contract. Due to the court of appeals’ reversal of the district court‘s finding of substantial performance, Lewis Electric may not recover under “the general rule”
that a contractor who substantially performs under a building or construction contract is entitled to recover the contract price minus the cost of repairing the defects or completing the unfinished part of the work so as to bring the construction up to the level required by the contract.
24 Richard A. Lord, Williston on Contracts § 66:14, at 448-51 (4th ed. 2002) (noting any recovery under this rule is “subject to the qualification that the contractor cannot recover more than the contract price“) [hereinafter Williston on
Of course, recovery by Lewis Electric will occur only if the remaining contract price is greater than Miller‘s cost of completing or remedying Lewis Electric‘s work. If Miller‘s damages4 exceed the remaining contract price of $19,200, Miller will be entitled to a judgment in the amount of that excess. See Conrad v. Dorweiler, 189 N.W.2d 537, 540-41 (Iowa 1971) (applying rule that “party left with an uncompleted contract could secure its completion and recover from the wrongdoer the reasonable cost of finishing the work in excess of the original contract price“); Restatement (Second) of Contracts § 347, at 112 (1981) (“[T]he injured party has a right to damages ... measured by (a) the loss in the value to him of the other party‘s performance caused by its failure or deficiency, plus (b) any other loss ... caused by the breach, less (c) any cost or other loss that he has avoided by not having to perform.“) [hereinafter Restatement];5 Restatement § 348(2)(b), at 119-20 (“If a breach results in defective or unfinished construction ... [the injured party] may recover damages based on ... the reasonable cost of completing performance or of remedying the defects if that cost is not clearly disproportionate to the probable loss in value to him.“);6 Williston on Contracts § 66:17, at 462 (“If the defect causing the breach is remediable from a practical standpoint, recovery generally will be based on the market price of completing or correcting the performance, minus the unpaid part of the contract price.“).
III. Disposition.
We affirm the court of appeals’ decision with the following specific instructions. Upon remand, the district court shall enter judgment for Lewis Electric on its Sioux City contract claim in the sum of $4164.53, plus interest and costs. The court shall also determine Miller‘s damages resulting from Lewis Electric‘s breach of the Le Mars contract, and enter judgment in favor of Lewis Electric on its Le Mars contract claim or in favor of Miller on its counterclaim, depending on whether Miller‘s damages exceed the remaining contract price of $19,200.8
The court of appeals ordered that the costs on appeal be taxed one half to Lewis Electric and one half to Miller.
DECISION OF COURT OF APPEALS AFFIRMED AS MODIFIED; DISTRICT COURT JUDGMENT REVERSED, AND CASE REMANDED.
Notes
A contracts to build a house for B for $100,000, but repudiates the contract after doing part of the work and having been paid $40,000. Other builders would charge B $80,000 to finish the house, but B finds a builder in need of work who does it for $70,000. B‘s damages are limited to the $70,000 that he actually had to pay to finish the work less the $60,000 cost avoided or $10,000, together with damages for any loss caused by the delay. See Illustration 2 to § 348.
Restatement § 347 cmt. e, illus. 12, at 116.A contracts to build a house for B for $100,000 but repudiates the contract after doing part of the work and having been paid $40,000. Other builders will charge B $80,000 to finish the house. B‘s damages include the $80,000 cost to complete the work less the $60,000 cost avoided or $20,000, together with damages for any loss caused by delay. See Illustration 12 to § 347.
Restatement § 348 cmt. c, illus. 2, at 121-22.