delivered the opinion of the court:
Aрpellant contends that by pleading to the declaration after the demurrer was overruled the appellee waived all objection to the declaration; that the sufficiency of the declaration was conclusively determined by the judgment overruling the demurrer to it, аnd that the question of the limitation in the contract could not again be raised by plea. In actions at law it is not in accordance with the rules of pleading for the plaintiff to anticipate and attempt to answer or avoid a possible defense that might be interposеd by plea. He is only required to state his cause of complaint, and anything beyond this is surplusage. That a cause of action is barred by limitation, whether the limitation is by contract or by act of the legislature, is a defense which may or may not be interposed. Although it may appeаr on the face of the declaration that the cause of action ■is barred if that defense is interposed, yet at law, if it is not relied upon as a defense by pleading it specially, it can not be taken advantage of by the defendant, the plaintiff not being required to negаtive the defense in his declaration, as is the rule in chancery. If he does so, such allegations, not being necessary to the statement of his cause of action, are to be treated as surplusage, but as a general rule the declaration will not on that account bе obnoxious to demurrer, (1 Chitty’s Pl. 230; Stephen’s Pl. 422; Higgins v. Halligan,
We do not think the judgment overruling the demurrer to the declaration was an adjudication that the allegations in the declarаtion were a good and sufficient answer to a defense that the cause of action was barred by limitation under the contract. The proper way to have presented the sufficiency of the matter relied on in avoidance would have been by replication tо the plea setting up that defense. But we are of opinion that the allegations relied on in the declaration, if they had been set up in a replication to the plea, would not have been sufficient. This is the question to which the briefs of both sides are mainly devoted.
Appellant contends that the bond of appellee is to be treated as a contract of insurance and construed strictly against the appellee. This position is correct. This court is committed to the rule that where a contract of insurance leaves room fоr construction, courts are inclined against the construction that will impair the indemnity. If the contract is susceptible of two interpretations, the interpretation most favorable to the assured will be adopted. ( Terwilliger v. Masonic Accident Ass.
Johnson v. Humboldt Ins. Co.
The Supreme Court of Wisconsin, in Hart v. Citizens’ Ins. Co. 21 L. R. A. 743, adopts the same rule announced in the Johnson case, and cites numerous cases supporting the decision as well as cases adopting a contrary rule. After stating the reasoning of thе cases holding the contrary view the Supreme Court of Wisconsin said: “We cannot assent to this line of reasoning. It does violence to plain words. It smacks too strongly of making a contract which the parties did not make. It construes where there is no room for construction. Plаin, unambiguous words which can have but one meaning are not subject to construction. ‘Twelve months next after the fire’ has one certain meaning, and but one. It can have no other.”
’ If there was no room left for construction in the Johnson case there certainly can be none in this case.
Appellant further contends that the clause limiting the right to bring suit to March 15, 1903, is unreasonable, and on that ground should be held invalid and void. It is not denied that the parties to a contract may fix a different time within which suit may be brought thereunder from that fixed by the g'eneral Statute of Limitations. The аrgument made in support of this last contention of appellant is, that the time limited for bringing suit expired several months before the building was completed; that appellant could not know the amount and extent of his damages resulting from failure to comply with the contract until the building was completed, and the provision that required him to bring suit before that time, if binding, defeated the object for which the bond was given and was therefore unreasonable and invalid; also, that appellánt could not know until the time arrived at which all his damages were ascertainable, that Sсhleuter would not pay them. The period of limitation began to run from the breach of the contract, which was the failure of Schleuter to complete the building December 15, 1902, and a right of action accrued to appellant at that time. He might at any time thereafter, bеfore March 15, 1903, have instituted suit on the bond and have had his damages assessed at the amount that had accrued up to the time of the trial, whether such damages accrued before or after March 15. The bond did not limit the liability of the appellee to such damages as accrued prior to March 15 resulting from the failure to comply with the contract, but only required that suit be brought before that date.
Section 35 of the Practice act is as follows: “In actions brought on penal bonds, conditioned for the performance of covenant, the plаintiff shall set out the conditions thereof, and may assign in his declaration as many breaches as he may think fit; and the jury, whether on trial of the issue or of inquiry, shall assess the damages for so many breaches as the plaintiff shall prove, and the judgment for the penalty shall stand as a security for such other breaches as may afterwards happen, and the plaintiff may, at any (time) afterwards, sue out a writ of inquiry to assess damages for the breach of any covenant or covenants contained in such bond, subsequent to the former trial or inquiry; and whenever execution shall be issued on such judgment, the clerk shall endorse thereon the amount of damages assessed by the jury, with the costs of suit, and the sheriff or coroner shall only collect the amount so endorsed: Provided, that in all cases where a writ of inquiry of damages shall be issued for any such breaches, subsequent to the first trial or inquiry, the defendant, or his agent or attorney, shall have at least ten days’ notice, in writing, of the time of executing the same.”
In Dent v. Davison,
It is clear from these decisions that the appellant had a complete and adequate remedy for the recoveiy of all damages sustained -by him on account of the breach of the contraсt for the erection of his" building notwithstanding all damages sustained might not have accrued within the time he was required to bring his action. Under such circumstances it cannot be said the provision requiring him to bring suit before March 15, 1903, was unreasonable and invalid.
In our opinion there is no error in this record, and the judgment of the Appellate Court is affirmed.
Judgment affirmed.
