Aрpellant, A.P. Leonards d/b/a Carabeef Ranch (Leonards), appeals an order of the Benton County Chancery Court awarding a money judgment to appellee, E.A. Martin Machinery Company (Martin Machinery), for repairs Martin Machinery made to Leonards’s bulldozer. Martin Machinery cross-appeals from that part of the order deсlaring the repairmen’s lien statutes, Ark. Code Ann. §§ 18-45-201 to -207 (1987), unconstitutional as violative of both federal and state due process provisions set forth in U.S. Const, amend. 14 and Ark. Const, art. 2, § 8, respectively. Jurisdiction of this case is properly in this court as the constitutionality of a statute is questioned. Ark. Sup. Ct. R. l-2(a)(3).
BACKGROUND FACTS
Testimony at trial revealed the following facts. In November 1992, Leоnards contacted Martin Machinery concerning possible repairs to Leonards’s 1965 model Caterpillar D8H bulldozer. Joe Bill Morris, then a field service mechanic for Martin Machinery, went to Carabeef Ranch and began discussing the bulldozer’s problems with both Leonards and the ranch foreman, Jim Williamson. Morris suggested the bulldozer be transported to Mаrtin Machinery’s shop so the repairs could be done there. The bulldozer was transported to the shop where Martin Machinery made repairs to it for which Leonards was billed in the sum of $19,284.53.
Leonards questioned the amount of the bill as he thought it exceeded the current value of the bulldozer. Testimony from three witnesses placed the value of the bulldozer between $14,000.00 and $20,000.00. Leonards and Martin Machinery unsuccessfully attempted to reach a compromise on the repair bill. Pursuant to sections 18-45-201 to -207, Martin Machinery sent Leonards a notice dated July 9, 1993 of its intent to sell the bulldozer at public sale on July 31, 1993.
On July 30, 1993, Leonards initiated this suit by filing a petition in chancery court to enjoin the sale. Martin Machinery refrained from the sale, but answered the complaint in equity and counterclaimed for the amount of its repair bill, attorneys’ fees, costs, and interest. In its answer, Martin Machinery asserted it was maintaining possession of the bulldozer in accordance with the repairmen’s lien authorized in section 18-45-201. Leonards amended his petition twice to include a request that the repairmen’s lien statutes be declared unconstitutional, a request for damages for lost use and wrongful possession of the bulldozer, and a request for damages for Martin Machinery’s negligence in failing to advise Leonards of the costs of the repairs and in making the repairs without authorization from Leonards. A Deputy Attorney Gеneral for the State of Arkansas notified the trial court of the Attorney General’s receipt of Leonards’s second amended complaint as required by Ark. Code Ann. § 16-lll-106(b) (1987), and informed the trial court that the Attorney General would not participate in the defense of the constitutionality of the repairmen’s lien statutes.
After trial, the chancellоr entered an order finding the repairmen’s lien statutes unconstitutional, but dismissing Leonards’s claims for damages. In addition, the chancellor awarded Martin Machinery attorneys’ fees, interest, and the amount of the repair bill less $750.00 for unjustified expenses. The order did not address the issue of possession of the bulldozer.
Leonards’s appeal and Martin Maсhinery’s cross-appeal followed the entry of the trial court’s order. We consider the cross-appeal first, as resolution of that question determines the need to address certain issues raised on direct appeal. See Nabholz Constr. Corp. v. Graham,
CROSS-APPEAL
Martin Machinery challenges the trial court’s finding that the repairmen’s lien statutes are unconstitutional as violative of the due process clauses in the United States and Arkansas Constitutions. The trial court ruled the repairmen’s lien statutes violated both state and federal due process provisions because they did not provide the property owner with a right of replevin or conversion, or a hearing, or a right to pоst bond in order to obtain possession prior to the sale. In ruling the repairmen’s lien laws unconstitutional, the trial court relied on Flagg Brothers, Inc. v. Brooks,
Martin Machinery makes several arguments on cross-appeal of which we consider only that concerning state action, as reversal is required on that point. Martin Machinery cites Flagg Bros.,
In the context of fedеral due process analysis, the issue of state action is well-settled in the area of state statutes on creditor’s remedies and similar statutes. Citing with approval its decision in Flagg Bros.,
Therefore, we hold that, with respect to the application of federal due process analysis to this case, no state action has occurred, thus the deprivation of Leonards’s property interest is not protected by the Fourteenth Amendment. While ownership is a significant interest in property, Mitchell v. W.T. Grant Co.,
Turning now to consideration of the state action issue in the context of due process under the Arkansas Constitution, we begin with this court’s determination of state action in South Central Dist. of the Pentecostal Church of God of America, Inc. v. Bruce-Rogers Co.,
When engaging in state due process analysis, this court has used a balancing test of competing interests somewhat similar to the federal test enunciated in Mathews v. Eldridge,
First, the deprivation must be caused by the exercise of some right or privilege created by the State or by a rule of conduct imposed by the State or by a person for whom the Statе is responsible.... Second, the party charged with the deprivation must be a person who may fairly be said to be a state actor. This may be because he is a state official, because he has acted together with or has obtained significant aid from state officials, or because his conduct is otherwise chargeable to the Stаte.
Id. The second requirement of the foregoing test has not been met in this case. We therefore conclude no state action was taken in this case, and the trial court erred in holding the repairmen’s lien laws at issue here were unconstitutional as violative of the due process clause of the Arkansas Constitution.
On cross-appеal, we reverse and dismiss the trial court’s decision declaring the repairmen’s lien laws unconstitutional on both state and federal due process grounds.
DIRECT APPEAL
Leonards alleges four points of error on direct appeal. We find no error and affirm the judgment on direct appeal.
For his first point of error, Leonards contends the trial court еrred in not awarding him damages for wrongful detention of the bulldozer after declaring the repairmen’s lien statutes unconstitutional. This point is premised upon the trial court’s erroneous finding that the lien statutes are unconstitutional. Our holding on cross-appeal that the lien statutes are indeed constitutional therefore renders moot any claim by Leonards for wrongful detention of the bulldozer. With few exceptions not applicable here, we do not address moot issues. Wright v. Keffer,
Second, Leonards challenges the amount of damages awarded to Martin Machinery on its counterclaim. Leonards contends the trial court erred in finding the amount of the repair bill to be fair and reasonable and in awarding Martin Machinery the amount of the repair bill rather than the amount by which the repairs increased the market value of the bulldozer.
Relying on Hawkins v. Delta Spindle of Blytheville, Inc.,
[w]here labor or material is furnished by a party and no price is agrеed upon, the law will imply an agreement to pay what it is worth. If a contract makes no statement as to the price to be paid for services, the law invokes the standard of reasonableness and the fair value of the services is recoverable.
Id. at 834,
The burden was therefore on Martin Machinery to prove that the invoiced amount fоr which it sought recovery, $19,284.53, was the fair and reasonable value of the parts and labor furnished. Hawkins,
The trial court’s order specifically found the repair bill was reasonable and did not exceed the industry standard. The trial court awarded the amount of the bill, less $500.00 for credit on the sale of the existing radiator and less $250.00 for the markup on transportation costs. Based on the foregoing evidence, we conclude Martin Machinery satisfied its burden of proving the reasonableness of the value of its parts and labor and therefore cannot say the trial court’s findings were clearly erroneous.
Third, Leonards argues the trial court erred in not finding Martin Machinery negligent in failing to discuss costs or give an estimate. The trial court ruled Martin Machinery was not negligent in the way it handled this job, finding that Martin Machinery discussed the repairs with Leonards in person at Leonards’s ranch and twice by telephone, that Leonards had authorized the repairs, and that Leonards was experienced in business transactions and had done business with Martin Machinery previously. There is substantial evidence in the record to support these findings. Indeed, we need look no further than the testimony of Leonards himself to support the trial court’s findings. We cannot say the trial court was clearly erroneous in this regard.
Fourth, Leonards challenges the jurisdiction of the chancery court. Prior to appearing at trial in chancery court, Leonards filed a motion to transfer to circuit court. On appeal, Leonards argues he had an adequate remedy at law, although he never formally abandoned his request for an injunctiоn based on irreparable harm. Leonards never obtained a ruling on his motion to transfer and appeared at trial in chancery court without ever raising the jurisdictional objection again. Even assuming arguendo that Leonards’s complaint failed to state a ground for equitable relief, Martin Machinery supplied any defect by pursuing its lien in equity court pursuant to section 18-45-207(a). Nottingham v. Knight,
The judgment is affirmed on direct appeal and reversed and dismissed on cross-appeal.
Notes
Here we note that the United States Supreme Court has explained its summary affirmance in Sрielman-Fond, Inc. v. Hanson’s Inc.,
