Lenz Hardware, Inc. v. Board of EducationLenz Hardware, Inc. v. Board of Education
Memorandum: Supreme Court properly granted defendant’s motion for partial summary judgment dismissing the first and third causes of action of the complaint. Plaintiff commenced this action seeking damages for “extra” plumbing and electrical work it allegedly performed at the request of defendant’s construction manager and architect. Plaintiff requested payment for the extra work and, by letter dated February 21, 2001, the construction manager refused payment. By letter dated April 30, 2001, the architect refused payment and advised plaintiff that “[n]o further direction . . . will be given on this issue.” The construction manager ignored “claims” filed against it pursuant to the contract on May 18, 2001. Plaintiff did not serve a notice of claim on defendant until August 19, 2002.
Pursuant to
We reject plaintiff’s contention that defendant should be estopped from asserting a notice of claim defense. A school district may be estopped from asserting such a defense when, based on its activities, conduct, statements or writings, or those of its representatives, it “‘lulls a [plaintiff] into taking no action until after the statutory period for [service has] passed’” (Welsh v Gindele & Johnson, 50 AD2d 971, 972 [1975]; see also Matter of Daley v Greece Cent. School Dist. No. 1, 21 AD2d 976 [1964], affd 17 NY2d 530 [1966]). Here, plaintiff has not alleged that it was promised or led to believe that its claims would be viewed favorably and thus has failed to allege that it was lulled into taking no action until after the statutory period for service had passed.
We further conclude that the court properly denied the cross