645 F.2d 886 | Ct. Cl. | 1981
delivered the opinion of the court:
L’Enfant Plaza Properties’ claim arises under a 99-year lease by plaintiffs predecessor, as lessee, from the District of Columbia Redevelopment Land Agency (RLA), then an agency or instrumentality of the federal government,
I
The underlying land was owned by RLA and formed part of the development now known as L’Enfant Plaza in the District of Columbia. Plaintiffs lease provided for the L’Enfant Plaza company’s construction of a large combined hotel and office building, the "East Building” of the L’Enfant Plaza Complex. The necessary land was leased by RLA for a long period.
Between November 1965 and August 1969, GSA’s contractor, John McShain, Inc., built what is now the Housing and Urban Development (HUD) Building, on property adjoining plaintiffs to the east. During the course of that construction, McShain trespassed on the property involved here (under lease to plaintiff) by constructing a portion of the underground footings for the HUD Building on and near the edge of the leased property. In April 1971 RLA approved L’Enfant Properties’ revised final plans for construction of the East Building. These plans were prepared by plaintiff in partial reliance on GSA and RLA plans showing the footings of the HUD building as abutting, but
This contractor quickly discovered that the footings of the HUD Building had been built on L’Enfant Plaza Properties’ land. Those footings interfered with plaintiffs construction plans and caused it substantial damages and delays. Plaintiff sued McShain in the Superior Court for the District of Columbia and recovered part of its damages.
II
We first consider plaintiffs claims for breach of the lease agreement, unmixed with its separate allegations of fraud and misrepresentation. This is the sole burden of plaintiffs motion for partial summary judgment (see note 2, supra) and we have already rejected (see note 1, supra) the only argument against our jurisdiction of that purely contractual claim which is founded on duties said to flow from alleged express and implied warranties and covenants of title, from the pre-fixed procedure for plaintiffs obtaining of full unconditional possession of the property (which did not occur until the spring of 1971), and from alleged promises in the lease as to the fitness of the leased property for the construction of the improvements.
For this part of the case we assume arguendo, without deciding, that the lease can be read to contain some such covenants, warranties, and promises.
It is not easy to resolve this problem; the lease is not precise, one way or the other, in describing the risks and obligations of the parties with respect to this third-party trespass during the pre-building period. But there are certain lease provisions, and enough in the lease framework, to enable us to determine the limited issue before us.
First, the McShain trespass occurred, unknown to either party, during the period after the beginning of the lease but before the L’Enfant Plaza company received full possession of the land in 1971 and started to build. We do not believe that the company could (or was expected to) keep itself ignorant during that time of the things happening on the property it had formally leased in 1965 which could affect the construction of the large building plaintiff intended to build. On the contrary the natural understanding would be that the lease contemplated that plaintiff had both the right and the obligation to investigate the condition of the property in this 1965-1971 period. That was an important reason, in our view, why plaintiff was expressly granted full access to the leased property prior to full possession:
Access to Leased Property Prior to Vesting of Possession. Prior to the date Possession of the Leased Property is*6 Vested in the Redeveloper pursuant to this Agreement, the Agency [RLA] shall permit the Redeveloper access thereto whenever necessary to carry out the purposes of this Agreement; Provided, That the Redeveloper shall execute an appropriate "Save Harmless Agreement” with the Agency * * *. [Lease, § 202(f) (emphasis in original)].
In this specific situation — from the beginning there was expected to be a substantial period of time after plaintiff had leased the property for the very purpose of erecting the East Building but before it could actually start to build— the provision for full access appears to us to have contemplated that the company would concern itself with the matters which could interfere with its later erection of the building, and it could and would therefore investigate and inspect conditions on the property during that time. It follows, we think, that the L’Enfant Plaza firm would itself bear the risk of McShain’s hidden encroachments which could have been discovered by investigation and inspection but were not. Plaintiffs contention that the access provision was solely for its own option, whenever it chose to use it in its own full discretion —and that the provision has no other significance — disregards the natural expectation that a developer that leases property (to which it has access) on which it intends to build will try to make sure that the leased property is not misused to its detriment during the pre-building period. Whatever warranties and covenants on the part of RLA the lease may have contained did not cover these third-party encroachments on the property during the pre-vesting period, and did not protect plaintiff from its own failure (negligent or not) to discover those third-party interferences.
There has been no showing that plaintiff was ever prevented from entering and inspecting the property pursuant to the access clause; in fact plaintiff did enter and exercise possession over part of the leased premises before the 1971 vesting date. That entry took place in May 1969, and was for the purpose of beginning partial construction of the East Building footings in order to facilitate the District
In addition, plaintiff knew of the construction of the adjoining HUD Building and probably had even more reason than RLA to check the leased site during the pre-building time. That was the area on which it was to erect the East Building. Upon discovery of the encroachment, plaintiff could have attempted to act on its own,
Nor do we have any reason to believe that, whatever opportunity or duty plaintiff had to inspect the property, RLA had a superior chance to learn of McShain’s trespass. (The footings were underground.) Plaintiff does not allege RLA had actual notice of the encroachment, at least for purposes of this motion or of the non-tort claim we are now considering. See notes 2 and 6, supra, and Part III, infra. Instead, plaintiff argues that we should impute knowledge on RLA’s part either because of its governmental status, or because of its duties under the Area Project Coordination
in a business so vast as that engaged in by the United States Government, with its multitudinous departments, bureaus, and independent agencies, with various and sundry projects scattered all over the world, it is impossible for one department to know what another department is going to do. In such case it seems unreasonable to charge one agency with knowledge of what another is going to do. [145 Ct. Cl. at 391-92, 172 F. Supp. at 457].
See also, J. A. Jones Constr. Co. v. United States, 182 Ct. Cl. 615, 625, 390 F.2d 886, 891-92 (1968). Here, we see no ground for charging RLA with constructive knowledge of the activities of GSA’s contractor. RLA and GSA are independent entities and have no connection, outside of the fact that both agencies were involved with the urban renewal development of the L’Enfant Plaza complex. There is nothing to show that RLA was required to supervise or control the actions of GSA’s contractor, or that it was responsible for plaintiffs reliance on the supposed accuracy of building plans submitted by GSA to RLA.
In particular, the Area Project Coordination Agreement and the lease provisions relating to it are not sufficient to create the kind of close relationship between GSA and RLA under which it would be appropriate to impute to the latter any knowledge which the former might have had of McShain’s improper placement of the HUD Building footings. Under the Coordination Agreement and lease section 208(b), RLA’s duties dealt primarily with coordinating construction schedules between redevelopers pursuant to a "critical path schedule” such that various phases of building were accomplished in an orderly, time-efficient manner. Neither the terms of section 208(b) nor of the Coordination Agreement made RLA responsible to one redeveloper for the quality of work being done by another. It would be incorrect to construe the Coordination Agreement as extending over-all supervisory authority to RLA. Aside from the absence of any such provision, the Coordination Agreement was of limited duration and ended before construction
L’Enfant Properties’ own obligation to oversee the property and bear responsibility for it during the pre-building period was augmented by a lease condition that "[t]he Redeveloper shall not permit, commit, or suffer waste or impairment of the Leased Property, Air Rights, or the Improvements or any part thereof.” Lease §302. We agree with defendant that the most acceptable interpretation of this condition is that it was effective for the term of the lease (which pursuant to lease section 101 began in 1965) rather than just the time period after the 1971 vesting of full possession in plaintiff.
The special authority and obligations created and recognized in plaintiff by these access and waste-or-impairment clauses limit or negate any explicit or implicit covenants to put L’Enfant Properties in full, unqualified possession of the leasehold upon the signing of the Certificate of Vesting of Possession in May 1971.
Accordingly, we conclude that under the lease plaintiff must bear the risk of trespasses by third parties such as McShain during the pre-vesting period. For this reason plaintiffs motion for partial summary judgment must be denied and the Government’s cross-motion for summary judgment must be granted insofar as it relates to the indisputably contractual claim we have discussed in this Part.
Ill
The Government argues, in its cross-motion for full summary judgment, that the whole case must be dismissed because the remaining claims (not dealt with in Part II, supra) sound in tort (fraud, misrepresentation, and constructive fraud)
In certain circumstances, a case which is within the exclusive jurisdiction of the district courts but which is improperly filed in this court, may be transferred to a district court in which it could have been filed. 28 U.S.C. § 1506. This transfer statute is discretionary, however, and is available only when transfer is in the interest of justice. Id. We hold that transfer is not in the interest of justice although the district court has exclusive jurisdiction under the Federal Tort Claims Act. First, it has not been requested by either party, and second, it is unlikely that any purpose would be served by transferring those counts since there is little likelihood that they would succeed in the district court because of the bars of limitations and
For these reasons, plaintiffs motion for partial summary judgment is denied and defendant’s motion for full summary judgment is granted. The petition is dismissed.
In L’Enfant Plaza Properties, Inc. v. United States, 209 Ct. Cl. 727 (1976), this court held, in this caáe, that, for the times relevant here, the RLA would be considered a federal entity the contracts of which may be vindicated in this court.
For its motion, plaintiff relies solely on its undiluted warranty and promise claims, and does not stand on its allegations of fraud and misrepresentation, about which, even on plaintiffs view, there are disputed issues of fact. Defendant claims that these fraud and misrepresentation claims sound in tort and are outside our jurisdiction. See Part III, infra.
These are the undisputed facts relevant to the cross-motions for summary judgment.
The lease also gave plaintiff an option to purchase fee simple title to the land on or before the fifteenth anniversary of the completion of the East Building. Lease § 1001(b).
The decision was affirmed on appeal in John McShain, Inc. v. L’Enfant Plaza Properties, Inc., 402 A.2d 1222 (D.C.C.A. 1979).
The Government seems to deny that there were any such warranties, covenants, or promises at all, but merely representations at most, and there has been much argument on these points. For the purpose of the present motions we assume, in general, the plaintiffs characterization of the portions of the lease agreement on
We are also required to assume that RLA was wholly unaware of McShain’s trespass. In its motion plaintiff has made no showing to the contrary and, indeed, assumes (for present purposes) RLA’s total unawareness of McShain’s improper activity with respect to the footings of the HUD building. See note 2, supra.
The conventional rules on warranties and covenants of title, as well as the duty to place a tenant into unconditional possession of the leased property, recognize the primacy of the lease terms over the rules which could apply where "the lease is silent on the point.” See Keydata Corp. v. United States, 205 Ct. Cl. 467, 480, 504 F.2d 1115, 1122 (1974). Cf. Algonac Mfg. Co. v. United States, 192 Ct. Cl. 649, 673, 428 F.2d 1241, 1255 (1970). There are, in addition, no statutory provisions which would preclude RLA from entering into a lease which imposed the risk and burden of a third-party’s pre-vesting trespasses on the L’Enfant Plaza company’s land.
We repeat that none of the alleged warranties, covenants, and promises, explicit or implicit, deals specifically with the particular problem before us — and that each of them can (and we think should) be read, in the light of other parts of the lease and of the arrangement’s basic framework, as excluding the present situation.
While plaintiff argues that it would have had no rights as against a trespasser on the leased property prior to the vesting of possession in 1971, we are not convinced that this is a correct statement of applicable law. See, e.g. D.C. Code § 16-1101 et seq. (ejectment action).
There is no language limiting this clause to post-1971 waste or impairment, and since plaintiff had access to the property prior to 1971 through lease section 202(f), the access clause discussed supra, it had the means to carry out its duties under section 302 (the waste-or-impairment clause) throughout the full lease term.
Other provisions of the lease also lend some support to defendant’s position that the parties agreed between themselves to divide up certain other risks rather than to make RLA fully liable for all risks occurring before the 1971 vesting of possession. See, e.g., Lease §§ 403 (indemnification for damages), 404 (reimbursement for legal expenses), 812 (excusable delays). Plaintiff says that these provisions are not applicable to the instant case, but whether or not this is so the existence of these provisions shows that the parties agreed to a sharing of various risks.
These claims are that RLA actually knew or should have known of McShain's improper activities but did not tell or inform plaintiff.
Since we hold for defendant on this ground, we need not reach the argument that these claims must also fail because they are the torts of an independent contractor of the Government for which the Government is not liable.