Lead Opinion
Plaintiff corporation, a licensed electrical contractor, brought this action for reformation of a contract with defendant county, and it appeals from a judgment for defendant after the sustaining of a general demurrer without leave to amend.
The allegations of the complaint may be summarized as follows; Plaintiff submitted a bid for $172,421 for electrical work to be done at the county hospital. This bid was found to be the lowest, and, when defendant announced that the bids of other contractors ranged from $197,500 to $222,700, plaintiff realized that some material mistake had been made
Two questions are presented on this apрeal. Does the complaint allege sufficient facts to entitle plaintiff to reformation? Did the court err in sustaining the demurrer without leave to amend 1
Once opened and declared, plaintiff’s bid was in the nature of an irrevocable option, a contract right of which defendant could not be deprived without its consent unless the requirements for rеscission were satisfied. (M. F. Kemper Const. Co. v. City of Los Angeles,
Beformation may be had for a mutual mistake or for thе mistake of one party which the other knew or suspected, but in either situation the purpose of the remedy is to make the written contract truly express the intention of the parties. Where the failure of the written contract to express the intention of the parties is due to the inadvertence of both of them, the mistake is mutual and the contract may be revised on the application of the party aggrieved. (See e. g. Mills v. Schulba,
In the furtherance of justice great liberality should be exercised in permitting a plaintiff to amend his complaint, and it ordinarily constitutes an abuse of discretion to sustain a demurrer without leave to amend if there is a reasonable possibility that the defect can be cured by amendment. (Wennerholm v. Stanford University School of Medicine,
Plaintiff had a remedy, which it chose not to exercise, that would have relieved it of any hardship that could result from its error. Howevеr, instead of rescinding, plaintiff, with full knowledge of its mistake, proceeded to perform the contract, and it cannot now compel defendant to pay the amount which it claims it intended to bid or obtain recovery on a quasi contractual basis as if no contract existed. Such a result would not only be contrary to settled legal principles, but it would also create uncertainty and confusion in the field of competitive bidding.
The judgment is affirmed.
Carter, J., Traynor, J., Spence, J., and McComb, J., concurred.
Notes
Seetion 3399 of the Civil Code reads: “When, through fraud or a mutual mistake of the parties, or a mistake of one party, which the other at the time knew or suspected, a writtеn contract does not truly express the intention of the parties, it may be revised, on the application of the party aggrieved, so as to express that intention, so far as it can be done without prejudice to rights acquired by third persons, in good faith and for value.”
Dissenting Opinion
Dissenting.—This case is before us on appeal from a judgmеnt of dismissal after the sustaining of a general demurrer without leave to amend. As stated in the majority opinion, “In the furtherance of justice great liberality should be exercised in permitting a plaintiff to amend his complaint, and it ordinarily constitutes an abuse of discretion to sustain a demurrer without leave to amend if there is a reasonable possibility that the defect can be cured by amendment. [Citations.] ” Nevertheless, the majority opinion, with unjust strictness rather than with liberality, refuses to permit plaintiff the opportunity to amend and forecloses plaintiff from any remedy for a mistake of which (it must be conceded for the purpose of this appeal) defendant sought to take advantage although, as alleged by plaintiff, defendant knew that the mistake occurred under circumstances which made it the result of excusable inadvertence and not the result of neglect of a legal duty.
In my opinion plaintiff has alleged facts sufficient to show that it might unambiguously state a cause of aсtion on the one hand for recovery on a contract at a corrected figure or on the other hand for the reasonable value of the work and materials furnished. Plaintiff’s allegations, tested by the general demurrer, are sufficient to show that no express contract was formed at the mistaken figure stated in the bid; that with
Plaintiff has alleged particular facts by which it attempts to bring the case within the provision of section 3399 of the Civil Code that “When, through ... a mistake of one party, which the other at the time knew or suspected, a written contract does nоt truly express the intention of the parties, it may be revised on the application of a party aggrieved, so as to express that intention . . . ”; i. e., an intention, plaintiff argues, to contract at a corrected figure. Plaintiff should have been allowed an opportunity to have made its complaint clear either by allegations showing such intention and removal from the complaint of the more general—and possibly immaterial—allegation that “there has been no meeting of the minds of plaintiff and defendant,” or by allegations showing a quasi-contraetual cause of action; i. e.: when defendant, knowing plaintiff’s bid excusably expressed a mistаke, attempted to accept the bid and form, and unjustly profit by, a contract based on the erroneous figure stated in the bid, no contract was formed at that figure; nor was a contract formed at the figure to which plaintiff subsequently attempted to correct the bid, for that figure was not known to defendant at the time it purpоrted to accept the bid; since no contract was formed at either figure but since it is manifest in equity and good conscience that defendant should pay for the work and materials which it accepted the law implies a promise to pay their reasonable value.
On the basis of plaintiff’s allegations it does not аppear that it should be adjudged, by upholding the dismissal after the sustaining of the general demurrer without leave to amend, that plaintiff could not state any cause of action. I would reverse the judgment.
Dissenting Opinion
I dissent.
On the undisputed facts of the ease section 3399 of the Civil Code was properly invoked by the plaintiff and it is entitled to relief by reformation. The record shows that on January 19, 1954, the board of supervisors of the defendant county opened bids for electrical work in connection with
On January 22,1954, thrеe days after the bids were opened, the plaintiff informed the board of supervisors by letter of an error as to one item. This item was mistakenly listed as $104.52 when it should have been $10,452. The plaintiff submitted to the board its work sheets and machine tapes indicating the mistake in the placing of the decimal point. The error was brought to the cоunty’s attention immediately after the plaintiff became aware of it and an earnest and diligent effort was made to have the county recognize the error and approve its correction. Had the correction been made as requested the plaintiff would still have been the lowest bidder. Nevertheless, on Februаry 2d, the board by resolution accepted the erroneous bid.
By the present action, commenced within 22 days after the action of the board of supervisors in accepting the erroneous bid, the plaintiff sought a reformation of the contract. It has in good faith performed the contract in compliance with the demands of the county. It is conceded that section 3399 of the Civil Code is controlling. That section provides in part: “When, through . . . mistake of one party, which the other at the time knew or suspected, a written contract does not truly express the intention of the parties, it may be revised, on the application of a pаrty aggrieved, so as to express that intention, so far as it can be done without prejudice to rights acquired by third persons, in good faith and for value.” The rights of third parties were not involved.
The court holds that the purpose of reformation is to effectuate a common intention of both parties. But this is not its sole purpose. Another just as сlear and distinct purpose is to permit “revision,” which is “reformation” when there is a mistake of one party which is known to the other at the time the contract comes into being, and in this case that was when the plaintiff’s bid was accepted on February 2d. Both parties knew of the mistake as early as January 22d.
It may be assumed that if аn inadvertent error is discovered by one party after the contract is executed, and is not known to the other party prior thereto, reformation would not lie. (Bailard v. Marden,
The result оf the court’s decision is that the action of the defendant is condoned in compelling the plaintiff to accept $104.52 for $10,452 worth of work and materials furnished and under circumstances which should have impelled the board to grant the request of the plaintiff to correct the error. As shown the mistake consisted in the clerical еrror as to one item of placing the decimal point two places to the left, making a difference on its face of over $10,000. The request was promptly made and was so obvious from the work sheets produced by the plaintiff that no possible prejudice could have resulted to the county inasmuch as with the item as сorrected the plaintiff was still the lowest bidder.
There can be no question but that the plaintiff has a cause of action for reformation under section 3399 of the Civil Code. It should not be foreclosed from amending the complaint. The Kemper case (M. F. Kemper Const. Co. v. County of Los Angeles,
If the facts alleged were applied to a controversy bеtween private parties the defendant would not under the circumstances here shown be justified in retaining the benefit of over $10,000 worth of materials and services without paying for them. The fact that the defendant in this case happens to be a public entity should not clothe it with immunity in perpetuating such an injustice as is here permitted. (See Farrell v. County of Placer,
Appellant’s petition for a rehearing was denied July 5,1956. Shenk, J., and Schauer, J., were of the opinion that the petition should be granted.
