LEISURE RESORTS, INC., Petitioner, v. FRANK J. ROONEY, INC., Respondent.
No. 82578.
Supreme Court of Florida.
April 27, 1995.
654 So. 2d 911
WELLS, Justice.
James E. Glass and Linda Dickhaus Agnant of James E. Glass Associates, Miami, for respondent.
R. Earl Welbaum of Welbaum, Zook & Jones, Coral Gables, amicus curiae for The Associated Gen. Contractors of America.
WELLS, Justice.
We have for review the following question certified to be of great public importance:
WHETHER THE PROVISIONS OF SECTION 718.203(2), FLORIDA STATUTES (SUPP. 1992), IMPOSE ON A CONTRACTOR AN IMPLIED WARRANTY OF FITNESS FOR THE INTENDED USE AND PURPOSE WHERE THE CONTRACTOR WITHIN THE CONTEMPLATION OF THE CONTRACT DOCUMENTS SUGGESTS AND SUPPLIES A MANUFACTURED ITEM SUCH AS INDIVIDUAL AIR CONDITIONING UNITS TO A DEVELOPER FOR USE IN A BUILDING PROJECT, WHERE SUCH ITEMS LATER PROVE NOT TO BE FIT FOR THE SPECIFIC PURPOSE FOR WHICH THEY WERE SUPPLIED?
Frank J. Rooney, Inc. v. Leisure Resorts, Inc., 624 So. 2d 773, 779 (Fla. 4th DCA 1993). We have jurisdiction.
Leisure Resorts, a developer, retained an architect who in turn retained an engineer to prepare plans and specifications for a 22-story condominium. The engineer designed the condominium so that each unit would contain its own air-conditioning system. In accordance with the design, a condensing unit was placed on the balcony of each condominium. The condensers were stacked one above the other all the way up the east side of the building. This design was less costly than a central air-conditioning system but presented a potential problem which the developer, architect, and engineer recognized early in the construction process. The heated discharged air from one condenser could rise up to the next condenser, causing the higher condenser to overload and automatically shut off.
Carrier, the air-conditioning unit manufacturer originally required in the contract specifications to supply air-conditioning units, declined the job. General Electric, a manufacturer later identified as acceptable in the specifications,1 would guarantee its units only if certain modifications were made to the condominium design. Leisure Resorts declined to incorporate those modifications into the condominium design.
Frank J. Rooney, Inc. (Rooney) and the air-conditioning subcontractor subsequently suggested, and the architect and engineer approved, the use of Frigiking Tappan units. Tappan represented that the units would operate properly under the specified conditions, but after the building was complete, occupied,
Several unit owners brought a class action against Leisure Resorts alleging a variety of construction defects, including failure of the air-conditioning units. Leisure Resorts then filed a third-party complaint against Rooney seeking contribution or indemnity for the defects Rooney allegedly caused. The third-party complaint was severed from the main action in which Leisure Resorts and the owners settled. Leisure Resorts then proceeded against Rooney for indemnity alleging that its liability to the owners was caused by Rooney‘s breach of contract, breach of warranty, or negligence.
At the close of Leisure Resorts’ case, Rooney moved for a directed verdict. The trial court granted the motion as to the developer‘s claims for breach of contract and negligence. The case then proceeded to a jury determination on Leisure Resorts’ indemnity claim for breach of the statutory warranties in
The issues for your determination on Leisure Resorts’ claim against Rooney for indemnity based on breach of warranty are whether the air conditioning equipment supplied by Rooney for the individual condominium apartments was defective within one year after substantial completion of all construction, and if so, whether such defect was a legal cause of loss or damage sustained by Leisure Resorts through no fault of Leisure Resorts.
The equipment was defective if it was not reasonably fit for the specific purpose for which it was supplied.
The jury returned a verdict in favor of Leisure Resorts and awarded the developer $250,000 in damages and $133,000 in attorney fees. Rooney appealed.
In its opinion, the district court set forth a detailed analysis of
With respect to this point, we do not approve the district court‘s decision. Rather, we assume that the legislature intended the plain and obvious meaning of the words used in the statute. See Holly v. Auld, 450 So. 2d 217 (Fla. 1984); United Bonding Insurance Co. v. Tuggle, 216 So. 2d 80 (Fla. 2d DCA 1968). Specifically, we conclude that manufactured items constitute “materials” as that term is used in
We do approve the district court‘s conclusion that the contractor‘s warranties and developer‘s warranties differ in scope. The district court noted a material distinction between the developer‘s warranty mandated by
The trial court thus erred in instructing the jury that a defect in the equipment could be found, and the contractor‘s warranty was thereby violated, if the equipment was not reasonably fit for the specific purpose for which it was supplied. The trial court‘s instruction had the effect of including in the contractor‘s warranty the design of the condominium buildings.
Having determined that the statutory warranty is applicable to the contractor in respect to the air conditioning units, it follows that a directed verdict for the contractor as to the breach of implied warranty claim would be proper only if there was no evidence upon which a jury could find that the equipment was defective. Accordingly, we reject the district court‘s conclusion that a directed verdict for the contractor with regard to the contractor‘s statutory warranty was appropriate. Here, the engineer‘s testimony regarding his study of the malfunctioning units created a jury issue as to whether the air-conditioning units conformed with generally accepted standards of performance of air-conditioning units complying with the specifications of the contract.4 That issue should be resolved by a jury instructed as to the contractor‘s warranty in accord with this opinion.
It is so ordered.
GRIMES, C.J., and OVERTON, SHAW, KOGAN and HARDING, JJ., concur.
ANSTEAD, J., recused.
Notes
(1) The developer shall be deemed to have granted the purchaser of each unit an implied warranty of fitness and merchantability for the purposes or uses intended as follows:
... .
(b) As to the personal property that is transferred with, or appurtenant to, each unit, a warranty which is for the same period as that provided by the manufacturer of the personal property, commencing with the date of closing of the purchase or the date of possession of the unit, whichever is earlier.
... .
(d) As to all other personal property for the use of the unit owners, a warranty which shall be the same as that provided by the manufacturer of the personal property.
... .
(2) The contractor, and all subcontractors and suppliers, grant to the developer and to the purchaser of each unit implied warranties of fitness as to the work performed or materials supplied by them as follows:
(a) For a period of 3 years from the date of completion of construction of a building or improvement, a warranty as to the roof and structural components of the building or improvement and mechanical and plumbing elements serving a building or improvement, except mechanical elements serving only one unit.
(b) For a period of 1 year after completion of all construction, a warranty as to all other improvements and materials.
we determined that there was a sufficient amount of recirculation around the condensing units to affect their performance. We also found that the capacity of the units under several different conditions, the conditions that were installed and all the conditions that were officially set units to test in the best possible conditions, the units did not meet the capacity that was specified on the contract drawings.... [T]he main conclusion is that the units were not performing, did not have the capacity sufficient to satisfy the contract documents even under the best conditions.
