Lead Opinion
This appeal is to reverse a judgment of the district court, wherein the State Highway Commission was enjoined from entering into a contract with a firm known as McGuire & Cavender for the construction of a highway project designated as Federal Aid Project 139.
The proceedings were begun by Green-Boots Construction Company, alleged competitive bidders for the construction work in question, but defendants in error, who were also alleged competitive bidders, were allowed to intervene, and the cause was tried upon the issues presented in their cross-petition, the issue being whether, under the statutes, time for the completion of the project is an essential item to be considered in determining the lowest bid.
Under the form- of proposals or bids furnished by the Commission, each bidder is required to name the time in which he will complete the proposed work and each bidder is authorized to name a different time for completion.
Upon the project in question, viz, the construction of 18 miles of hard-surfaced road in Logan county, only three bids were submitted, to wit: Ward-Beekman & Brooks and H. L. Canady Company proposed to complete the project in four months for $483,617.03; Green-Boots Construction Company proposed to complete it in six months for $452,918.10 (this was rejected because of some defect in the proposal) ; and McGuire & Cavender proposed to complete it in twelve months for $444,776.50.
This last bid was accepted, as the best bid, and this suit was brought to enjoin the Commission from awarding the contract to McGuire & Cavender on the grounds and with the result above stated.
The only question presented is whether the Commission should have named the time for completion and required each bidder to bid upon the same time as well as upon the same specification in other regards.
This identical question was before us and definitely passed upon, in cause No. 18405, Flynn Construction Co. v. Leininger,
The same argument is made in this case that was made in the Flynn Case, supra, and the same authorities are cited in both cases. Both the argument and authorities were carefully considered in the Flynn Case, resulting in the conclusion set forth in ihe opinion in said case. Wte find no reason in the instant case for changing the conclusion reached in the Flynn Case, nor d,o we see any necessity for additional reasoning. The statute, chapter 48, S. L. 1923 4, comtem-plates and implies competitive bidding and competitive bidding means bidding upon the same material items in the subject-matter, bidding upon the same thing, and, as was held in the Flynn Case, the statutes make time an essential element in bids upon high *116 way construction, and to permit each bidder to name a different time for completion is to violate the purpose of the statutes.
We note, however, that the record herein contains testimony intending to show that more competition and better results are obtained by requiring each bidder to name his own time than by requiring all bidders to bid upon the same time for completion. It may be a fact that more bids and better bids are now obtained than were obtained in former years, when al bidders were re-qui.ed to bid upon the same time, but the record is by no means conclusive that the better results are due to the change in the form of bids. In fact, it tends to refute the correctness of such contention, especially when we consider the manifold increase in road construction and corresponding increase in number of contractors.
Besides, when we take into consideration the expense of maintaining a detour, which in the present case is 20 miles, the interest paid by the counties on outstanding bonds while they are doing without the roads, and the inconvenience and expense to the counties and also to the general public in doing without roads already paid for, we are not sure that the bid of $444,776.50 in 12 months is a better bargain to the public than the one for $483,617.03 in four - months. And we cannot sustain the contention that the convenience of the public is immaterial. The public highways are built and maintained by the public and for the public, and when the public by paying automobile and gasoline taxes has contributed the money to build a road — in other words, when it has already paid for a road — it is entitled to have that road as soon as it can be built consistent with good business principles; hence the convenience of the public is a material matter and time of completion becomes an essential element in the matter, and the Legislature has provided accordingly. So if it were true that more bids could be obtained by disregarding the element of time and allowing each bidder to take his own time, then such fact should be presented to the Legislature rather than to the courts. Both the existing conditions and the Legislature have made time an essential element and the courts are not authorized to change the law.
While the bid in this case has been accepted as the lowest responsible bid, still no contract has been entered into, no work has been done nor material furnished for which the state should be obligated to pay, as was true in the Flynn Case, supra. No substantial detriment can result from a readvertisement for bids in conformity with the statutes. The judgment is therefore affirmed.
Dissenting Opinion
(dissenting). I dissent for two reasons:
First. I did not agee and do not now agree with that part of the Flynn Case holding that the time limit within which a road project is to be completed must be fixed by tbe Highway Commission and included in the advertisement for bids so that all contractors bid on the same time. The law, of cou.'se, places some discretion in the Highway Commission, and in my judgment a fair and liberal construction of that portion of the law providing that contracts should be let to the lowest responsible bidder and that the work should be completed in the shortest time possible consistent with good business management would require that the matter of fixing the time limit within which a project should be completed be left discretionary with the Commission. In other words, in some projects it might be advisable to fix the time limit within which the work must be completed, and in others not, this to be determined by the Commission in each particular instance in the exercise of its sound discretion. I concede, however, that this proposition is settled by the majority opinion in the Flynn Case.
Second. The record in this case shows that the bids on this project were opened by the State Highway Commission on April 12, 1927, and the contract was awarded to the successful bidder, McGuire & Cavender, on April 14, 1927.
It further appears that this work was advertised and contract awarded by the State Highway Commission under the same rules and regulations and in the same manner as the contract involved in Flynn Construction Co. v. State Highway Commission,
The contract in the instant case, as above staged was awarded on April 14, 1927, at a time when the departmental construction *117 had been in force six months longer than when the contract involved in the Flynn Case was entered into. It is true that performance of the contract in the Flynn Case was more near.y complete, but in our judgment there can be no degrees as to performance, and the amount of performance under the contract is immaterial. The successful bidder in the instant case, in order to comply with the law, was required to put up with the Highway Commission a certified check equal to five per cent, of its hid, and has therefore, for practically four months, had a sum of money in excess of $40,000 in the hands of the Highway Commission, and had necessarily held itself m readiness to proceed with the work under the contract as awarded to it, and but for the injunction granted herein would ctoub.less have had the work well under way long before now.
The authorities holding that a departmental construction of a law when upheld by the courts, become a part of the law itself, are numerous. See Murphy v. Wabash R. R. (Mo.)
I am therefore of the opinion that the Flynn Case is ample authority for holding the contract awarded herein to be a valid and binding contract, and the injunction granted by the district' court should be dissolved and this work allowed. to proceed under' the contract as awarded on April 14th without further, delay.
I am authorized to state that Mr. Justice HEFNER concurs with the views herein expressed.
