Lehmaier v. Standard Specialty & Tube Co.

108 N.Y.S. 402 | N.Y. App. Div. | 1908

Ingraham, J.:

This action'was brought to recover the damages caused by the . defendant’s breach of a contract made January 8, 1904, whereby the defendant agreed to purchase from the plaintiffs-the entire supply of metal used by it in making collapsible tubes and ketchup caps between January 8, 1904, and January 8,1907,'the metal to be rolled to the thickness required and to be satisfactory in every respect, and to refrain from selling to any one but the defendant coated metal for making collapsible tubes during the period covered by the contract.

The complaint alleges that the plaintiffs performed each and every of the terms of the agreement on their part required to he performed ; that the defendant committed a breach of the agreement in that it failed to purchase from the plaintiffs, as by the agreement it was required to do, all the metal used by it in making collapsible tubes and ketchup caps, but had on the contrary purchased the metal it used in making collapsible tubes and ketchup caps from persons, firms or corporations other than the plaintiffs.

The answer admits the making of the contract; denies that the plaintiffs performed the contract on their part; admits that the defendant purchased and used metals in making collapsible tubes from persons and corporations other than the plaintiffs, and sets up a counterclaim. Upon the trial it was proved- that the defendant commenced to take metal from the plaintiffs under the contract in March, 1904; that the defendant purchased from others than the plaintiffs during the period covered by the contract 21,765 pounds of tin which at the contract price would amount to $28,895.79, which would have been $652.95 above the market price of tin during that period; that the cost of rolling the tin would have been $103.39, malting the damage sustained by the plaintiffs by reason of the .defendant refusing to purchase the tin from the plaintiffs, under the *434contract $544.66. I do not understand that any point is made by the appellant as to the amount of damages, allowed for breach of the contract in relation .to the tin, the question arising, under the breach . in relation to the other branch of the contract for the purchase of what is called coated metal. The question' arises under the clause of the contract by which the plaintiffs were to furnish the defendant coated metal in sheets for which the defendant, was to pay seven cents per pound. It appeared that the defendant commenced the purchase of coated metal from others .than the plaintiffs on April 5, 1904, and purchased during the' year 1904 approximately 51,037 pounds ; during ■ the year .1905 approximately 102,627-^ pounds.; and during the whole period' co.yered by the contract 412,797-J pounds. It also appeared that after tlie making of the contract the plaintiffs estimated the amount ■ of lead and tin that would be required to furnish the defendant with the-' amount that it was estimated it would ■ require during the term-of. the contract at 100 tons of lead and 10 tons of tin, and purchased this amount of these metals, which they reserved for use in completing the contract.; that the defendant discontinued ordering any coated metal from the plaintiffs after March, 1904, and after January 1,1905, the plaintiffs used,'in other ways, the.lead and tin that had been purchased- and reserved to-manufacture the coated metal for.the.defendant. The plaintiffs paid fdr this tin at the rate of twenty-nine and twenty-five. one-hundredths cents per pound and for the lead four and forty-five one-hundredths cents per pound. At these prices the cost of the completed product Was estimated at 5.86-2' cents per pound, and plaintiffs were allowed to recover the- difference between this cost of the product and the amount that the defendant was to pay under the contract; namely', seven cents per pound. It further appeared that the 100 tons of lead and 10 tons of tin would have .made approximately 225,000 ■ pounds of the .coated metal. ‘ During the. year 1904 the price- of these metals remained, about the same so that when the plaintiffs used.the.lead and tin which they had purchased for this contract in their own business-the price was about the same, as that at which they had purchased it.-. After January, 1905, the price of lead advanced.. In- August, 1905, it was- four and seven-tenths cents per pound; in September, 1905, it "was four and eighty- ■ seven and one-half one-hundredths cents per pound; in October, 1905, *435it was five and one-tenth cents per pound; in November, 1905, it was five and forty-eight one-hundredths cents per pound; and in 1905 the price ranged from five and thirty-five one-hundredths cents per pound in January to six and eight-tenths cents per pound in December.

It would seem, therefore, that immediately after the contract was made the plaintiffs purchased 100 tons of lead and 10 tons of tin to be used by them' in carrying out the contract; that that amount of lead and tin would have produced 225,000 pounds of the manufactured product which would have been sufficient to supply the requirements of the defendant to May, 1906; that for any additional metal that the plaintiffs would have been required to purchase to manufacture the product they would have been compelled to pay an increased price, so that it may fairly be said that there would have been no profit in carrying out the contract. The first question relating to .the measure of damages is whether there can be said to be a total breach of the contract by the defendant in consequence of its neglect to purchase from the plaintiffs the metal that it required from time to time. I do not-think there was any total and final breach by the defendant. The defendant never refused to carry out the contract; no demand was ever made by the plaintiffs that it receive any particular amount of this metal; and there was no refusal by the defendant to comply with its contract. There was complaint made about the quality of the metal furnished by the plaintiffs, with promises by the plaintiffs to improve the quality. Both parties to the contract understood the purpose for which the metal was to be used, and the contract made was based upon that knowledge. It does not appear that metal that was satisfactory to the defendant, or that it was bound to consider as satisfactory, was ever furnished or tendered. It seems to me, therefore, that the case must be considered as if each purchase of metal by the defendant was a partial breach of its contract to purchase all the metal it required from the plaintiffs, and the plaintiffs were entitled to recover the difference between what it would have cost them to furnish each lot of metal that the defendant purchased from others and the price which they would have been entitled to receive from the defendant. If we may assume that the conduct of the defendant would have justified *436the plaintiffs in electing to consider sncli conduct as a total breach of the contract, there is no evidence of such an election; on the contrary, plaintiffs insisted -that the contract was in force; and coin-, menced this action to enforce it' as an existing contract, and it was long after the action had commenced and long after the period covered by the contract that the action was, by an amendment to the complaint, turned into am action to recover for a breach of the conJ¡má^_/íthink, therefore, that this action must be treated as having ■ been commenced after the period covered by the contract had e'xpired, with no evidence ,of a distinct refusal to perform on behalf of the defendant, no tender or demand by the plaintiffs that the defendant perform, and without evidence that at any time prior to the amendment to the complaint the plaintiffs had elected to treat the defendant’s conduct as a breach.y'This brings the case within Brown v. Muller (L. R. 7 Ex. 319) and Roper v. Johnson (L. B. 8 C. P. 167), and what ivas said in the latter case by Keating, <L, . seems to me to be the reasonable rule to apply in cases of a breach of such a contract, and-one which-affords the injured party full' ■ indemnity. “ The promisee, if he pleases, may treat the notice of intention as inoperative and await the time when the contract is to be executed, and then hold the other party responsible for all the consequences of non-performance: but in that case he keeps the contract alive for the benefit of the other party as'well' as his own ; he remains subject to all his own obligations and liabilities under it, and enables the other party not only to complete -the contract, if so advised, notwithstanding his previous repudiation of it, hut also to take advantage of any .supervening circumstances which would justify him in declining to complete it. On the other hand, the promisee may, if he thinks proper, treat the repudiation of the other party as a wrongful putting an end to the contract, and may at once bring his action as on a breach of it, and in such action he will be entitled to such damages as would have arisen from the non-performance of the 'contract at the appointed time.’ And he adds this qualification : ‘ Subject, 'however, to abatement in respect of. any circumstances which may have afforded him the means of mitigating his. loss.’ "" . * * It seems to me that, when the plaintiffs have shewn, that there has been a distinct breach of the contract on the part of the defendant, and. *437have further shewn that, at the periods at which the coal should have been delivered, they could only have obtained them at an advanced price, they were entitled to the difference between that advanced price and the contract price, unless the defendant gave evidence that another similar contract might have been obtained on more mitigated terms.” (See, also, McMaster v. State of New York, 108 N. Y. 542.)

Applying this rule the solution seems to me quite plain. What sum will indemnify the plaintiffs for the failure of the defendant to comply with its contract and purchase this metal from the plaintiffs ? Surely tlie difference in the cost of- manufacturing the metal •and the amount that the plaintiffs were to receive for it from the defendant. The plaintiffs had supplied themselves with the constituent metals necessary for the manufacture of the completed product. If the defendant had complied with its agreement the plaintiffs would have manufactured that metal thus on hand and purchased for that purpose into the coated metal and delivered it to the defendant and would, therefore, have made as profit the difference between the' cost of the product to be delivered to the defendant and what the defendant would have been required to pay for it. During the period that the metal purchased would have sufficed to supply the wants of the defendant the price of the component metals had not advanced so as to make a serious difference in the result. It seems to me that the plaintiffs were entitled to recover this difference upon the 225,000 pounds of metal that the 100 tons of lead and 10 tons oj: tin would provide; but it is also equally clear that as to the balance of the coated metal the plaintiffs could not have purchased the component metals at a price that would have yielded, any profit, and that, therefore, as to the subsequent installments the plaintiffs were entitled only to nominal damages.

Were this the only question presented I think we could reduce the damages to the amount indicated and affirm as to that amount, for on the trial the question was treated purely as a question of law, and there was no substantial dispute as to any of the facts which would have a bearing upon the ease under the construction of the contract which we have adopted. It seems to me, however, that it was error for the court below to refuse to admit evidence to show that the metal that the plaintiffs furnished was not satis*438factory to the defendant as it was not of a character suitable to manufacture these collapsible tubes for which both plaintiffs and defendían t understood that the metal was to be used. It appeared from the evidence that after the delivery of the first shipment the defendant expressed dissatisfaction with the metal, saying that the core of the metal should be slightly harder to get the best results and requesting- additional shipments as soon as possible. This letter was dated February 8, 1904. On February 20, 1904, the defendant .wrote the plaintiffs saying that the quality of the coated metal of a shipment of February twelfth was satisfactory and wished the plaintiffs would furnish the defendant the same grade. On March eleventh the defendant wrote plaintiffs that they had waited until the shipment of March fourth was received before taking the matter up in further detail, as the defendant wished to try it to determine whether it was any better than the former lots sent; that “we' find' that while it may be a little improvement, it is not yet as we think it should be, nor as good as we used when operating, our factory at New York.” The defendant then sent samples of the metal to the plaintiffs stating their objections to it, and in reply to that the plaintiffs wrote to the defendant on March twelfth, admitting- that some of the samples were unsatisfactory and closing: “.In justice to ourselves we think that you should try your very best to use up all the metal, -sent you, and we on the other hand, will do our' utmost in the way of experimenting to give you improved metal over any heretofore produced.” This was all before the first breach of the contract by the defendant. Defendant then attempted to prove the quality of this metal that had -been furnished by the plaintiffs prior to April 5, 1904, when they made their first purchase from others. This was objected to as immaterial, whereupon the defendant’s counsel stated : “ I expect to show by this witness that the coated metal furnished by the plaintiffs to the defendant was imperfect and produced bad tubes, and that it contained a number of defects, and that- the product, owing to the condition of the metal furnished, was imperfect and unsalable.” The court: “ That is the metal that you kept and paid for 1 ” Defendant’s counsel: “Yes.” The objection was then renewed by the plaintiffs and the objection sustained, and to that the defendant’s counsel éxcepted. •

*439I think this evidence should have been admitted. The answer of the defendant denied the allegation that plaintiffs had performed the contract and alleged that the metal furnished by the plaintiffs was found to be unsatisfactory in every respect and that the defendant has been at all times ready and willing to carry out said contract, but that the plaintiffs have neglected and refused to carry out the said contract on their part and have committed a breach of the contract in that they have failed to furnish the defendant the metals referred to in said complaint rolled to the thickness required and satisfactory in every respect and at the price set forth in the contract, as a counterclaim for which the defendant asked an affirmative judgment of $12,000. While I have doubts as to whether there was evidence to sustain the counterclaim, I think the evidence was competent upon the question as to whether the plaintiffs had complied with their contract and had furnished coated metal as provided for by the contract. Certainly if the plaintiffs had failed to furnish the metal contemplated by the contract suitable for the manufacture of these collapsible tubes that was reasonably satisfactory to the defendant for that' purpose, it was not a breach of the contract for the defendant to purchase from others such metal as would answer the purpose for which both' parties understood the metal was to be used. The rule contended for by the plaintiffs that an objection to the metal as not complying with the contract would not survive acceptance by the vendee has no application, as that applies only to an action for the purchase price and that the defendant has recognized by paying for the metal that was purchased. The question here is whether there was a breach of the contract by reason of the defendant purchasing the metal from others, and I think upon that question it was competent for the defendant to show that the metal furnished by the plaintiffs was not of the quality or character required by the contract, and that in consequence of the failure of the plaintiffs to furnish the coated metal that the contract required, the defendant was compelled to go out and purchase other metal in order to carry on its business. The question was as t.o whether there was a breach by the defendant, and it seems to me that there was no breach if the act of the defendant in purchasing the metal from others was made necessary by the quality of the metal that had been furnished by *440the plaintiffs, and which was of.'itself a violation of the contract by the plaintiffs. I think, this evidence should have been admitted; and it was error to exclude it.

It follows that the judgment and order must be reversed and a new trial ordered, with costs to the appellant to abide the event.

Patterson,-P. J., Laughlin, Clarke and Scott, JJ., concurred.

Judgment and order-reversed, new trial ordered, costs to appellant to abide event.

midpage