132 Va. 257 | Va. | 1922
delivered the opinion of the court.
The Virginia Steamship Company, hereafter called steamship company, recovered a judgment against the Lehigh Portland Cement Company for $7,854, and the defendant thereupon obtained a writ of error.
The material facts and circumstances out of which the litigation arose are, substantially, as follows:
On the 24th day of June, 1918, the United States government entered into a contract with F. W. Mark Construction Company, Inc., to construct and complete at the fuel-oil station at Yorktown, Va., twelve re-enforced concrete oil reservoirs, which contract contained a clause permitting the United States government to curtail the amount of the work under the contract, under cetrain conditions. The F. W. Mark Construction Company-entered into a contract with the Virginia Portland Cement Company (the predecessor of the Lehigh Portland Cement Company), to furnish it cement for this work. The steamship company had no knowledge of the terms of this contract. Afterwards, the Virginia Portland Cement Company made a contract with the steamship company to transport the cement from West Point, Va., to Yorktown, Va., the contract providing that the steamship company should unload the cars at West Point, and that the cement company was to furnish labor to unload the steamer at Yorktown.
The original contract was for the carriage of 10,000 barrels of cement, which was afterwards increased to 40,000 barrels. The. freight charge agreed upon was 16% cents per hundred pounds. This contract appears from certain letters and telegrams' filed as evidence in the case, being consummated in the letter from the steamship company to the Virginia Portland Cement Company, dated November 5, 1918.
The Virginia Portland Cement Company began the ship
In its letter of April 22, 1919, the Lehigh Portland Cement Company, acting through the same officers who had acted for the Virginia Portland Cement Company, approved a bill in favor of the steamship company and promised to send check, and from that time on made the shipments of the cement and conducted all correspondence in regard to the movement of the cement and payments for same, and made payments as per the original contract.
These officers acted for the Lehigh Portland Cement Company without explanation, and in July, 1919, wrote that they were unable to advise as to when balance of cement would be shipped, but stated that Mark Construction Company would need six to ten cars more to complete the work.
The steamship company wrote the Lehigh Portland Cement Company on July 28, 1919, that it had been informed that the shipment of the residue of the 40,000 barrels of cement to Yorktown would be discontinued, and advised it that under the terms of the contract with its predecessor (Virginia Portland Cement Company), it had a definite contract to transport 40,000 barrels, and informing the cement company that the steamship company would make claim against the Lehigh Portland Cement Company for freight on approximately 15,000 barrels which had not been hauled, 26,924 barrels having been hauled and paid for. The Lehigh Portland Cement Company replied to this letter, but did not deny that it was the successor of the Virginia Portland Cement Company, nor deny its liability for freight on the cement which had not been shipped. Its letter stated that it was not fully informed as to the suspension of the construction at Yorktown and would go into the situation in detail and communicate with the steamship company further at an early date. They failed to communicate further with the steamship company until No
Not only is the bill of particulars full enough to give the defendant notice of every item of its claim, but the notice of motion also contained a detailed statement of the plaintiff’s claimi. If the bill of particulars was insufficient, the defendant might have moved the court to reject any evidence offered by the steamship company touching any matter not described in its notice or other pleading so plainly as to give notice of its character. This it did not do, and it is manifest that the matters in evidence were plainly described in the notice of motion and bill of particulars. There is no merit in this assignment of error.
The contract between the cement company and the steamship company required the latter to transport 40,000 barrels of cement from West Point to Yorktown and to unload same from the cars and take it to Yorktown whenever the shipments arrived at West Point. The. Lehigh Portland Cement Company had informed the steamship company
The following instructions were granted by the court:
1. (Requested by the plaintiff.) “The court instructs the jury that the letters and telegrams that passed between the plaintiff and the Virginia Portland Cement Company, mentioned in the notice of motion and introduced in evidence, contain the terms' of the original contract involved in this suit; and if the jury believe from the evidence that the Lehigh Portland Cement Company afterwards succeeded to the business of the Virginia Portland Cement Company and continued to ship cement to the F. W. Mark Construction Company at Yorktown, to be carried by the plaintiff company from West Point, Va., to Yorktown, Va., and con
2. (Requested by plaintiff, amended by court.) “The court instructs the jury that if they believe from the evidence that the plaintiff made a contract with the Virginia-Portland Cement Company to carry for said company 40,-000 barrels of cement at 16% cents per cwt., as charged in the notice of motion, and that subsequently the Lehigh Portland Cement Company succeeded to the business of the Virginia Portland Cement Company and assumed and undertook to carry out said contract, but failed to carry out its part by delivering to the plaintiff for carriage by it all of the 40,000 barrels of cement and failed to pay the plaintiff all of the sum of $25,460.00, the entire contract price for such carriage, then the defendant was guilty of a violation of its contract to the extent it did not deliver to the plaintiff for carriage from West Point, Va., to Yorktown, Va., the 40,000 barrels of cement, and to the extent that it did not pay therefor at the rate of 16% cents per cwt. Provided you shall further believe from the evidence that the plaintiff was always ready and willing to perform its part of said contract.”
3. (Requested by plaintiff, amended by court.) “The coiirt instructs the jury that, should they believe from the evidence there was such a contract and breach- thereof, causing damage as charged in the notice of motion for judgment in this cause, it,-nevertheless, became incumbent upon the plaintiff to make reasonable efforts to minimize the damage done it by such breach. But this duty did not
4. (Requested by plaintiff.) “The court instructs the jury that there is no evidence in this case that either the government of the United States or the F. W. Mark Construction Company was a party to the contract; and, although the jury may believe from the evidence that the United States government canceled its contract with the F. W. Mark Construction Company, yet that fact did not release the defendant company from its contract made with the plaintiff.”
5. (Requested by defendant.) “The court instructs the jury that the burden of proof rests upon the plaintiff in this case to establish by a preponderance of the evidence the contract alleged by it, the alleged breach by the defendant, and to establish with reasonable certainty the amount of the damages actually suffered by it by reason of the alleged breach.”
6. (Given by the court.) “The court instructs the jury that in case of breach of contract, the broad general rule is that the party injured is entitled to recover all his damages, including gains prevented as well as losses sustained by reason of the breach of contract, that this rule is subject to but two conditions: The damages must be such as may fairly be supposed to have entered into contemplation of the parties when they made the contract; that is, must
“The court further instructs the jury if they should find for the plaintiff in this case, the measure of damages is the value of the bargain to the plaintiff or the loss which the fulfillment would have prevented or which the breach has entailed, the intent of the law is to put the injured party, so far as can be done by money, in the same position as if the contract had been performed; therefore, the measure of damages for the breach of such a contract as that sued upon in this case is the difference between the contract price remaining unpaid and the cost of delivery.”
The following instructions were refused by the court:
“Certificate No. II.—The court instructs the jury that if they believe from the evidence that at the time this contract was entered into both parties thereto assumed under all the circumstances and conditions then existing, as the basis of their agreement, even though not expressly provided in their contract, the continuance of the government work at Yorktown for which the cement was to be furnished, and that it may be fairly implied that both parties assumed that the performance of their contract was based upon the continued existence of this government work, and that this work was discontinued by the government without fault on the part of the defendant, then the court instructs the jury that there has been no breach of this contract for which the defendant is liable to the plaintiff, and they should find for the defendant.”
“Certificate No. III.—The court instructs the jury that if they believe from the evidence that the defendant in this case violated the contract existing between it and the plaintiff without excuse for so doing, as is explained in instruction No. —, they must find for the plaintiff, and that the measure of damages is the difference between the con*267 tract price remaining unpaid, to-wit: $8,354.00, and the cost the plaintiff would have been put to in performing the contract, and that in estimating this cost they must take into consideration the length of time it would have required the plaintiffs to haul the cement remaining undelivered under the terms of the contract, the costs and expenses of operating the boat during this time, including the salaries of officers, the wages of the crew, the cost of feeding the crew, fuel, sundry expenses, insurance, interest charges, loss and damage and taxes, but in so doing the jury are instructed that they must apportion such expenses between the transportation of the unshipped cement and the other business done by the plaintiff during the said period.”
“The court further instructs the jury that the evidence of the said costs and expenses during the period in which the plaintiff was engaged from September 1, 1918, to July 28, 1919, in hauling the cement delivered to it under the contract, may be considered by it in arriving at the plaintiff’s costs and expenses in transporting the undelivered portion of the cement.”
“Certificate No. IV.—The court instructs the jury that should they find for the plaintiff, then the measure of its damages is the difference between the contract price for carrying the cement remaining unpaid and the additional cost it would have been put to had it actually carried the cement, instead of lying at the wharf ready and waiting to carry, provided you shall believe from the evidence that such was the case.”
In L. R. A. 1916F, at page 48, it is said: “The rule appears to be that if one undertakes unconditionally to perform an act which is not inherently impossible, but merely requires the acquiescence or consent of a third party, or the performance of a preceding act by the latter, the nonperformance is not ordinarily excused by the fact that it subsequently proves impossible for the promisor to com
In Dannenhower v. Hayes, 35 App. D. C., at page 57, 33 L. R. A. (N. S.), at page 702, this is stated: “This is simply a case of the appellant’s undertaking to do a perfectly lawful thing which he was unable to perform. Such contracts, in the absence of fraud, are enforceable. In 2 Parsons on Contracts, page 673, it is said: Tf one, for a valid consideration, promises another to do that which is, in fact, impossible, but the promise is not obtained by actual or constructive fraud and is not on its face obviously impossible, there seems no reason why the promisor should not be held to. pay damages' for the breach of the contract; not, in fact, for not doing what cannot be done, but for undertaking and promising to do it (cases cited). So, if it becomes impossible by contingencies which should have been foreseen and provided against in the contract, and still more, if they might have been prevented, the promisor should be held responsible. So, if the impossibility applies to the promisor personally, there being no natural impossibility in the thing, this will not be a sufficient excuse.’ Such contracts, when fairly and honestly made, are enforceable.”
To the same effect is Van Etten v. Newton, 15 Daly 542, 29 N. Y. S. R. 411, 8 N. Y. Supp. 478, and Cobb v. Harmon, 23 N. Y. 148.
In L. R. A. 1916F, page 31, it is said: “It is well
In 6 Ruling Case Law, page 1014, section 375, we find this: “Act of third party.-—Generally speaking, it may be said that where a party undertakes expressly for the performance of some act, his positive engagement casts upon him a duty, the discharge of which cannot be excused by showing his inability by reason of the lawful interfer-. ence of some third person. By neglecting to qualify his contract, so as to make such an excuse available, he waives it as a defense against a recovery of damages for nonperformance. * * * A promise may, of course, be conditioned upon the act or consent of a third person. But the performance of an absolute promise is not excused by the fact that a third person refuses or fails to take action essential to performance * * * The nonperformance of a contract ordinarily is not excused by the mere fact that the promisor has no control over the third person.”
The plaintiff in error relies with great earnestness upon the principles of law enunciated in the case of Virginia Iron Co. v. Graham, 124 Va., pp. 700, et seq., 98 S. E. 659, as being applicable to the facts in the instant case. But
In the Graham Case, which involved a mining contract, the foundation of the contract was the existence of sufficient iron ore to justify the operations of the mines for forty years, and both parties assumed its existence and contracted with reference thereto.
When it appeared that the ore did not exist it was clear that each party had entered into the contract under a mistake of fact which affected the substance of the contract and the contract became inoperative for a failure of the consideration, and the lessee was plainly entitled to be relieved from the payment of the royalty provided for in the lease.
In view of the foregoing authorities, wo find no error in the action of the court in granting or refusing instructions, of which the plaintiff in error can complain.
Nor can we sustain the defense of the plaintiff in error that it was and is now discharged and excused from performance of the contract because of supervening impossibility of performance and frustration of adventure by the act of the United States government in canceling its contract with F. W. Mark Construction Company, Inc.
The government was not a party to the contract sued on, and its action in curtailing the work at Yorktown simply destroyed the demand for cement at that place, without making the transportation of the cement impossible.
The steamship company, having no knowledge of the terms of the contract between the government and the F. W. Mark Construction Company, it is apparent that the continuance of the work upon the cement reservoirs at Yorktown to final completion was not the basis and implied condition upon which the liability of the parties to perform the contract sued on rested.
The failure of the cement company to release it from the contract prevented the steamship company from seeking other business.
Only fuel and oil were saved while the boat was idle, and it is in evidence that the fuel and oil used in making the
The plaintiff’s claim was for $8,354.00, with interest from August 11, 1919, making a total claim of $9,019.54, the day the verdict was rendered, while the jury returned a verdict for only $7,854.00, without interest, showing they deducted for expenses over $1,100.00.
In view of the evidence, we cannot say the damages are excessive.
For the foregoing reasons, we find no error in the rulings of the trial court, or in the judgment under review, and the case will be affirmed.
Affirmed.