We reverse the final judgment in favor of appellee on its breach of contract claim. First, we find that the record does not support appellee’s claims of substantial compliance. Because time was “of the essence” in the post-closing agreement, ap-pellee’s failure to complete construction of RCA Boulevard by the deadline in the contract constituted a material breach. Sublime, Inc. v. Boardman’s Inc.,
We also reverse the trial court’s finding that appellant was not entitled to the Seacoast connection fee credit. We review de novo the trial court’s interpretation of the post-closing agreement. See Detroit Diesel Corp. v. Atl. Mut. Ins. Co.,
Reversed and remanded.