42 Minn. 414 | Minn. | 1890
Defendant Little, being the owner of the land described in the complaint, in August, 1887, entered into a contract with defendant Stalbird for the erection of a dwelling-house on the premises. Stalbird then entered into a contract in writing (Exhibit B) with plaintiffs, by which the latter agreed “to furnish and lay the tile on the house according to the plans and specifications by L. S. Buffington, using shingle tile for the sides, and Spanish tile for roof; also finials and crestings for ridges; for the sum of $2,100. Terms, spot cash on completion of job.” The plaintiffs, claiming to have performed their contract, and not having received their pay from Stalbird, in September, 1888, filed their affidavit and statement for a lien, to which was annexed a copy of the written contract between them and Stalbird. To an action to enforce this lien Little interposed two defences:' First, that plaintiffs had not filed a properly itemized account of the labor and material, as required by Gen. St. 1878, c. 90, § 6; and, second, that they had. not fulfilled their contract.
2. A careful inspection of the answer satisfies us that the second defence tenders no issue as to the quality of plaintiffs’ work, but merely charges a failure on their part to complete the roof within the time agreed, (alleged to have been November 1, 1887,) by reason of which certain damages resulted to defendant. The eourt finds that no time was agreed on when the .work should be completed, in which case, of course, the law implies a reasonable time. The court further finds that the plaintiffs entered upon the performance of their contract October 15, 1887, and prosequted work thereunder and thereon until June 16, 1888, at which time they had fully corfipleted it. In the absence of the evidence on the question, and of any find
This would be decisive of the case in favor of the plaintiffs; but if it be assumed that the parties, voluntarily and outside of the pleadings, tried issues as to the quality of the work, the same result is reached. The only provision in the specifications referred to in Exhibit B, as to the manner of laying the tile, is that they shall be “all laid in proper manner.” The only objection made to the manner of laying the tile' on the roof is that they were not laid in cement. The, finding of the court is to the effect that, at the time this contract waffmade and this work done, cement had never been used in this locality in laying tile, but they had been uniformly laid on felt, without-cement, although tile laid in cement make a better roof than when-laid without it. While this, like many of the findings, is rather a. summary of the evidence than a finding on an issuable fact, yet, as-contracts are presumed to be made with reference to the general customs and usages of trade and business, it must be construed as equivalent to a finding that the roof tile was laid in a proper manner. To the suggestion that the specifications provide that the work was to be done to the satisfaction of the architect and the owner, and that the defendant objected to the tile being laid without cement, it is enough to say that, even conceding that, this would give the own’erthe right to exact’ a method of doing the work different from that expressed or implied by the contract, no such thing is pleaded, or even suggested, in the answer. Lautenschlager v. Hunter, 22 Minn. 267. This disposes of the objection to the roof.
As to the tile on the sides of the house, the court finds that they were improperly laid on, without being fastened-properly, so that some of them fell off; but that there was no evidence tending to prove what it would cost to take off and repláce them in a proper manner, or in any way fixing the amount of damage sustained by reason of these tile not having been properly put on. Defendant’s contention is that, plaintiffs’ "contract being an entirety, they to be paid a gross sum on completion of the job, they cannot recover on the contract until it has been fully performed in all respects; that,
The question what, if anything, a contractor, who has in some respect failed to completely perform his contract according to all its provisions, may recover, and whether upon the contract or on a quantum meruit, is one of some difficulty, and which has given rise to some diversity of judicial decision, especially in the case of building contracts, or others where the party has expended labor and material upon the land of another which cannot be returned to him, but which the owner of the land must necessarily retain and have the benefit of. In some states, such as Massachusetts and New Hampshire, the courts have adopted what is sometimes called the modern equitable rule, that the party who has the possession and enjoyment of the labor and materials of another must make compensation for what, he has received, after full allowance has been made to him for any damage he may have sustained by the non-performance of the contract in its entirety. Hayward v. Leonard, 7 Pick. 181; Smith v. First Cong., etc., 8 Pick. 178; Cullen v. Sears, 112 Mass. 299, 308; Britton v. Turner, 6 N. H. 481. In other states, like New York, a more rigid rule has been adopted, founded upon the policy of securing full and faithful performance of contracts, and of discouraging parties from abandoning their contracts or executing them as their interest or caprice may dictate. Smith v. Brady, 17 N. Y. 173. The severity of the rule has, however, been much relaxed in subsequent cases in that state, under a very liberal application of the doctrine of “substantial performance.” Glacius v. Black, 50 N. Y. 145; Johnson v. De Peyster, Id. 666; Phillip v. Gallant, 62 N. Y. 256; Woodward v. Fuller, 80 N. Y. 312; Heckman v. Pinkney, 81 N. Y. 211.
Without now considering or deciding in what cases, if any, a party who has not substantially performed his contract in its entirety may
In the case at bar no objection is made to the quality of the tile. The only defect is in the manner of fastening those placed on the sides of the house. That this is a defect easily remedied is apparent from its intrinsic character. How many there are of these tile, or how much it would cost to fasten them properly, does not appear. They may be very few in number, and the cost of remedying the defect may be very trifling. Under 'the circumstances, taking all the findings of the trial court together, we think they must be construed as in effect finding that, notwithstanding the defect referred to, there had been a substantial performance of the contract by plaintiffs. Hence, under the rule already announced, it was for the defendant to prove the amount, if anything, which he was entitled to have deducted from the contract price on account .of the defect complained of.
Judgment affirmed.