26 Pa. Super. 405 | Pa. Super. Ct. | 1904
Opinion by
When this case was here last year, 22 Pa. Superior Ct. 564, the judgment was reversed upon the ground that:
“The trial judge in the court below tried the case upon the theory that the cancelation of the original agreement having been made in good faith, for the purpose of making a new agreement, under which it would be possible to borrow money for the completion of the buildings, and a stipulation for (against) liens having been made part of the new agreement, and it having been recorded within the ten days required by the act of assembly, all parties furnishing material upon the faith of the building subsequently to that date were bound by the stipulation therein contained, unless it were shown affirmatively that the latter agreement was fraudulent and collusive and entered into for the purpose of cheating some one, and instructed the jury that there was no evidence that the said contract was made for that purpose.” In reference to that we said:
“ This view of the case was entirely erroneous. It was not a question of fraud or collusion. The motive which influenced the parties to the contract did not properly enter into the consideration of the case. It was a question of the legal right of the defendant owners and the defendant contractor to enter into a contract, after the building had .been commenced and partially completed, to make a valid stipulation against liens,” etc.
This was the main ground upon which the case was reversed. It is true that, in the consideration of the case, we assumed
The question raised by the present record was not before us in the former case and was not considered. The principal question here is raised by the first assignment of error which relates to the rejection of defendant’s offer of testimony, as follows:
“ Defendants’ counsel: We propose to prove by the witness on the stand, that he is the John W. Zimmerman, agent, who executed the first contract dated August 11, 1897, for the construction and erection of the buildings in question. We further propose to prove that in pursuance of said contract he proceeded with the work up to about the 7th or 8th of September, 1897, when the work was stopped and a new contract made. That prior to September 7, 1897, the witness had a conversation with George F. Lee, one of the plaintiffs in this action, prior to the order upon which this lien is based. That in the course of the said conversation, George F. Lee requested Zimmerman, the witness, to purchase the supplies and material for said building from his firm, to wit: Lee and Scouton. That George F. Lee, further, in the course of said conversation, agreed to supply the witness with sufficient funds to pay off all liabilities incurred by him for labor and material up to that date in and about the construction of the Owens and Williams building, so that the firm of Lee and Scouton might obtain the orders for furnishing the balance of the material necessary for the completing of the buildings, said money to be used in obtaining releases from those who had already furnished material or labor, so that a new contract could be made containing a stipulation against liens. That at that time, to wit: during this conversation, which occurred prior to the time the goods were ordered, upon which this lien was based, the witness notified George F. Lee that he was about to or had already entered into a contract with the defendants, which contract contained a stipulation against the filing of mechanics’ liens, and that said contract had been or was about to be filed of
“ This to he followed further by the testimony of this witness that no goods or material were ordered or supplied to the buildings in question by the firm of Lee and Scouton, the plaintiffs in this case, until said contract and stipulation had been filed as above stated, and until a week or more had elapsed after the said filing, and about two weeks after the plaintiffs had received actual notice, as above stated, from the Avitness that such a contract had been or Avas about to be made and had been or was about to be filed.”
After objection, the defendant added to his offer as follows:
“ Defendants’ counsel: The defendant further proposes to prove by the Avitness on the stand that the contract dated September 9,1897, between John W. Zimmerman, agent, and James E. Zimmerman, principal, and the defendants in this case, Avas reduced to writing, signed by the parties thereto, filed in the prothonotary’s office of the county of Luzerne, in Avliich the land in question lies, within ten days after its execution, and before Zimmerman, the principal contractor, Avas authorized to proceed with said work under said contract, to Avit: the contract of September 9, 1897.”
The objections were renewed and sustained and we are, therefore, to consider whether or not the testimony offered should have been admitted.
The question for consideration practically comes to this: Is a material man a subcontractor after a building has been commenced, under a contract between the owners and the contractor containing no stipulation against liens, from whom no material has been ordered and who has furnished none, which contract has been canceled by the parties thereto, bound by the provisions of a second contract containing a stipulation against liens, of which he has actual notice and Avhich is filed in the
If the defendants’ testimony rises to the height of their offer, this question would be fairly raised and, as we are bound to accept the offer as verity, we must deal with it, so far as the case now before us is concerned, as if the testimony would be equivalent to the offer; We are unable to see, under such circumstances, why an issue of fact would not be raised which must go to a jury. Whatever may be our opinion of this offer, in view of the manner in which it is made and of the testimony in the former case, we feel bound to say that, if the facts therein offered to be proved are clearly shown, it will be for a jury to pass upon the credibility of the witnesses and the other facts in the case upon which their testimony is based, under careful instructions from the court as to the relative value of the evidence adduced by the plaintiffs and defendants respectively.
The second assignment of error relates to a similar offer to be proved by another witness.
It follows that if the defendants make good their offer, the case is not one for binding instructions but must go to the jury, as already intimated, under proper instructions.
Judgment reversed and a new venire awarded.